Public Hearing - February 27, 2013

    


       1      JOINT HEARING BEFORE THE NEW YORK STATE
              SENATE STANDING COMMITTEE ON INVESTIGATIONS AND
       2      GOVERNMENT OPERATIONS
              AND
       3      SENATE STANDING COMMITTEE ON CORPORATIONS, AUTHORITIES,
              AND COMMISSIONS
       4
              --------------------------------------------------------
       5                          PUBLIC HEARING

       6        TO EXAMINE THE BEST COURSE OF ACTION TO ENSURE THE
               RESIDENTS OF LONG ISLAND RECEIVE THE ELECTRICAL AND
       7      CUSTOMER SERVICE THAT THEY DESERVE AT AFFORDABLE PRICES

       8      --------------------------------------------------------

       9                       Van Buren Hearing Room A, 2nd Floor
                               Legislative Office Building
      10                       Albany, New York

      11                       February 27, 2013
                               11:00 a.m. to 3:30 p.m.
      12
              PRESIDING:
      13
                 Senator Carl L. Marcellino
      14         Chairman
                 NYS Senate Standing Committee on
      15         Investigations and Governmental Operations

      16         Senator Michael H. Ranzenhofer
                 Chairman
      17         NYS Senate Standing Committee on
                 Corporations, Authorities, and Commissions
      18
              SENATE MEMBERS PRESENT:
      19
                 Senator Brad Hoylman (RM)
      20
                 Senator Ruben Diaz
      21
                 Senator John J. Flanagan
      22
                 Senator Kenneth P. LaValle
      23
                 Senator Bill Perkins
      24
                 Senator Lee M. Zeldin
      25







                                                                   2
       1
              ASSEMBLY MEMBERS PRESENT:
       2
                 Assemblyman Alfred C. Graf
       3
                 Assemblyman Chad Lupinacci
       4
                 Assemblyman David G. McDonough
       5
                 Assemblyman Michael A. Montesano
       6
                 Assemblyman Andrew P. Raia
       7

       8      ALSO IN ATTENDANCE (in the audience):

       9         Senator Philip M. Boyle

      10

      11

      12

      13

      14

      15

      16

      17

      18

      19

      20

      21

      22

      23

      24

      25







                                                                   3
       1
              SPEAKERS:                               PAGE  QUESTIONS
       2
              Regina Calcaterra                         11      26
       3      Executive Director
              The Moreland Commission on
       4           Utility Storm Preparation & Response

       5      Gil C. Quiniones                          11      26
              President and CEO
       6      New York Power Authority

       7      Robert F. Lurie                           11      26
              Senior VP of Strategic Planning
       8      New York Power Authority

       9      David Daly                                91     118
              Vice President, LIPA Transition
      10      Public Service Enterprise Group

      11      Neal Lewis                                91     118
              Board Member
      12      Long Island Power Authority
                   Appearing as an appointed
      13           volunteer member of the
                   LIPA Board of Trustees
      14
              Shelly Sackstein                         161     186
      15      Chairman and CEO
              Action Long Island
      16           Also, Chairman of Suffolk County
                   LIPA Oversight Committee
      17           Also, Former Board of Trustee, LIPA

      18      Cynthia Kouril, Esq.                     161     186
              Former Counsel, Inspector General for
      19      NYC Dept. of Environmental Protection;
                   Former Special Assistant,
      20           U.S. Attorney General,
                   Southern District of NY
      21
              Donald J. Daley, Jr.                     200     217
      22      Business Manager
              International Brotherhood of
      23           Electrical Workers, Local 1049

      24

      25







                                                                   4
       1
              SPEAKERS:                               PAGE  QUESTIONS
       2
              Tom Rumsey                               200     217
       3      Vice President of External Affairs
              New York Independent System Operator
       4
              Rick Gonzales                            200     217
       5      Sr. Vice President and
                   Chief Operating Officer
       6      New York Independent System Operator

       7      Charles Bell                             221     229
              Programs Director
       8      Consumer Union

       9      Elizabeth Horan                          221     229
              Volunteer
      10      AARP-New York

      11      Bill Ferris                              221     229
              State Legislative Representative
      12      AARP-New York

      13

      14                             * * * * *

      15

      16

      17

      18

      19

      20

      21

      22

      23

      24

      25







                                                                   5
       1             SENATOR MARCELLINO:  Good morning.

       2             If we could take our seats, please.

       3             Good morning, ladies and gentlemen.

       4             My name is Senator Carl Marcellino, and I am

       5      the Chairman of the New York State Senate -- Senate

       6      Committee on Investigations and Government

       7      Operations.

       8             Sitting to my right is

       9      Senator Mike Ranzenhofer, who is the Chairman of the

      10      Corporations, Authorities, and Commissions Committee

      11      in the New York State Senate.

      12             We are joined by our colleagues:

      13             To my left, Senator Ken LaValle,

      14      Senator Lee Zeldin;

      15             And to our right, Assemblyman Dave McDonough,

      16      Assemblyman Graf, and Assemblyman Montesano.

      17             We are here for a hearing, a joint public

      18      hearing, on, basically, the future of LIPA; the

      19      Long Island Power Authority.

      20             Governor Cuomo has made the decision -- his

      21      desire clear that he would like to see a change in

      22      the structure of LIPA.

      23             Excuse me.  There may come a time when I have

      24      to pull a "Rubio," so --

      25                  [Laughter.]







                                                                   6
       1             SENATOR MARCELLINO:  Hopefully, I can get the

       2      water a little closer than lurching for it.

       3             But, he's made his desire clear to see a

       4      change in the structure of LIPA.

       5             He's not happy with the way it performed in

       6      the aftermath, and during "Superstorm Sandy," and he

       7      would like to see some kind of a change.

       8             To that end, he is seated a

       9      Moreland Commission to do a study for the Executive.

      10             Our two committees are going to do a joint

      11      study, and issue a report at the end of this

      12      hearing, and after we get in some other written

      13      testimony that we expect, to issue a report of our

      14      own and make some recommendations to the

      15      Legislature.

      16             Hopefully, between the Executive and the

      17      Legislature, we can come up with a position that is

      18      in the best interests of the ratepayers, within the

      19      LIPA perspective, which is, basically, Long Island

      20      and Queens.

      21             I don't believe areas -- I don't think it

      22      goes into Brooklyn.

      23             No, I don't believe so.

      24             So, we are -- we are looking to take

      25      testimony today from the people, we have panels,







                                                                   7
       1      that are seated.

       2             And paperwork is at the top of the floor

       3      there.  If you didn't get a list of the people who

       4      are seated, who are going to be testifying today,

       5      you can pick it up.  That's for your avail.

       6             This will be taped.  A video replay of this,

       7      if you want to have good sleeping at night, a good

       8      retape and a replay will be on the Senate

       9      Investigations Committee website, the Senate website

      10      as well, so that you can watch this.

      11             This is being broadcast live on the Senate

      12      channel and the Senate Investigations Committee

      13      website.

      14             You can also go to my own personal Senate

      15      website and you can see it as well.

      16             So, we'll replay this for the public so

      17      anybody can hear it.

      18             We have received written testimony from many

      19      individuals and groups who wanted to do so, and,

      20      testimony has been by invitation only.

      21             We are concerned as to the complexity of the

      22      issue, and it is an extremely complicated issue.

      23             Lots of interrelated issues come into play,

      24      not the least of which is, what to do, and how to

      25      deal with the Shoreham debt, and what's going to







                                                                   8
       1      happen with that, that problem.  That's the

       2      800-pound gorilla that sits out there and affects

       3      the ratepayers most.

       4             So we are particularly interested in seeing

       5      how we -- how this group is going to recommend, and

       6      what we're going to do to handle that, and what are

       7      the recommendations, and how that's going to be

       8      dealt with.

       9             I see that we've been joined with

      10      Assemblyman Raia from Long Island.

      11             We have, as I said, written testimony.

      12             I would appreciate it if the people

      13      testifying wouldn't read their statements.

      14             They don't have to, we have the written

      15      testimony.

      16             Last I looked, everybody up here could read,

      17      and we will be happy to go through this and read it

      18      as well, but we'd like as much time as possible for

      19      questions of the panels, as they go forward.

      20             So that issue being done,

      21      Senator Ranzenhofer, do you have any comments?

      22             SENATOR RANZENHOFER:  Yes, thank you.

      23             Thank you, Senator Marcellino.

      24             My name is Mike Ranzenhofer.  I am the

      25      Chairman of the Standing Committee on Corporations,







                                                                   9
       1      Authorities, and Commissions, and co-hosting this

       2      public hearing with Senator Marcellino.

       3             And, Senator Marcellino, I want to thank you,

       4      and your staff, for your leadership in convening

       5      this very important meeting today.

       6             I also want to thank those who are going to

       7      be appearing before us today at this public hearing,

       8      for their time and thoughts and effort putting

       9      together the written statements, and for being here

      10      today and testifying.

      11             And for also those who are here in the

      12      audience, and then watching this on television.

      13             This is a very important issue for the

      14      ratepayers in this geographical area.

      15             As Senator Marcellino said, this is a very

      16      complex and complicated area; basically, proposing

      17      changes in a structure that's been existing for some

      18      time.

      19             So, I also look forward to hearing from the

      20      participants today.

      21             And, Senator Marcellino, again, thank you for

      22      your leadership on this issue.

      23             SENATOR MARCELLINO:  Any of my colleagues?

      24             Senator LaValle?

      25             SENATOR LAVALLE:  No.







                                                                   10
       1             SENATOR MARCELLINO:  Anybody else want to

       2      make -- any statement you'd like to make?

       3             Okay, with that, just a quick background.

       4             LIPA was created to deal with, as I said, the

       5      Shoreham debt, replacing the Long Island Lighting

       6      Company (LILCO) that preceded it.

       7             It is a holding company, in effect.  It is a

       8      State authority; hence my colleague's involvement in

       9      this hearing.

      10             It has a total of about 100 employees.

      11             When you see trucks on Long Island, riding

      12      around, and it says "LIPA" on it, and you see a crew

      13      in those trucks, more than likely that crew are

      14      employees of National Grid, because National Grid is

      15      the company that provides the services and provides

      16      the -- the repairs, and does all the repair work and

      17      maintains the system.  They also own the power

      18      plants.

      19             LIPA owns the lines that bring the power from

      20      the power plants to your home, and from the top of

      21      the mast, which is that thing that reaches up above

      22      your house and connects to your meter, that's the

      23      personal property of the ratepayer, the homeowner.

      24             So, you own, from your house, from your meter

      25      to the top of the mast.







                                                                   11
       1             LIPA controls, from the mast to the

       2      transformers, to the power plant, and Grid owns the

       3      power plants.

       4             Now, to add to the complexity of this, in

       5      2013, we're changing.

       6             National Grid will be replaced.  The contract

       7      with National Grid will be changed and altered, and

       8      we'll be taking on PSE&G, which is a company from

       9      New Jersey.

      10             They're gonna be replacing Grid, and

      11      providing the service for our customers and the

      12      maintenance of the system.

      13             However, Grid, to my knowledge, will still

      14      own the power plants, unless some deal was made

      15      between PSE&G and National Grid so that PSE&G could

      16      buy the power plants.

      17             So, as you can see, this is not exactly

      18      simple.  This becomes even more calculated and more

      19      complicated as we move on.

      20             But, we will move on.

      21             So with that background in mind, I would like

      22      to introduce our first panel.

      23             We have Ms. Regina Calcaterra, executive

      24      director of the Moreland Commission on Utility Storm

      25      Preparation and Response, chaired by -- set up by







                                                                   12
       1      Governor Cuomo;

       2             We have Gil Quiniones, president and

       3      chief executive of the New York Power Authority;

       4             And Robert Lurie, senior vice president of

       5      strategic planning for the New York Power Authority.

       6             Ms. Calcaterra, I understand you're going

       7      first.

       8             REGINA CALCATERRA:  Thank you.

       9             Good morning, Chairman Marcellino, and

      10      Ranzenhofer, and members of the Committee.

      11             I am Regina Calcaterra, executive director of

      12      the New York State Moreland Commission on Utility

      13      Storm Preparation and Response.

      14             I appreciate this opportunity to discuss the

      15      commission's investigation and findings concerning

      16      LIPA's response to "Superstorm Sandy," and the

      17      options of how best to structure LIPA, going

      18      forward.

      19             The commission has conducted an investigation

      20      that solicited a broad spectrum of views and

      21      experiences associated with LIPA, from the public,

      22      industry experts, business owners, and

      23      representatives who represent critical

      24      infrastructure entities, as well as from LIPA

      25      personnel, National Grid personnel, and local







                                                                   13
       1      government officials.

       2             The commission focused first on, among many

       3      things, the serious shortcomings in LIPA's recovery

       4      from "Sandy," and whether its current structure

       5      contributed to those shortcomings.

       6             The commission's findings and recommendation

       7      in this respect were presented in the interim report

       8      which was submitted on January 7th, and the two

       9      findings just related to LIPA determined that the

      10      ineffective manner in which LIPA addresses

      11      emergency-planning preparedness and storm response

      12      in its service area, and it also addressed the

      13      inherent defects in the current LIPA-National Grid

      14      structure that must be avoided in any future

      15      alternative organizational structure that are being

      16      considered.

      17             The interim report provides sufficient

      18      evidence that LIPA's outsourcing of most of the

      19      day-to-day management and operations of its system

      20      to National Grid just does not work.

      21             In short, the bifurcated LIPA-National Grid

      22      structure lends itself to mismanagement, a lack of

      23      appropriate investment in infrastructure, a lack of

      24      accountability to customers, and excessive rates.

      25             The commission recommended consideration of a







                                                                   14
       1      unified structure that both owns the T&D assets and

       2      is entirely responsible for serving LIPA's current

       3      service area.

       4             In this respect, the commission identified

       5      three options for consideration:

       6             The first, is the sale of LIPA's assets to a

       7      qualified investor-owned utility that would serve as

       8      the sole utility manager and operating -- an

       9      operator to the existing LIPA service area;

      10             The second option, is full public ownership

      11      in operations by LIPA of the transmission and

      12      distribution systems;

      13             The third option, was full public ownership

      14      and operation by the New York Power Authority of the

      15      LIPA electric system.

      16             For the purposes of this testimony, I'm going

      17      to highlight a significant flaw associated with the

      18      management-service agreements between LIPA and

      19      National Grid, which is set to expire on

      20      December 31, 2013.

      21             This agreement has been set in place --

      22      there's been an MSA continuing between LIPA and

      23      whoever it was that has been operating their system

      24      for years, and it's changed hands over time.

      25             And the present agreement is between LIPA and







                                                                   15
       1      National Grid -- LIPA as the owner, National Grid as

       2      the operator of the system -- so their roles are

       3      delineated in this agreement.

       4             And National Grid has three primary roles:

       5             The first, is to operate and maintain the

       6      T&D system;

       7             The third, is to repair the T&D system -- the

       8      second, is to repair T&D system;

       9             And the third, is to provide customer

      10      service.

      11             And they do these three major functions with

      12      over 2,000 employees on Long Island.

      13             And LIPA's role is also defined in this

      14      agreement as well, but they're non-core functions as

      15      opposed to what National Grid does.

      16             And what their role is, to set the rates, to

      17      determine and implement energy-efficiency programs,

      18      to create a budget, to issue debt, and provide legal

      19      compliance.

      20             So it's very distinct what LIPA does with its

      21      100 employees, and what National Grid does with its

      22      2,000 employees.

      23             So while National Grid assumed responsibility

      24      for day-to-day operations in what we call "blue sky"

      25      conditions -- when things are normal -- LIPA







                                                                   16
       1      specifically retained the ultimate authority in

       2      control over the operations of the T&D system,

       3      including the right to direct the manager in

       4      connection with the manager's obligation under the

       5      MSA.

       6             And what this resulted in, was a problem

       7      during an emergency, because in the event of an

       8      emergency, LIPA even retains the right to take

       9      possession of and use any or all of National Grid's

      10      staff and resources, and directly manage them, even

      11      though they don't do that on a day-to-day basis.

      12             The commission has determined that the unique

      13      relationship between LIPA and National Grid leads to

      14      public confusion about the provision of customer and

      15      operational service related to the fact that

      16      operations are delegated to National Grid, while

      17      operational oversight and approval powers are vested

      18      in LIPA.

      19             The relationship has been particularly

      20      ineffective in the context of storm response.

      21             As an example of the problem, the MSA between

      22      LIPA and National Grid specifies, that:

      23             "During a storm event, National Grid shall be

      24      relieved of any of its obligations to comply with

      25      the performance metric, and such compliance shall







                                                                   17
       1      not constitute an event of a default to the extent

       2      and for any period during which the operation of the

       3      T&D system is affected."

       4             In other words, during a storm, National Grid

       5      has no performance metrics to follow.  And if they

       6      fail to do what they need to do, they're not in

       7      breach of contract.

       8             Thus, LIPA, with its strong brand identity

       9      and exclusive financial responsibility, has only two

      10      choices in the context of a storm:

      11             They could accept zero control over

      12      National Grid's performance, due to a lack of a

      13      penalizing metric, or, take 100 percent control

      14      through its contract emergency powers, which is what

      15      they did in "Superstorm Sandy."

      16             Obviously, neither of these are optimum

      17      choices.

      18             Indeed, based on the testimony taken during

      19      the investigation, as well as the relevant review of

      20      documentation, the commission concluded that the

      21      lack of appropriate contract controls and the

      22      bifurcated structure between LIPA and National Grid

      23      were largely responsible for the ineffective storm

      24      response.

      25             And the interim report, as you know, is over







                                                                   18
       1      50 pages, the majority of which does cover the LIPA

       2      investigation.  And there are several examples there

       3      of the challenges that the bifurcated structure

       4      between LIPA and National Grid creates.

       5             I just highlighted one of them in

       6      relationship to a storm because this is what brought

       7      us here today.

       8             Without getting into much detail, the

       9      commission also found that these same problems

      10      caused much of the ineffective day-to-day operations

      11      of the LIPA-National Grid structure.

      12             Restructuring the Long Island electric

      13      utility service:

      14             What the Moreland Commission did within the

      15      short amount of time, while we were preparing the

      16      interim report, was also take a look at a variety of

      17      options, because you could sit there and you could

      18      determine what the problem was, but it's also

      19      constructive if you take a look at options, and

      20      possibly make a recommendation, which is what the

      21      Moreland Commission did.

      22             The commission considered three options as

      23      possible longer-term remedies for the current

      24      inadequacy of the LIPA structure, as I mentioned

      25      earlier:  LIPA privatization, full public ownership







                                                                   19
       1      under LIPA, or public ownership under NYPA.

       2             A majority of commission members recommended

       3      privatization.

       4             The commission identified potentially

       5      millions of dollars in synergy benefits that could

       6      be achieved in privatization to offset privatization

       7      costs, including efficiencies in the areas of

       8      operating and maintenance costs, power supply, fuels

       9      management, and contractor fees.

      10             Importantly, under this option, the new

      11      utility would be subject to independent oversight of

      12      the PSC, which is being strengthened by way of the

      13      Governor's budget --

      14             The Moreland Commission put forth a proposal

      15      to strengthen the PSC.

      16             -- ensuring that any future rate requests are

      17      fully justified, and adequate plans are in place for

      18      storm response and any other contingencies.

      19             The challenge with privatization, would be to

      20      ensure that the debt plus the rates charged by the

      21      new private utility would, together, be affordable

      22      for ratepayers.

      23             Second, public power, which is LIPA ownership

      24      and operation of the T&D system, which they don't

      25      have now.







                                                                   20
       1             Another alternative that the commission

       2      considered is full ownership and operation of LIPA

       3      by the T&D system.

       4             This would entail ending the contract for

       5      management and operation of the system, and moving

       6      those responsibilities wholly into LIPA.

       7             LIPA will become the direct employer of all

       8      the employees currently providing electric service,

       9      and would be directly responsible and accountable

      10      for the quality of service.

      11             While cognizant of the many possible benefits

      12      of public power, the commission is also aware that

      13      it may cause potential problems, particularly given

      14      the complete loss of confidence in LIPA, the limited

      15      ability to recruit qualified executives, and the

      16      potential addition of over 2,000 employees to an

      17      already overburdened State employee pension system.

      18             The third option was NYPA ownership and

      19      operation of the T&D system.

      20             This structure would be similar to the LIPA

      21      ownership and operation, except that NYPA would

      22      assume ownership and operating responsibilities.

      23             Electrical-system revenues and expenses from

      24      Long Island and the Rockaway Peninsula will be kept

      25      completely separate from the existing NYPA funds.







                                                                   21
       1             A potential advantage of the NYPA model

       2      versus the LIPA public-power-model discussed above,

       3      is that oversight of the entity would be done by

       4      NYPA's successful professional energy industry and

       5      financial-management team.

       6             Some potential problems with this model

       7      include that NYPA has no expertise in retail utility

       8      operations or retail customer service, and NYPA's

       9      management is a full LIPA public power effort could

      10      divert considerable management attention away from

      11      NYPA's historical mission.

      12             To some of the commission's findings,

      13      fundamental changes are essential to the provision

      14      of safe and reliable electric service on

      15      Long Island.

      16             The interim report goes into the pros and

      17      cons of each of -- option that was provided, and the

      18      Moreland Commission's investigation is ongoing, and

      19      we plan on issuing the final report by spring.

      20             And I do know that -- I'm going to hand the

      21      microphone on over to my colleagues over here, and I

      22      understand, thereafter, we'll be taking questions

      23      and answers.

      24             SENATOR MARCELLINO:  Yeah, that is our

      25      policy.







                                                                   22
       1             We'll move on to Mr. Quiniones, and allow

       2      them, and then we'll have questions from the panel

       3      after the fact.

       4             Go ahead, Mr. Quiniones.

       5             GIL C. QUINIONES:  Thank you.

       6             Good morning, Mr. Co-Chairman, and members of

       7      the Committees.

       8             I am Gil Quiniones, the president and

       9      chief executive officer --

      10             SENATOR MARCELLINO:  Mr. Quiniones, one

      11      second.  I apologize.

      12             We have been joined by my colleague in the

      13      New York State Senate, Bill Perkins.

      14             Senator Perkins is here.

      15             And -- oh, I'm sorry.

      16             And, also, Senator John Flanagan.

      17             He sneaks in; right?  He's a stealth senator.

      18             I'm sorry.  Mr. Quiniones, please.

      19             GIL C. QUINIONES:  Okay.

      20             I am Gil Quiniones, the president and

      21      chief executive officer of the New York Power

      22      Authority.

      23             And I appreciate this opportunity to discuss

      24      options for ensuring that customers of the

      25      Long Island Power Authority receive high-quality







                                                                   23
       1      electric service at affordable rates.

       2             With me here today is Robert Lurie, NYPA

       3      senior vice president of strategic planning, and,

       4      the project executive for NYPA's ongoing analysis.

       5             As the New York's only statewide public power

       6      authority, the Governor sought NYPA's assistance in

       7      reviewing LIPA's current legal and organizational

       8      structure, and in providing him with options for

       9      restructuring LIPA.

      10             It has become abundantly clear that LIPA's

      11      current structure has failed ratepayers and must be

      12      overhauled.

      13             The Governor indicated that the suggested

      14      option should address five key objectives, to better

      15      serve the customers on Long Island and in

      16      The Rockaways.

      17             First, he stated that there must be rate

      18      stability, both in the short and the long term;

      19             Second, any solution must improve the quality

      20      of service ratepayers on Long Island have

      21      experienced to date, and the new option provide

      22      ratepayers with a level of service equivalent to

      23      that which the best utilities provide to their

      24      customers;

      25             Third, any plan must provide for property-tax







                                                                   24
       1      stability;

       2             Fourth, any resulting utility must have the

       3      full confidence of Long Island residents that it is

       4      highly prepared for storms and other extreme events;

       5             And, fifth, the utility must have a

       6      well-formulated and resourced plan for responding to

       7      extreme weather events in a manner that restores

       8      service quickly, and provides customers with the

       9      critical information they need.

      10             In short, the Governor wants a utility that

      11      will provide safe, reliable, affordable, and

      12      environmentally responsible electric supply on

      13      Long Island.

      14             In order to evaluate the restructuring

      15      alternatives with the goal of achieving the

      16      Governor's objectives, NYPA assembled a group of

      17      highly qualified financial and legal advisors, led

      18      by the investment banking firm Lazard.

      19             In addition, I assigned an internal NYPA team

      20      of senior executives in strategic planning, finance,

      21      law, and power-resource planning to work with the

      22      LIPA staff, and the -- our consulting team.

      23             Lazard, along with our internal team, is

      24      performing an extensive analysis of the costs and

      25      benefits of various options for LIPA's transmission







                                                                   25
       1      and distribution assets, including, continuing to

       2      have LIPA own the assets and have a third party

       3      manage them, taking on the operation itself as a

       4      municipally owned and operated utility, and selling

       5      the assets to a private utility company.

       6             In addition, Lazard is analyzing the

       7      alternatives for dealing with the, roughly,

       8      $7 billion of debt on LIPA's books, over 3 billion

       9      of which is a legacy of LIPA's acquisition of LILCO

      10      and the debt that utility incurred in the

      11      construction of the now-dismantled, or

      12      decommissioned, Shoreham nuclear power plant.

      13             Their work, and our work, continues, and

      14      includes an analysis of the power-supply contracts

      15      in LIPA's portfolio.

      16             With Lazard's assistance, we are assessing

      17      different options and models that would best meet or

      18      achieve the five stated goals of Governor Cuomo.

      19             Part of this initial study has included an

      20      analysis of the privatization which appears to have

      21      the potential to meet the Governor's goals.

      22             Additional review is ongoing, and needed, to

      23      fully determine if privatization, or any other

      24      model, will meet these goals.

      25             I would like to conclude by emphasizing, that







                                                                   26
       1      this review and work is not yet done, and the State

       2      has not made a final determination of which

       3      restructuring option will best serve LIPA customers.

       4             We are open to any plan that others may have

       5      that can be clearly demonstrated to meet those

       6      objectives.

       7             In the end, what Governor Cuomo wants is

       8      what's best for Long Island ratepayers.

       9             We look forward to working with you, and your

      10      colleagues, in the vital process of bringing

      11      transparent, reliable, and affordable utility

      12      service to the residents and businesses of

      13      Long Island and The Rockaways.

      14             This concludes my prepared testimony, and we

      15      are now, as a panel, ready to take your questions.

      16             SENATOR MARCELLINO:  Mr. Lurie, are you going

      17      to --

      18             ROBERT F. LURIE:  I have no prepared

      19      testimony.  I will just take Q and A.

      20             SENATOR MARCELLINO:  Okay.

      21             Just for record, I wanted to make sure that

      22      we understood it:  Lazard Group was invited here,

      23      and initially accepted to testify before the

      24      hearing.

      25             And then for reasons, personal and otherwise,







                                                                   27
       1      pulled out of the testimony.

       2             And, the Governor's Office was kind enough to

       3      send Mr. Quiniones, Mr. Lurie, and Ms. Calcaterra

       4      in their place.

       5             I have talked to the Governor's people, and

       6      told them that Lazard's testimony for this Committee

       7      would be most important to us, since they are the

       8      numbers people.

       9             And we're most interested in the impact on

      10      the ratepayers, as to how that debt is handled, in

      11      moving forward, what -- as you stated in your

      12      testimony, and -- both of you stated in your

      13      testimony, would be the impact on customers.  The

      14      key element -- in fact, on property taxes, the key

      15      the element.

      16             Just a quick question, and then I'll turn it

      17      over to some of my colleagues who may have questions

      18      as well.

      19             Anybody see this article in "Newsday" today?

      20             My favorite newspaper.

      21                  [Laughter.]

      22             SENATOR MARCELLINO:  It is:  A LIPA 2010

      23      study, rate hike, likely -- likely will -- likely --

      24      likely with privatization.

      25             A rate hike likely with privatization.







                                                                   28
       1             That's a key element here that we're talking

       2      about.

       3             Would you agree with this?

       4             They cite reports done.  The information for

       5      this article was apparently obtained from the

       6      Suffolk County Legislature's LIPA Oversight

       7      Committee, through a Freedom of Information Request

       8      by that committee.

       9             It cites three different studies done

      10      under -- by various groups and organizations.

      11             I'm talking about a 15 to 20 percent increase

      12      in the rates.

      13             Any comments on that?

      14             GIL C. QUINIONES:  I did see the article.

      15             I have not read the report fully, but I

      16      just -- I browsed through it.

      17             And I just want to point out, on page 4, it

      18      says that, in this particular study that you have

      19      cited, that:

      20             "These results are based on very high-level

      21      assumptions, and the purpose of this analysis is to

      22      provide ballpark numbers for the strategic options

      23      to consider."

      24             My take on it, it was really done for a

      25      different purpose.







                                                                   29
       1             What we are doing, which is still ongoing and

       2      not yet completed, is a very detailed analysis,

       3      based on the facts, and based on input from various

       4      stakeholders.

       5             And, so, I -- you know, it's -- to me, it's a

       6      different study than what we're -- what we're

       7      interested in, is get to -- to do an analysis that's

       8      fact-based, and that will -- that will produce the

       9      results based on what's best, in the long term, for

      10      Long Island ratepayers.

      11             SENATOR MARCELLINO:  You mentioned the

      12      preliminary report in your testimony.

      13             Is that possible to receive a copy of that?

      14             REGINA CALCATERRA:  Absolutely.

      15             It's also on our website, which is

      16      moreland.ny.gov.

      17             But, I certainly will make sure that your

      18      office gets a copy of that.

      19             SENATOR MARCELLINO:  Thank you, we would

      20      appreciate that.

      21             And you anticipate a final report by the

      22      commission sometime in the spring?  Is that what you

      23      said?

      24             REGINA CALCATERRA:  Correct.

      25             SENATOR MARCELLINO:  Okay.







                                                                   30
       1             In your testimony, you talked about

       2      synergies, and the benefits, with privatization.

       3             What synergies, and what benefits?

       4             REGINA CALCATERRA:  If another utility was to

       5      take over the entire T&D system -- basically, if it

       6      was, an IOU came in -- the strong likelihood, is

       7      that they're operating somewhere else in New York or

       8      somewhere else in the region.

       9             So as a result of that, they've got fuel;

      10      they have staff; they've got mutual aid; they have

      11      other resources, polls and wires, that they're going

      12      to stockpile.

      13             So it's not as if it's just one entity that's

      14      buying all this fresh, so they'll be able to get,

      15      potentially, lower prices, because they'll be buying

      16      more things in bulk.

      17             So those were some of the examples with the

      18      synergies that we got by way of the meeting that we

      19      had with Lazard, which briefed us.

      20             ROBERT F. LURIE:  And I might also add to

      21      that, if I could, Senator, that they're -- you know,

      22      LIPA currently pays tens of millions of dollars in

      23      fees to outside parties, not National Grid being

      24      one, but, also, other consultants.

      25             And we believe that, in combination, as







                                                                   31
       1      Ms. Calcaterra said, with another utility, those

       2      fees would no longer be required.  They've -- those

       3      services could be performed by the existing staff of

       4      that larger utility, so that there could be tens of

       5      millions in savings just from that alone.

       6             So, there are some examples there that, you

       7      know, are going to be factored into the analysis.

       8             And, really, the question that we have is:

       9      Will that add up to enough to offset some of the

      10      other costs, and add on to the other benefits that

      11      will be factored into that analysis.

      12             SENATOR MARCELLINO:  Under the proposed

      13      privatization plans, how would the monthly debt

      14      service be handled?

      15             ROBERT F. LURIE:  It's useful, I think, to

      16      think of LIPA's 7 billion in outstanding debt in,

      17      essentially, two categories:

      18             One being, the debt that -- the bonds that

      19      were issued to finance or acquire the T&D system;

      20      that is, the wire assets, all the equipment, and so

      21      forth, that are used in the everyday operation of

      22      the electric system, that's about half of LIPA's

      23      debt, about $3 1/2 billion, attributable to that.

      24             The other 3 1/2 billion is attributable to

      25      the cost originally, it's a legacy, of having







                                                                   32
       1      acquired the Shoreham assets, which are no longer in

       2      use.

       3             So, that debt is not, in a sense,

       4      attributable to a productive asset.

       5             So, in privatization, what -- the way the

       6      structure would have to work, is that the sale of

       7      those assets would be done for a price somewhere

       8      roughly equivalent to the $3 1/2 billion of bonds

       9      that were issue for those assets.

      10             The remaining debt, the $3 1/2 billion, would

      11      likely need to be accounted for, or paid, completely

      12      separate from the buying utility, and paid for out

      13      of a separate charge that would be on ratepayers'

      14      bills.

      15             And by doing so, we believe that the cost of

      16      servicing that debt could be brought much lower than

      17      its current cost.

      18             So, that is something that is not in all of

      19      these studies, but is something that -- a technique

      20      that we've brought into this analysis, and will be

      21      included in the pros and cons that we put forth.

      22             GIL C. QUINIONES:  Now, if I may just add --

      23             SENATOR MARCELLINO:  Go ahead.

      24             GIL C. QUINIONES:  -- that this analysis is

      25      ongoing.  We're stress-testing it.  It's not yet







                                                                   33
       1      complete, but, in structure, and in form, it is how

       2      Mr. Lurie described how that's going to work.

       3             SENATOR MARCELLINO:  All right, it's -- I

       4      just have a couple more questions, and then I'll

       5      turn it over to my colleagues.

       6             We've also been joined by Senator Ruben Diaz,

       7      and Assemblyman Chad Lupinacci.

       8             Private organization, private utility, makes

       9      a profit.

      10             How do we transform from a publicly owned

      11      non-profit organization to a privately owned

      12      profit-making entity, and still not have an increase

      13      in rates to the ratepayers? -- which is my prime

      14      concern.  You know, I think the prime concern of my

      15      colleagues as well.

      16             ROBERT F. LURIE:  Sure.

      17             The first thing that I would like to say, in

      18      answer to that question, is that we're not here to

      19      advocate for privatization, or any other option.

      20             SENATOR MARCELLINO:  Yeah, but the commission

      21      did.

      22             ROBERT F. LURIE:  That question that you've

      23      asked is one of the central questions, maybe the

      24      central question, in evaluating privatization in our

      25      analysis as well.







                                                                   34
       1             So if the only -- if the only factor were the

       2      transition from a tax-exempt entity to a tax-paying

       3      entity, then, certainly, the cost of privatization,

       4      you know, would be a non-starter, and it would not

       5      even be on the table.

       6             But there are other factors, including the

       7      synergies which reduce costs substantially,

       8      potentially, and other factors that will be

       9      included, that may or may not offset the costs that

      10      you've rightly point out.

      11             But, that's exactly what we've got to

      12      determine, and we will be doing so in our final

      13      report, when that's delivered.

      14             SENATOR MARCELLINO:  My last question for now

      15      would be:

      16             It's my understanding that the debt was

      17      structured for Shoreham in such a way, that,

      18      basically, the bondholders are guaranteed their

      19      interest.

      20             There are penalties, fees, and the like, for

      21      the prepayment of the debt.

      22             Much like a mortgage; if you have a mortgage

      23      on your house, and you go to prepay it, there may be

      24      a penalty that the bank charges you for prepaying

      25      that balance; that they get a percentage of their







                                                                   35
       1      interest on the debt.

       2             It's my understanding that this arrangement

       3      with the Shoreham bondholders is significant, to the

       4      tune of several billion dollars more.

       5             So it's not 7 billion-plus.  It could be as

       6      much as 12 billion in debt that has to be dealt

       7      with.

       8             Is that true?

       9             ROBERT F. LURIE:  No.

      10             No, I think --

      11             SENATOR MARCELLINO:  Where am I wrong?

      12             ROBERT F. LURIE:  -- I believe those numbers

      13      are correct.

      14             SENATOR MARCELLINO:  Where am I wrong?

      15             ROBERT F. LURIE:  There are -- I don't know

      16      where the "$12 billion" number comes from, but let

      17      me speak to your --

      18             SENATOR MARCELLINO:  It was a number that was

      19      given to us in a meeting that we held with the

      20      Governor's Office, and then -- with Lazard present.

      21             ROBERT F. LURIE:  I'm sorry, I can't speak to

      22      that number, but let me speak to the description

      23      that you gave.

      24             It is true that some of the outstanding bonds

      25      of LIPA can only be retired prior to maturity if







                                                                   36
       1      there is a penalty paid.

       2             It is not a large penalty, in some cases.

       3      It's a small penalty.

       4             In other cases, they can't be called at all

       5      before maturity by virtue of the contractual terms

       6      with bondholders.

       7             In -- there are about 4 billion of the

       8      7 billion dollars in bonds that can be retired

       9      early.  That's not to say they can be retired today.

      10             As you correctly point out, if by their

      11      terms, in some cases, it takes several years before

      12      LIPA has the right to retire those bonds prior to

      13      maturity.  And they would, in some cases, in many

      14      cases, have to pay at least some penalty, which

      15      is -- I don't believe it's going to come close to

      16      the "$12 billion" number.

      17             SENATOR MARCELLINO:  Would that set of

      18      numbers be included in the preliminary report that

      19      Moreland has?

      20             Or could we get a set of figures on that, so

      21      that we would know what the exact --

      22             GIL C. QUINIONES:  That would --

      23             SENATOR MARCELLINO:  -- debt would be?

      24             GIL C. QUINIONES:  -- that is part of the

      25      ongoing analysis that we have, not only in







                                                                   37
       1      privatization, but the other model, where we are

       2      looking at various scenarios, stress-testing the

       3      various models, to make sure that we all are working

       4      from a shared set of facts as we finalize the

       5      analysis.

       6             SENATOR MARCELLINO:  Now, what I would like

       7      to see is, is in some place that we can get a set of

       8      numbers that are consistent, so that we're all

       9      working with same set of numbers, going forward.  We

      10      don't have to go up and down.

      11             I believe we --

      12             ROBERT F. LURIE:  We agree.

      13             GIL C. QUINIONES:  We agree.

      14             SENATOR MARCELLINO:  Any -- any new members?

      15             All right.

      16             I think Senator Boyle is sitting out there.

      17             If you want to, come on up.  We'll get you a

      18      chair.

      19             SENATOR BOYLE:  I'm okay.

      20             SENATOR MARCELLINO:  Okay.

      21             Senator Ranzenhofer.

      22             SENATOR RANZENHOFER:  Thank you.

      23             Thank you, Chairman Marcellino.

      24             I would like to address my question to

      25      Ms. Calcaterra, as the executive director of the







                                                                   38
       1      Moreland Commission.

       2             It is my understanding that the

       3      Moreland Commission was created in November, really,

       4      to do an investigation into what --

       5             SENATOR MARCELLINO:  You have to talk into

       6      that.

       7             SENATOR RANZENHOFER:  Start from scratch.

       8             Did you hear what I just said?

       9             Should I start from the beginning?

      10             REGINA CALCATERRA:  I did.

      11             I got, "November", and "executive order," and

      12      "investigation."

      13                  [Laughter.]

      14             REGINA CALCATERRA:  I got their proper

      15      pronunciation of my last name, which I'm very

      16      impressed with.

      17             So, please continue.

      18             SENATOR RANZENHOFER:  Okay.  Well, then, you

      19      missed that I also thanked Senator Marcellino for

      20      his questioning.

      21             But to continue:

      22             Obviously, you completed, or you started,

      23      your investigation.  You've issued a preliminary

      24      report.  You indicated the final report is going to

      25      be forthcoming.







                                                                   39
       1             The Governor has now introduced a bill which

       2      encompasses a lot of your recommendations, and

       3      especially, what it does is, it gives a lot of

       4      increased authority to the PSC.

       5             REGINA CALCATERRA:  Yes.

       6             SENATOR RANZENHOFER:  Some view it as

       7      punitive, some view it as overregulatory.

       8             But in any event, you made some

       9      recommendations which have now been codified in the

      10      bill.

      11             And the question that I have for you is:

      12             In your testimony, and a lot of what has

      13      happened, dealt with the power to the electrical

      14      system, but yet your recommendations in the bill

      15      talk about expanding it for all utilities, which, to

      16      my knowledge, you know, other the utilities did not

      17      have the problems that were experienced on

      18      Long Island with LIPA.

      19             And I wanted to know whether or not it was

      20      thought among the membership, that there needed to

      21      be regulatory increases in other utilities which did

      22      not experience problems, which did not have customer

      23      complaints.

      24             It seemed to me that it was overkill, in

      25      terms of some of the recommendations, and the bill







                                                                   40
       1      that was ultimately introduced.

       2             And I wanted to ask you for an explanation of

       3      that.

       4             REGINA CALCATERRA:  The executive order

       5      provides the Moreland Commission with a narrow goal,

       6      and a very broad goal.

       7             The narrow goal, is that we need to take a

       8      look at all of the utilities around the state.

       9             So, there's six IOUs, and there's LIPA.

      10             If you take a look at all of them and

      11      investigate their emergency plan and their storm

      12      response for what is defined as "recent storms," and

      13      those recent storms include, not only "Sandy," but

      14      "Irene," "Lee," and the December 2008 snowstorm.

      15             So even though, in the short term, in the

      16      interim report, we looked at LIPA, because you're

      17      dealing with an entity that's dysfunctional and you

      18      need to immediately address it, our investigation

      19      with the other utilities are now ongoing as well.

      20             So we're using the same model we use with

      21      LIPA, and investigating all of the other utilities.

      22             But as we were preparing for that, we were

      23      trying to figure out how best would they, for their

      24      prior performance --

      25             And I can't disclose what it is that we're







                                                                   41
       1      finding, and that will be disclosed in the final

       2      report.

       3             -- is that, there isn't a way to penalize

       4      them.

       5             And the reason why is, because the PSC -- the

       6      only way that the PSC has the ability to penalize,

       7      is if they actually go to court, and they have a

       8      very high bar to prove knowingly.

       9             So as a result, they never went to court,

      10      because it's an incredibly high bar to prove, so

      11      they haven't -- they have very limited ability to

      12      penalize internally.

      13             And to penalize a utility, or to penalize

      14      anyone in the market, is a way to incentivize them

      15      to perform.

      16             So then we started taking a look at other

      17      states around this area in the northeast, and

      18      elsewhere, to see what it is that they actually do.

      19             So we benchmarked, to see what they do with

      20      utilities.

      21             And what we found is that, you know, we

      22      focused on, with the recommendation, two things:

      23             To take a look at the certificates, and

      24      whether or not there's actually reviews that are

      25      being done for -- to determine whether or not there







                                                                   42
       1      are actually -- if there are standards that are set

       2      by other states that utilities have to provide on

       3      "gray sky" days and "blue sky" days;

       4             And we also took a look at states, to

       5      determine whether or not, actually, if their

       6      equivalent of a PSC has the ability to give a

       7      penalty.

       8             Because, otherwise, to go to court, could be

       9      problematic, and it could take a long time, and it

      10      could be years down the road by the time you

      11      actually get a penalty.  And, then, how is it that

      12      you're actually going to apply it so it goes back to

      13      the ratepayers?

      14             So we found that, with the issue of

      15      certificate and certificate revocation, that

      16      10 other states have it, but they've never used it

      17      before, but at least they have it as a threat; and,

      18      22 other states actually have the ability to give

      19      administrative penalties.

      20             So it's not something that's burdensome;

      21      other states have that as well.

      22             And that information we can easily give you.

      23             And as far as the penalties, the other

      24      penalty that is presently existing, is that, if a

      25      utility is not -- it doesn't comply, they're only







                                                                   43
       1      penalized $100,000 a day per event.

       2             That's not a lot of money, based upon these

       3      privately owned companies that are making hundreds

       4      of millions of dollars.

       5             So if you're going to penalize a company and

       6      force them to act, you want to hold something over

       7      their head, where they're threatened by it.  And

       8      they're not threatened by $100,000-a-day penalty.

       9             So we also took a look at what other -- how

      10      other states penalize utilities, and it's based upon

      11      a percentage of their income, so it would vary,

      12      based upon the size of the utility.

      13             So these are some of the examples that we

      14      looked at, as far as, benchmarking, and making the

      15      recommendations, so there's stronger oversight.

      16             And then also thinking that, if LIPA does go

      17      private, the PSC is going to be overseeing them, and

      18      what type of regulation would we want the PSC to

      19      have over LIPA, to make sure that they perform --

      20      or, whoever it is that's operating that, that they

      21      perform during storms, because you have no ability

      22      to threaten anything, to take anything away from

      23      them.

      24             So that's what those recommendations are.

      25             SENATOR RANZENHOFER:  Okay, did you see a







                                                                   44
       1      distinction, though?

       2             Because it seemed to me that some of the

       3      recommendations made the PSC more of a utility

       4      manager than the utility regulator.  I mean, it

       5      actually got into managing the business.

       6             And did you see a distinction between LIPA,

       7      which, obviously, had the very well-reported and

       8      terrible, you know, situation that it had during

       9      those storms, versus what has happened across the

      10      state?

      11             It seemed like you were taking a broad brush

      12      and not really making a distinction, where there may

      13      be a need to make a distinction between the

      14      performance of LIPA and some of the other companies

      15      across the state.

      16             REGINA CALCATERRA:  The -- that distinction

      17      will be, and the comparison will be, made in the

      18      final report, because, as you investigate -- as we

      19      investigate seven utilities, there's document

      20      production and there's depositions.

      21             So, that's ongoing.

      22             So, we can't -- it was too short of a window

      23      to report on anything related to the other

      24      utilities.

      25             And based upon the legislative calendar, if







                                                                   45
       1      we're going to make recommendations for

       2      consideration of what was tremendously important,

       3      that's why we put forth the LIPA information.

       4             So the other utilities, in comparison, will

       5      be forthcoming.

       6             But, actually, if you look at the -- now, we

       7      learned this all during this short interim process,

       8      is also learning the history of the PSC; is that,

       9      the PSC was set up as a regulatory structure, and it

      10      actually moved away, and drifted away, from that

      11      core mission over the past few decades.

      12             So some of the things that are in that --

      13      that are in the bill, and that are in the report,

      14      were actually provided in the past, but were removed

      15      as well.

      16             And one of them, is the ability to audit; is,

      17      they were doing certain types of audit, but then

      18      they stopped doing those audits, and completely

      19      removed the audit function, and left it up to two or

      20      three people in the entire PSC doing audits of

      21      utilities.

      22             And audits are where we're actually finding

      23      out, let's say, you take one example of mutual aid,

      24      and see how it is that they're all dealing with

      25      mutual aid.  That wasn't being done anymore.  There







                                                                   46
       1      was no comparison and contrast.

       2             So some of these, we looked back at how it

       3      was done in the past as they moved away from the

       4      core mission, and we also looked at what other

       5      states were doing as well, as a benchmark.

       6             And, it wasn't as if we did it with a broad

       7      brush looking at LIPA, and not the other utilities.

       8      We've looked at what the other states did.

       9             And, more, importantly, we looked to see if

      10      the utilities in New York State actually operate in

      11      those other states that have these penalties, that

      12      were -- have in our recommendations.

      13             And they do.

      14             So they're already operating in that

      15      environment; and, so, this is normal business

      16      practice.

      17             And if you take the PSC and compare it to its

      18      sister agencies elsewhere, it is a lot weaker.

      19             SENATOR RANZENHOFER:  Okay, final question

      20      that I have for you:

      21             Obviously, on your temporary report, as I

      22      said, there was a bill that was introduced, you

      23      know, as part of the budget, adopting some of your

      24      recommendations.

      25             Are you going to have your final report -- I







                                                                   47
       1      imagine your final report might be different than

       2      your preliminary report.

       3             REGINA CALCATERRA:  Yes.

       4             SENATOR RANZENHOFER:  And is your final

       5      report going to be done before the legislative

       6      calendar requires the budget be passed on April 1st?

       7             REGINA CALCATERRA:  No, it will not be done.

       8             SENATOR RANZENHOFER:  Okay, so there could be

       9      recommendations where you change or contradict or

      10      remove or add some recommendations after the budget

      11      is already passed, and the budget's incorporated

      12      some of your language from your preliminary

      13      recommendations.

      14             REGINA CALCATERRA:  I'm -- I'm limited in

      15      what it is that I can discuss about our

      16      deliberations because, there's a certain point, it's

      17      protected.

      18             But what I can confidently say, is that,

      19      we're finished with that part of it.

      20             We're finished with the PS -- with

      21      investigating the PSC's strengths and weaknesses.

      22             SENATOR RANZENHOFER:  Okay, thank you.

      23             REGINA CALCATERRA:  Thank you.

      24             SENATOR MARCELLINO:  So for the members'

      25      edification, we have requested questions from







                                                                   48
       1      Senator LaValle, Zeldin, Assemblyman McDonough,

       2      Senator Perkins.

       3             Mr. Graf?

       4             Okay.

       5             Anybody else?

       6             And Mr. Raia.

       7             All right, Senator LaValle.

       8             SENATOR LAVALLE:  Mr. Quiniones, the -- you

       9      talked about Lazard models, and my question is:

      10      When will we see those models?

      11             GIL C. QUINIONES:  We are -- as I mentioned,

      12      we are still in the process of doing the analysis.

      13             We don't want to rush the analysis that we're

      14      that doing.  We want to make sure that it is

      15      complete and accurate.

      16             We are --

      17             SENATOR LAVALLE:  Is it weeks? months?

      18             GIL C. QUINIONES:  It would depend.

      19             Right now, we are also getting input, as you

      20      know, led by Secretary Larry Schwartz.  We are going

      21      to -- we're meeting with stakeholders -- various

      22      stakeholders on Long Island.  We've met with the

      23      Senate and the Assembly.

      24             We want to get all of that input and be able

      25      to model part of our analysis.







                                                                   49
       1             I hate to give you a date and then it doesn't

       2      comply with that, but what I can tell you, is that

       3      we are doing this in a very deliberate way, to make

       4      sure that it's done in a fact-based and accurate

       5      way.

       6             SENATOR LAVALLE:  You know, we have the

       7      Brattle report, Navigant report, they're out there,

       8      so that people can look at it and pick them apart.

       9             We don't have anything to really have a

      10      thorough discussion on the issue because we don't

      11      know what these models are.

      12             And, so, I -- of course you can't tell me

      13      with preciseness, but are we talking about weeks, or

      14      months, as your guestimate?

      15             GIL C. QUINIONES:  It could be months, but

      16      not -- you know, again, I hate to put a date on it

      17      because of the uncertainty of input that we're

      18      getting, and requests of scenarios and assumptions

      19      that we're getting, from the stakeholder outreach

      20      that we're making.

      21             And also, our own analysis; we're doing a lot

      22      of stress testing of what Lazard has done, and just

      23      to make sure that we're doing a fact-based and

      24      thorough and complete analysis.

      25             SENATOR LAVALLE:  Okay.







                                                                   50
       1             After "Hurricane Irene," Senator Marcellino,

       2      in Oyster Bay, held a hearing.

       3             And one of the things at that hearing, was

       4      trying to figure out who was in charge of the

       5      day-to-day operations.

       6             And I think, after pulling and tugging, I

       7      think LIPA finally threw National Grid under the

       8      bus, and said:  Well, it's their job.

       9             During the "Nemo" storm, it was very clear --

      10      and if I were to guess, I could see the Governor's

      11      invisible hand -- that it was clear that

      12      National Grid was in charge.

      13             Clearly, LIPA had no role.

      14             During "Irene," my educator personality came

      15      out and I graded LIPA with an F.

      16             During "Sandy," it was probably a little

      17      better than an F, but not much.

      18             But it's clear that the "Nemo" storm,

      19      National Grid, because they were clearly in charge,

      20      seemed to do a job that the general public and

      21      municipalities seemed satisfied with.

      22             So am I right in my assessment of "Nemo,"

      23      National Grid gets good grades?

      24             GIL C. QUINIONES:  I think that it was --

      25      there was less confusion in terms of communication.







                                                                   51
       1             It was clear to local officials and to

       2      ratepayers that they were getting a consistent

       3      message, and, again, less confusion in that process.

       4             From that perspective, I do agree with you.

       5             SENATOR LAVALLE:  Just, last question is:

       6             As you know, LIPA has a contract with PSE&G

       7      that begins January 1, 2014.

       8             So the clock is ticking as to, what do we do

       9      with that contract, and other contracts that they

      10      have?

      11             And what is your -- I mean, what do we do

      12      with the PSE&G contract?

      13             GIL C. QUINIONES:  It is my understanding

      14      that that transition process, those negotiation --

      15      that process is continuing.

      16             SENATOR LAVALLE:  That continues?

      17             GIL C. QUINIONES:  Correct.

      18             SENATOR LAVALLE:  So, PSE&G -- because we --

      19      you know, we have constituents, and they want to

      20      know:  Well, we have a transition period.  Is PSE&G

      21      still going to perform their contract come

      22      January 1, 2014?

      23             Your guess is, yes?

      24             GIL C. QUINIONES:  Yes.

      25             My understanding is, those negotiations and







                                                                   52
       1      transition process is continuing.

       2             SENATOR LAVALLE:  Okay.  So, then, what

       3      happens if the recommendation is, that we are going

       4      to do a privatization model?

       5             What then happens with that contract?

       6             GIL C. QUINIONES:  It depends on when --

       7      on -- you know, assuming that happens, it depends on

       8      when that decision is made.

       9             SENATOR LAVALLE:  Okay.

      10             GIL C. QUINIONES:  All right?

      11             SENATOR LAVALLE:  So --

      12             GIL C. QUINIONES:  And there has to be a

      13      transition process, depending on when that decision

      14      is made.

      15             SENATOR LAVALLE:  So I -- I mean, I --

      16      we're -- it's a work in progress, and the -- the

      17      final decision will be made;

      18             We don't know when we're going to get the

      19      Lazard model so we can have a discussion;

      20             And, we really don't know what's going to

      21      happen with these contracts.

      22             Okay.

      23             That's it.  Thank you.

      24             SENATOR MARCELLINO:  Thank you.

      25             Senator Zeldin.







                                                                   53
       1             SENATOR ZELDIN:  So I come with one, I guess,

       2      complicated request, and, a very specific question.

       3             And I wanted to start off, first off, by

       4      recognizing, and thanking, Chairman Marcellino and

       5      Chairman Ranzenhofer for doing this.

       6             I think it's important for all of us to be

       7      here today, to have a continuing dialogue on these

       8      issues.

       9             I also want to, you know, commend the

      10      Governor as well, and thank him, because he has

      11      encouraged a very open line of communication.

      12             He has, as you mentioned, Mr. Quiniones,

      13      met with the Senate delegation.  I know that

      14      Mr. Schwartz met with the Assembly delegation.

      15             I think that it's very --

      16             SENATOR RANZENHOFER:  No, half the Assembly

      17      delegation.

      18             SENATOR ZELDIN:  Half the Assembly

      19      delegation?

      20             All right, well, I'll defer to my colleague.

      21             But I think it's -- I think it's good to have

      22      an on open line of communication.

      23             And, I read the article this morning in

      24      "Newsday" as well.

      25             And I -- you know, you said a few things that







                                                                   54
       1      jumped out.

       2             One, you -- to quote you, you mentioned the

       3      high-level assumptions in what you're reading,

       4      ballpark estimate, but what's most important is, you

       5      said that you thought it may have been done for

       6      different purposes.

       7             And, I seem to agree.

       8             And -- and I think we should take that study

       9      in 2010 with a grain of salt, and analyze whatever

      10      you propose with an open mind, with the several

      11      different considerations.

      12             So, I think what the Governor accomplished

      13      with the Tappan Zee Bridge, for example, a lot of

      14      people thought was an impossible task to be able to

      15      get that project done as cheaply and efficiently as

      16      seems like it's going to get done.

      17             So, hopefully -- hopefully, what we read in

      18      "Newsday" today about that LIPA study turns out to

      19      be inaccurate.

      20             So my -- my complicated request, I guess,

      21      piggybacking off of Senator LaValle's testimony, in

      22      questioning you just now --

      23             And, by the way, I want to recognize

      24      Senator LaValle, who has been a -- you know, very

      25      outspoken with regards to LIPA, since long time







                                                                   55
       1      before I was in the Senate, and I appreciate his

       2      leadership.

       3             And, Assemblyman Graf, who I overlap with,

       4      has also been very focused on these issues in the

       5      3rd Senate District where I represent.

       6             -- so, in the five points in your testimony,

       7      Mr. Quiniones, you discussed holding the line on

       8      rates, customer service, the storm-emergency

       9      response, to tax-certiorari issues.

      10             Throughout the rest of your testimony, you

      11      discussed dealing with the outstanding debt, the

      12      value that might be obtained from any sale.

      13             And these were all points that, you know, I'm

      14      looking for today, to get discussed.

      15             And I'm glad to hear that you're bringing

      16      that up, and incorporating that into whatever plan.

      17             The very specific request is, you know,

      18      whatever models end up being -- being offered to us,

      19      you know, we're going to be looking at all of those

      20      very closely, to be able to -- because we're going

      21      to have to go back to our constituents and let them

      22      know that we're doing everything in our power to

      23      fight for ratepayers, to be responsible with the

      24      debt, to make sure they're getting the right

      25      customer service.







                                                                   56
       1             That F grade that Senator LaValle gave last

       2      year, that he never has to give another F grade

       3      again, again, that's important.

       4             I wanted to ask you to speak a little bit

       5      about -- and Senator LaValle discussed the PSE&G

       6      contract -- I want to discuss workforce, and it's a

       7      very specific question.

       8             You know, we have -- I have a lot of

       9      constituents who currently are employed.  They don't

      10      know what their future is, and, obviously, they're

      11      going to be impacted with whatever model is pursued.

      12             And, also, what's very importantly, with

      13      regards to the workforce, is what that workforce

      14      looks like when that next storm hits, because, you

      15      know, we're pulling in resources from off of

      16      Long Island, to be able to have a pretty rapid -- to

      17      have the fastest response possible.

      18             So, if you can just speak to workforce, you

      19      know, keeping in mind those people whose jobs are on

      20      the line, but, also, to all those other ratepayers

      21      who are worried about that next storm hitting.

      22             Because that's just one topic we haven't

      23      discussed yet.

      24             GIL C. QUINIONES:  Well, we certainly agree

      25      that the workforce is extremely important.







                                                                   57
       1             As somebody who runs a utility like myself,

       2      in the New York Power Authority, it's number one.

       3             You have to have adequate and properly

       4      resource workforce in whatever structure you have,

       5      going forward.

       6             That it is not a -- that it is not a question

       7      that -- in our analysis.

       8             In our analysis, whatever structure we're

       9      considering, the line workers, the support to those

      10      line workers, are critical equally in all of

      11      structures that we're considering.

      12             SENATOR ZELDIN:  So I -- I guess, just my

      13      last question on that point -- or I guess it's not

      14      so much a question, as a request, just with the --

      15      all those other factors that have been discussed

      16      prior to just now:

      17             I would just ask that, when -- when that

      18      model is released, that, you know, we have an idea

      19      of what that workforce is going to look like, what

      20      their numbers are, what their -- the leadership

      21      structure is going to look like.

      22             And, you know, I guess I would just -- I

      23      would be remiss, every once in a while you find an

      24      opportunity to recognize good work on the part of

      25      specific individuals.







                                                                   58
       1             We see it a lot.  We have a great staff here

       2      in the Senate.

       3             But I just want to mention, there is one LIPA

       4      mid-management person who did so much to help out my

       5      district, his name is Steve Trajarico [ph.].

       6             And if you could write his name down, he

       7      represents the Brookhaven area, and, just a

       8      remarkable job that he did.

       9             So, you know, as a lot of bad publicity was

      10      coming out on LIPA, there are some folks there who

      11      are doing an exceptional job.

      12             GIL C. QUINIONES:  We agree.

      13             SENATOR MARCELLINO:  Thank you.

      14             We've also been joined by the ranking member

      15      of the Senate Investigations Committee,

      16      Senator Hoylman.

      17             Congratulations on your recent marriage.

      18             SENATOR HOYLMAN:  Thank you.

      19             SENATOR MARCELLINO:  Next question is from

      20      Senator McDonough -- or, Assemblyman McDonough.

      21             ASSEMBLYMAN MCDONOUGH:  Thank you, Chairman.

      22             For Ms. Calcaterra --

      23             Am I saying that correctly, Calcaterra?

      24             SENATOR MARCELLINO:  Calcaterra.  Hard C.

      25             REGINA CALCATERRA:  Calcaterra.  Two hard Cs.







                                                                   59
       1             ASSEMBLYMAN MCDONOUGH:  Close.

       2             REGINA CALCATERRA:  Thanks for asking.

       3             ASSEMBLYMAN MCDONOUGH:  Pardon me?

       4             REGINA CALCATERRA:  I said, "Thank you for

       5      asking."

       6             ASSEMBLYMAN MCDONOUGH:  Okay, well,

       7      "McDonough" sometimes is mispronounced too.

       8             In your mention -- you mentioned, obviously,

       9      the three or four options that are available.

      10             Cost is going to be a big consideration.

      11             And I'm wondering, in the agreement that was

      12      made with LIPA and PSE&G, which was some time ago,

      13      to come in another 10 months, what is the cost, or,

      14      do you know, is there a cost, if that contract or

      15      that agreement is broken?

      16             Is there a lot of expenditures that PSE&G

      17      will now be able to come back and say:  Well, we

      18      still have to get this money?

      19             Because I'm sure they've been doing studies,

      20      or, you know, going through the whole system, to get

      21      ready to come in in January.

      22             Did you look at that?

      23             REGINA CALCATERRA:  Those are called

      24      "breakage costs," when you break a contract.

      25             And the Moreland Commission actually relied







                                                                   60
       1      upon the expertise of NYPA, and the staff that they

       2      put together and the team of consultants that they

       3      did.

       4             So, I'm going to need to defer that question

       5      over to Rob Lurie, if you don't mind, so you can get

       6      a better answer.

       7             ASSEMBLYMAN MCDONOUGH:  Thank you.  Sure.

       8             ROBERT F. LURIE:  Sure.

       9             There is a fee that is due to be paid to

      10      PSE&G if the contract is broken for that purpose,

      11      and that fee is $7 million, plus reimbursement of

      12      any out-of-pocket costs, essentially, that PSE&G

      13      would have in unwinding their transition,

      14      essentially.

      15             Now, that's a lot of money, $7 million.

      16             Now, in the context of a, essentially,

      17      $7 billion transaction we're talking about, it's not

      18      a huge amount of money as a percentage.

      19             So, it's -- you know, it's going to be

      20      important, it's going to be factored into the

      21      analysis, but I doubt that that will swing it either

      22      way.

      23             ASSEMBLYMAN MCDONOUGH:  And, finally, is any

      24      information that they developed, or progress or

      25      plans that they've developed, would that be







                                                                   61
       1      available to LIPA, or whoever the new -- if we have

       2      a new operation, would they be required to give all

       3      of that to, let's say, the private operator, or

       4      whoever it is?

       5             ROBERT F. LURIE:  I believe so.

       6             I'm not familiar enough with the details of

       7      the contract, but the concept of that whole

       8      agreement, is that PSE&G is, essentially, building

       9      this out on behalf of LIPA, so LIPA generally owns

      10      whatever it is that is part of this organization.

      11             ASSEMBLYMAN MCDONOUGH:  Okay.

      12             Thank you very much.

      13             Thank you.

      14             SENATOR MARCELLINO:  Senator Perkins.

      15             SENATOR PERKINS:  Thank you very much.

      16             SENATOR MARCELLINO:  You're on.

      17             SENATOR PERKINS:  Oh, I'm on.

      18             Ms. Calcaterra --

      19             REGINA CALCATERRA:  Thank you, Senator.

      20             SENATOR PERKINS:  -- I don't live on the

      21      island.  I had the privilege to --

      22             SENATOR MARCELLINO:  Assemblyman Graf --

      23             Oh, I'm sorry.

      24             SENATOR PERKINS:  -- I live, actually, in

      25      Harlem, and I represent the 30th Senatorial







                                                                   62
       1      District, but I have the privilege of serving on the

       2      Committee on Corporations and Authorities, as the

       3      ranking member.

       4             And -- but, in that regard, you know, we're

       5      very interested in the public authorities, and how

       6      they are of value in terms of public needs and

       7      public services.

       8             And, so, this privatization model that we're

       9      now discussing, raises some concerns from that point

      10      of view.

      11             And so I want -- I don't -- I didn't read the

      12      Long Island newspaper, but I do read the

      13      "Daily News," and I had the opportunity to read an

      14      op-ed about this particular matter, that you may be

      15      aware of it, by Andrew Freedman and -- and

      16      Maya Gelman.

      17             Mr. Freedman is the executive director of

      18      The Center for Popular Democracy, and Ms. Gelman

      19      is an energy policy consultant and advocate for

      20      Energy Democracy in New York City.

      21             And I just want to read a quick quote, and

      22      get your response.

      23             And they basically say:

      24             "It's true, LIPA is a mess.  It is saddled

      25      with debt that comes from bailing out shareholders







                                                                   63
       1      from the last failed effort to privatize the

       2      utility, then-LILCO, but the bank-like private

       3      utilities to whom LIPA would be sold are not to be

       4      trusted.  They have a long record of lining their

       5      pockets at the expense of New Yorkers."

       6             How do you respond to that?

       7             REGINA CALCATERRA:  Well, first, I'd actually

       8      like to respond to that op-ed, because what was

       9      disconcerting about it was one of the earlier

      10      sentences in it, which you didn't mention, but it

      11      basically said that the Moreland Commission came out

      12      with its interim report after holding one hearing.

      13             The Moreland Commission has subpoena power.

      14             We subpoenaed all of the utilities.

      15             We subpoenaed LIPA, National Grid.

      16             We interviewed external stakeholders, we

      17      interviewed emergency managers, we interviewed

      18      managers of critical infrastructure, and many other

      19      players in the utility industry.

      20             We interviewed LIPA and National Grid low- to

      21      mid-level employees.

      22             And, we had three hearings.  One of them was

      23      a hearing where we actually brought National Grid

      24      and LIPA executives before us.

      25             So, before that group should put an op-ed in







                                                                   64
       1      the "Daily News," commenting on our report, they can

       2      disagree with the substance, but don't go after us

       3      on the process.  And don't make up the process, and

       4      change what the process was, just so it makes their

       5      argument sound stronger.

       6             So, right away, I take umbrage with the op-ed

       7      from the beginning, because they didn't read the

       8      report.  Because if they read the report and

       9      followed all of the -- followed our website and all

      10      the testimony that we have up there, they would have

      11      realized all the effort that actually went into the

      12      interim report.

      13             So now that I've said that, the -- we have

      14      six utilities in New York State that are

      15      independently owned and privately operated.

      16             And most of the utilities in the

      17      United States are private companies.

      18             They provide power, and they do it twofold:

      19             One is, they provide power -- I mean, they're

      20      publicly traded, and, yes, what a publicly traded

      21      company's responsibility is, to make sure that their

      22      shareholders are benefited from that.

      23             But the balance that you have with a utility,

      24      is that you have a strong PSC, because the utility

      25      is taking care of the rate -- is taking care of







                                                                   65
       1      their shareholders, because they're publicly traded,

       2      but you have a strong PSC that makes sure that that

       3      utility is also doing what it needs to do for the

       4      particular ratepayer as well.

       5             And you have six utilities in New York State,

       6      including Con Ed, which serves Harlem, and several

       7      others as well, that are already doing this, and

       8      they're doing it fine, and they didn't have the

       9      catastrophe that happened on Long Island, and you

      10      also have it in other states.

      11             So, taking that broad-based statement that a

      12      publicly traded company takes care of its

      13      shareholders, yes, we are in New York State.

      14      New York State has Wall Street.  We benefit from

      15      publicly traded companies.

      16             But it is -- we will -- but if a publicly

      17      traded company is a utility that's going to be

      18      providing service to ratepayers, the State of New

      19      York, which is performing right now, has a

      20      responsibility to make sure it has a strong PSC to

      21      regulate that company, to make sure it's doing what

      22      it needs to do for the ratepayer.

      23             And that's what the balance is.

      24             SENATOR PERKINS:  So -- thank you very much.

      25             Let me just be clear.  I'm not sure we're







                                                                   66
       1      reading the same article, because the one that I'm

       2      referencing points out that -- if I may quote:

       3             "Governor Cuomo's historic

       4      Moreland Commission will hold only a few hearings,

       5      but big changes are in the offing."

       6             So they don't say, one hearing.  They

       7      mentioned that there will be a few.

       8             I just want it for the record, in case we --

       9      I -- you know, we -- we have different stories.

      10             REGINA CALCATERRA:  Understood.

      11             But there's a lot of other work -- then I

      12      misunderstood that.

      13             But there's a lot of other work that we did,

      14      just -- instead of just hearings as well, that was

      15      behind the scene, that led to what our findings

      16      were.

      17             It was an intense several months of an

      18      investigation that we did.

      19             SENATOR PERKINS:  So -- that's good.  I'm

      20      glad to hear that, and I think the public is very

      21      glad to hear that as well.

      22             So the other concern I have is just, some of

      23      the other private utilities that are possibly going

      24      to be in the race for the opportunity, do you -- do

      25      we have a listing of some of those that might be







                                                                   67
       1      under consideration?

       2             REGINA CALCATERRA:  The Moreland Commission

       3      just provided our interim report, and handed it over

       4      to the Governor, so I'm going to have to defer

       5      anything that has to do with the present progress

       6      over to my colleagues.

       7             SENATOR PERKINS:  Okay.

       8             What are the private utilities that might be

       9      in the --

      10             ROBERT F. LURIE:  As you would expect --

      11             SENATOR PERKINS:  -- in consideration?

      12             ROBERT F. LURIE:  As you would expect, you

      13      know, we would -- we would think that the private

      14      utilities that are adjacent to LIPA would certainly

      15      be able to extract the most value; that is, be able

      16      to lower costs the most.  They'd be able to combine

      17      systems-operations facilities the most.

      18             And, then -- so that there are, you know, the

      19      ones that are immediately adjacent are:

      20             Con Ed;

      21             National Grid, of course, has their gas

      22      operations that are contiguous with LIPA's;

      23             And then, beyond that, of course, just beyond

      24      the New York City region, there's other utilities

      25      that are just beyond that.







                                                                   68
       1             So, PSE&G of New Jersey, which is now taking

       2      over the operations contract, they're nearby.  They

       3      might be interested.

       4             Northeast Utilities, also up in Connecticut,

       5      might be a candidate.

       6             So, none of these are going -- these

       7      companies aren't going to come out and say that

       8      they, you know, are going to do this.  You know,

       9      they have to keep their strategy close to the vest,

      10      but, you know, there's every reason to believe that

      11      they would take a look at this, that they would find

      12      value in it.

      13             Whether they would make a decision to put in

      14      an offer or not, I couldn't say.

      15             SENATOR PERKINS:  So, Mr. Chairman, just

      16      one or two more quick questions, and --

      17             SENATOR MARCELLINO:  Quick.

      18             If we could emphasize on the "quick."

      19             SENATOR PERKINS:  Yeah.

      20             So, forgive my naiveness, but -- so there's

      21      going to be some sort of announcement, and assuming

      22      this moves forward, and these companies will all be

      23      sort of applying in some sort of competitive

      24      process.  Or -- and --

      25             ROBERT F. LURIE:  If they choose to, yes.







                                                                   69
       1             SENATOR PERKINS:  -- could you just describe

       2      that --

       3             ROBERT F. LURIE:  If they choose.

       4             SENATOR PERKINS:  -- what did you anticipate

       5      the process being, assuming this moves forward, as

       6      per the Governor's --

       7             GIL C. QUINIONES:  Well, I think, first and

       8      foremost, we're still in the middle of our analysis

       9      of all the options, so it will be premature for us

      10      to say that, you know, there's one answer at this

      11      point.

      12             SENATOR PERKINS:  Okay.

      13             GIL C. QUINIONES:  And -- so I think that

      14      it's just premature to make that prediction.

      15             SENATOR PERKINS:  Okay.

      16             So the last final question, which is always

      17      important to the consumer, I guess, is -- at least

      18      from my community's perspective, which I assume is

      19      no different than anybody else's:  Is this going to

      20      cost the consumer more, or less, ultimately, do you

      21      anticipate?

      22             GIL C. QUINIONES:  Again, the Governor has

      23      set forth five criteria, as we analyze the various

      24      options.  And, we are going to stress test, and do

      25      scenario analysis, and make sure that the option







                                                                   70
       1      that satisfy the best -- the five criteria set forth

       2      by the Governor, will be the one that will be

       3      advanced and recommended.

       4             ROBERT F. LURIE:  If I could just add to --

       5             SENATOR PERKINS:  So the answer is "more"?

       6             ROBERT F. LURIE:  No, no.

       7             Any process, whether it's, you -- you know,

       8      municipalization, something like the status quo,

       9      whether it's privatization, the process we undergo,

      10      as well as the outcome, will be subjected to those

      11      five criteria.

      12             So, you know, any utility that would be

      13      interested, any municipal authority interested, will

      14      have to satisfy those five criteria.

      15             SENATOR PERKINS:  But can the public

      16      anticipate that this model, which might be applying

      17      here now, but might also be replicated in other

      18      instances, do you anticipate that this could cost

      19      more to the consumer?

      20             Is there a -- is there a scenario that could

      21      result in the consumer paying more?

      22             ROBERT F. LURIE:  Let me be clear:  I think

      23      this goes back to Senator Marcellino's question,

      24      because I think he put the finger on the question,

      25      which is, that we've got to be able to determine







                                                                   71
       1      whether the additional costs associated with having

       2      a private company involved, are more or less than

       3      offset by the savings that can be incurred by

       4      combining companies.

       5             We don't know the answer to that yet.

       6             So, clearly, the Governor said we're not

       7      going to do something that's going to cost more.

       8             That's the first factor he set forth.

       9             So, ultimately, the solution we recommend

      10      will not have an increased cost to ratepayers.

      11             GIL C. QUINIONES:  And what we can all agree,

      12      the status quo is untenable.  It has to change.

      13             And that's why we're evaluating all the

      14      options.

      15             We have five criterias:  Stable rates,

      16      predictable stable property taxes, customer service

      17      and performance, storm preparation, and storm

      18      response capabilities.

      19             So those are five screens.  We will apply

      20      those exactly the same way on each of the options

      21      that we are going to be looking at.

      22             SENATOR PERKINS:  It sounds like we want the

      23      best for less.

      24             SENATOR MARCELLINO:  That would be ideal.

      25             It is my understanding, so we can clarify







                                                                   72
       1      this, that while there has been a recommendation by

       2      members of the Moreland Commission, there has been

       3      no decision made as to go to privatization or not?

       4             GIL C. QUINIONES:  Correct.

       5             SENATOR MARCELLINO:  That is still up for

       6      discussion; that is still up in the air; that is

       7      still an open issue, and an open question.

       8             Is that correct?

       9             GIL C. QUINIONES:  Correct.

      10             SENATOR MARCELLINO:  Okay.

      11             GIL C. QUINIONES:  Remember, the

      12      Moreland Commission looks specifically on storm

      13      performance and response.

      14             We're talking about a utility with

      15      1.2 million customers.

      16             It is prudent that we do a fact-based

      17      analysis, that we do a thorough and complete

      18      analysis.

      19             We're doing it diligently, as fast as we can,

      20      but it's -- we want to do it right, and we don't

      21      want to do it fast for fast sake.

      22             SENATOR MARCELLINO:  That's exactly the

      23      charge my wife gave me this morning.

      24             So, you don't want to cross my wife.

      25             Trust me.







                                                                   73
       1             GIL C. QUINIONES:  Thank you.

       2             SENATOR MARCELLINO:  Assemblyman Graf.

       3             ASSEMBLYMAN GRAFF:  Thank you,

       4      Mr. Chairman.

       5             Let me start out with a statement.

       6             I'm not that happy with the Governor's lines

       7      of communication because, on my side of the aisle,

       8      in the Assembly, and we represent the largest

       9      percentage of Long Islanders on my side of the

      10      aisle, we were left out of the conversation.

      11             We had no such meeting.

      12             And to be honest, I'm not happy.

      13             With that said, I have a couple of questions.

      14             One of the things we didn't talk about today

      15      in any of the testimony, was smaller municipal

      16      electrics, as far as a Suffolk County municipal

      17      electric or a Nassau County municipal electric.

      18             And, I think we should be looking at that.

      19             The other thing is deregulation, like we did

      20      with the telephone companies, where you spur

      21      competition, instead of selling it to one entity.

      22             We saw this movie before.  It was called

      23      "LILCO."

      24             It didn't work out too well for us.

      25             Now, with that said, NYPA sells the







                                                                   74
       1      electricity to LIPA; am I correct?

       2             GIL C. QUINIONES:  No, we sell -- we sell

       3      power to 51 municipal and rural cooperatives across

       4      the state, not to LIPA.

       5             ASSEMBLYMAN GRAFF:  Oh, well, my

       6      understanding, because I went through this.  I've

       7      been living this for a year and a half.  Okay?

       8             And, I know that 62 percent of LIPA's budget

       9      is buying electricity.

      10             That was from LIPA.

      11             And, after going back and forth between NYPA,

      12      and everyone else, it took me a while, but the

      13      answers that I got from NYPA, was, yes, they were

      14      selling electricity to LIPA.

      15             So I don't know if that's correct.

      16             GIL C. QUINIONES:  It's -- this is -- it's

      17      the delivery.  You know, LIPA owns the wires on

      18      Long Island.

      19             So, for example, if we have a recharge

      20      New York customer on Long Island, we have to -- LIPA

      21      will have to deliver that power to those recharge

      22      customers on Long Island.

      23             If you mean in that manner, then that's

      24      correct.

      25             ASSEMBLYMAN GRAFF:  Okay, we have a







                                                                   75
       1      power-generating plant in Holtsville, which is owned

       2      by NYPA.

       3             GIL C. QUINIONES:  What was that?

       4             ASSEMBLYMAN GRAFF:  There's a power plant --

       5             GIL C. QUINIONES:  Yes.

       6             ASSEMBLYMAN GRAFF:  -- in Holtsville.

       7             GIL C. QUINIONES:  Yes.

       8             ASSEMBLYMAN GRAFF:  -- that's owned by LIPA.

       9             GIL C. QUINIONES:  We have a 150-megawatt,

      10      relatively small power plant that is under a

      11      long-term contract to LIPA.  That's correct.

      12             ASSEMBLYMAN GRAFF:  And is LIPA buying that

      13      electricity from that power plant?

      14             GIL C. QUINIONES:  That's correct.

      15             ASSEMBLYMAN GRAFF:  Okay.

      16             And right now, what happens is, when LIPA

      17      pulls power out of the grid, we're paying 9 cents

      18      per kilowatt; right?

      19             GIL C. QUINIONES:  I -- I don't know the

      20      blended amount.

      21             It depends on which power plant, and what

      22      type of contracts.

      23             ASSEMBLYMAN GRAFF:  Okay, I can tell you,

      24      we're paying 9 cents per kilowatt.

      25             But if you look at Rockville Center,







                                                                   76
       1      Freeport, Greenport, and Lake Placid, who get

       2      preference power, they're paying 1 cents per

       3      kilowatt; correct?

       4             GIL C. QUINIONES:  No, more than 1 cent at

       5      the -- at the preference rate, but more than 1 cent.

       6             But, again, they are part of the 51 munie and

       7      cooperatives that NYPA sells power to.

       8             ASSEMBLYMAN GRAFF:  Okay.

       9             GIL C. QUINIONES:  Across the state.

      10             ASSEMBLYMAN GRAFF:  All right.

      11             Now, when we're taking power from you, is

      12      there anyone throughout the state that's paying as

      13      much as we are, per kilowatt, that you know of?

      14             GIL C. QUINIONES:  Maybe in the -- I'm not

      15      100 percent sure, but maybe in the Con Ed service

      16      territory.

      17             ASSEMBLYMAN GRAFF:  So, basic -- we're paying

      18      a lot more than anyone else throughout the state.

      19             Would you agree with that?

      20             GIL C. QUINIONES:  Again, yes.

      21             ASSEMBLYMAN GRAFF:  Okay.

      22             And why this is important to us, is

      23      electricity affects everything for us.

      24             It affects our property taxes, and it affects

      25      our job growth.







                                                                   77
       1             Let me give you some numbers.

       2             Suffolk County's electric bill,

       3      Suffolk County government, their electric bill, per

       4      month, is $1,779,000.

       5             The Town of Islip, per month, $330,000 a

       6      month they pay for electric.

       7             The Town of Brookhaven, 451,000 a month.

       8             My school district, I believe, is 240,000 a

       9      month.

      10             So electricity is the main thing that's

      11      holding back our economy.

      12             And what I'm trying to figure out, is why

      13      Long Island constantly has to subsidize the rest of

      14      the state, and why we get treated differently, where

      15      we're paying more money for energy than other people

      16      are paying.

      17             That's number one.

      18             Number two, if you look at states like

      19      Pennsylvania, you can buy your power from

      20      five different companies.  You have a choice, all

      21      right, and there's competition there.

      22             Have you looked at the contract with PSE&G,

      23      to see if -- thoroughly looked at it, to see if

      24      there's any "out" clauses that would get you out of

      25      the contract?







                                                                   78
       1             Because I know every time the government

       2      enters into a contract, there's always an "out"

       3      clause.

       4             Have you thoroughly looked at the contract?

       5             ROBERT F. LURIE:  Well, I think that was the

       6      question earlier, having to do with what penalties

       7      there might be if we tried to cancel the contract.

       8             And there is a clause in there that allows us

       9      to cancel -- allows LIPA to cancel the contract.  It

      10      requires a $7 million penalty and a reimbursement of

      11      out-of-pocket costs.

      12             ASSEMBLYMAN GRAFF:  Okay.

      13             ROBERT F. LURIE:  So it is cancelable on

      14      those terms.

      15             ASSEMBLYMAN GRAFF:  What if LIPA enters

      16      bankruptcy and fails to exist anymore?

      17             GIL C. QUINIONES:  That option is something

      18      that, you know, is part of the analysis that we're

      19      doing.

      20             I have to tell, though, that there are a lot

      21      of unintended consequences to doing something like

      22      that, in terms of the State's authorities, and what

      23      promise they make to their bondholders.

      24             So to declare bankruptcy, I think, would have

      25      some unintended risks that need to be factored into







                                                                   79
       1      that analysis.

       2             ASSEMBLYMAN GRAFF:  Okay.

       3             And, now, when you were sitting there, you're

       4      looking at -- have you talked to other municipal

       5      electrics to see how they performed during the

       6      storm?

       7             REGINA CALCATERRA:  I can't disclose the

       8      other work that the Moreland Commission is doing --

       9             ASSEMBLYMAN GRAFF:  Okay.

      10             REGINA CALCATERRA:  -- until the report comes

      11      out.

      12             ASSEMBLYMAN GRAFF:  Well, let me put it this

      13      way:

      14             I lived in upstate New York during the ice

      15      storm.  All right?

      16             And Lake Placid had a municipal electric.

      17             You had Niagara Mohawk, but they had a

      18      municipal electric.

      19             During this storm, "Sandy," you have,

      20      Rockville Center has a municipal electric, Freeport

      21      has a -- you know, I'd like to see how they

      22      performed, and the satisfaction that their customers

      23      had.

      24             And, you know, I'm going more towards looking

      25      at a municipal -- a smaller municipal electric,







                                                                   80
       1      which will give more control to the local, you know,

       2      authorities, such as Suffolk County.

       3             And then the oversight on it, is if they're

       4      not performing right, then, election time, they can

       5      vote them out of office.

       6             So there's a little more oversight from the

       7      people that are buying the electricity.

       8             And just -- I'm going to leave one last

       9      thing, to give people an idea of what I'm talking

      10      about, when we're paying for electricity, and the

      11      cost that we're paying.

      12             When I lived upstate, Lake Placid had their

      13      own municipal electric.  This is in the Adirondacks.

      14      It goes below zero.

      15             And everybody up there heats their house with

      16      electric baseboard heat because the electricity is

      17      so cheap.

      18             Let me tell you something:

      19             They're doing something right; we're doing

      20      something wrong.

      21             And Long Island cannot afford any higher

      22      electrical rates.

      23             And there are ways to make it more equitable

      24      for the people down here.

      25             Thank you.







                                                                   81
       1             SENATOR MARCELLINO:  Thank you, Assemblyman.

       2             Assemblyman Raia.

       3             And, gentlemen, can we --

       4             SENATOR RAIA:  Very -- absolutely.

       5             SENATOR MARCELLINO:  -- move it along,

       6      because this group has been up for about an hour and

       7      a half, and I think we have four more groups that

       8      we'd like to hear give their testimony.

       9             SENATOR RAIA:  Thank you, Senator Marcellino.

      10             I will be brief, as is often the question --

      11      or, what happens when you're the last -- you know,

      12      one of the last ones to speak.

      13             I do want to echo Assemblyman Graf's concerns

      14      that 60 percent of the Assembly delegation wasn't

      15      briefed on any of these proposals.

      16             However, I do have some concerns.

      17             Is it true that -- under the Governor's

      18      proposal, that the tax-certiorari cases are all

      19      going to be frozen in the individual jurisdictions?

      20             Do you know anything about that, or --

      21             No?

      22             ROBERT F. LURIE:  And I'm not sure what

      23      [unintelligible] --

      24             SENATOR RAIA:  Well, here's the problem.

      25             I'm trying to figure out, in my mind, how a







                                                                   82
       1      privately-run utility, that won't be eligible for

       2      FEMA funds, that won't be eligible for low-cost

       3      bonding, and will not be able to recoupe any

       4      revenues through tax certiorari -- pending the

       5      tax-certiorari cases, could possibly survive, and

       6      make a profit.

       7             So -- so -- but, however, the tax-cert case,

       8      that issue is very important in my district, and I'm

       9      just trying to figure out if you know if whether or

      10      not there is a proposal to freeze --

      11             So, you don't know, or you're not sure?

      12             GIL C. QUINIONES:  We don't know.

      13             SENATOR RAIA:  Okay, thank you.

      14             Number two, I guess it was mentioned, the

      15      word "synergy" was used earlier.

      16             Has the commission taken a position, or

      17      studied, I guess, National Grid's announcement that

      18      they're not going to allow their non-electric

      19      workers to participate during storm emergencies?

      20             And one of my concerns is, is National Grid

      21      has been very good at cross-training a lot of their

      22      employees.

      23             So, you could have a gas person hooking up a

      24      power line on a house.

      25             You see an awful lot of National Grid trucks







                                                                   83
       1      out there, that are not going to be out there after

       2      2013 -- or I should say, this contract expires in

       3      2013.

       4             And I'm just wondering what type of impact

       5      that's going to have on the delivery of services,

       6      because now we're -- PSE&G is going to have to go

       7      out and hire a lot more subcontractors that just may

       8      not be available.

       9             We still have that problem during this most

      10      recent snow storm.

      11             Subcontractor's equipment breaks, they're not

      12      reliable, and it causes a problem.

      13             So --

      14             SENATOR MARCELLINO:  Assemblyman, with all

      15      due respect, okay, that is an important issue --

      16             SENATOR RAIA:  Yep.

      17             SENATOR MARCELLINO:  -- but I don't think

      18      it's germane to what we're here for.

      19             SENATOR RAIA:  I appreciate it.

      20             SENATOR MARCELLINO:  We're here, talking

      21      about the possibility of the fact of, privatization,

      22      or the other issues, [unintelligible].

      23             If we could take your questions, and an

      24      estimate, at a different --

      25             SENATOR RAIA:  Absolutely.







                                                                   84
       1             SENATOR MARCELLINO:  -- situation?

       2             SENATOR RAIA:  I'll leave it at that.

       3             I guess it was more of concerns that I would

       4      like the Governor's Office to be looking at, and the

       5      commission to be looking at, before they release

       6      their final report.

       7             They're valid, and they are concerns that are

       8      being raised by many groups within the Long Island

       9      community.

      10             Thank you, Senator.  I appreciate it.

      11             SENATOR MARCELLINO:  Thank you.

      12             We have two more members who would like to

      13      question: Assemblyman Montesano, and then

      14      Assemblyman [sic] Hoylman.

      15             Assemblyman Montesano.

      16             ASSEMBLYMAN MONTESANO:  Thank you, Senator.

      17             Ms. Calcaterra, I just have just -- I guess

      18      it's one question, or maybe two.

      19             When did the investigation with LIPA you,

      20      indicated, you know, the difficulties, we didn't

      21      know who was running the place during the storm

      22      and -- with National Grid.

      23             I guess my question would be:

      24             Everything that we're hearing today is going

      25      to involve some type of expense allocation which







                                                                   85
       1      can, potentially, come back to the ratepayer.

       2             And I was just wondering, in your analysis so

       3      far, is there any feasibility, that if we

       4      restructured LIPA, from top to bottom, and corrected

       5      the deficiencies in the management agreement they

       6      have with, right now, National Grid, and, hopefully,

       7      with PSE&G, can the model that's being used now

       8      continue to be viable?  Can it be salvaged?

       9             REGINA CALCATERRA:  The Moreland Commission

      10      spent a lot of time really looking at the bifurcated

      11      structure.

      12             And, at the public hearing, where we brought

      13      the executives before us, they, literally, sat

      14      there, and we asked that.

      15             We had the top people at LIPA and the top

      16      executives at National Grid sitting next to each

      17      other, so they couldn't point fingers.

      18             They all thought the existing structure

      19      actually works.

      20             So if you're dealing with two entities that

      21      think the existing structure works, but other

      22      Long Islanders, and legislators that are here, that

      23      knows that existing structure doesn't work, because

      24      they experienced the back end of it, I would

      25      question, and the Moreland Commission would







                                                                   86
       1      question, keeping those same parties in place who

       2      don't think that there's actually a problem.

       3             So, from the Moreland Commission's

       4      perspective, the status quo is untenable.

       5             Anything beyond that, I'm going to leave to

       6      the Governor's Office -- we'll leave for the

       7      Governor's Office and the Legislature to work out.

       8             The status quo, as it is now, is untenable.

       9             ASSEMBLYMAN MONTESANO:  Okay, but you're

      10      using the thought of the same parties that are

      11      involved.

      12             I'm just going by, if we change the parties

      13      around but kept that operating model in effect, can

      14      it be sustainable?

      15             I mean, right now, apparently, National Grid

      16      and LIPA just don't click, or don't operate.

      17             But, we see that bifurcated model, and just

      18      trying to spare the expense, and get the best of

      19      our -- out our dollar, is there any way of

      20      operating, or it has to be one way or the other?

      21             I mean, how would anybody see that on the

      22      panel?

      23             ROBERT F. LURIE:  The problem -- in --

      24      there's a problem inherent in that model, that the

      25      Moreland Commission I think eloquently pointed out,







                                                                   87
       1      and the difficulty of coordination and communication

       2      when you have a bifurcated structure.

       3             So there's a problem with the structure that,

       4      I think, has nothing -- you know, it goes beyond

       5      just the parties.  Okay?

       6             And that's one of the -- you know, the

       7      downsides of keeping a structure like that in place,

       8      going forward, is you have the risk of that

       9      miscommunication and lack of accountability.

      10             So, that's also one of the things we'll be

      11      looking at.  It's one of the options that we are

      12      including in our analysis, that we could go on with

      13      the PSE&G structure, maybe improve it.  There might

      14      be -- maybe there are ways to tweak the contract and

      15      make it more responsive.

      16             But one of the downsides of that is what

      17      we're pointing out here, is that, inherently, it

      18      doesn't fix that core structural problem that the

      19      Moreland Commission pointed out of the bifurcated

      20      structure.

      21             SENATOR RAIA:  Thank you.

      22             Thank you very much.

      23             SENATOR MARCELLINO:  Senator Hoylman.

      24             SENATOR HOYLMAN:  Thank you, Mr. Chair.

      25             Let me just, first, turn on the microphone,







                                                                   88
       1      and add my course of thanks for your efforts over

       2      the last few months.  Nothing short of heroic, and,

       3      I'm very appreciative.  And I know I speak on behalf

       4      of many of my constituents.

       5             I wanted to ask a question about the

       6      determination of privatization versus the other

       7      options.

       8             And, specifically, will Lazard be making

       9      that -- making a recommendation in that regard,

      10      obviously, in conjunction with your team, but, are

      11      they going to be presenting a recommendation in

      12      connection with that specific plan?

      13             ROBERT F. LURIE:  We have asked -- we have

      14      asked them for a recommendation.  So, that is part

      15      of the work that we charged them to do, and so we

      16      expect that they will do that.

      17             UNKNOWN SENATOR:  Now, I guess I just have

      18      some concern that they're --

      19             Obviously, I mean, they're a venerable

      20      institution.  One of the best investment banks in

      21      New York City.

      22             -- but, some concern that they may have a

      23      privatization bias, just given who they are.

      24             How will you incorporate in -- or, are they

      25      seeking, throughout their analysis, dissenting







                                                                   89
       1      voices, consumer groups, other metrics, by which to

       2      judge their ultimate recommendation?

       3             GIL C. QUINIONES:  Let me just answer it.

       4             In my testimony, I had mentioned that I also

       5      formed an internal team of experts from NYPA.  And

       6      we are, you know, scrubbing, doing stress testing,

       7      doing scenario analysis, of whatever Lazard is -- is

       8      doing, and other supporting consults that are

       9      feeding into that -- into that process.

      10             And as I had also mentioned, we are reaching

      11      out to various stakeholders all across Long Island,

      12      led by Secretary Schwartz, and, we will take into

      13      account input.

      14             And if there are other models out there, or

      15      people advocating a position, we want to see their

      16      models.

      17             And, take that all into account, do it in a

      18      very thorough, very fact-based way, you know, before

      19      any recommendation is made.

      20             UNKNOWN SENATOR:  And in terms of conflicts,

      21      I'm assuming that Lazard has cleared all of those,

      22      in terms of its business, and how it proceeds in its

      23      recommendation?

      24             I mean, they may be in the business of

      25      energy, I don't know, but I'm assuming that's







                                                                   90
       1      something that you do routinely?

       2             GIL C. QUINIONES:  Yeah.

       3             Well, in our agreement -- consulting

       4      agreement with Lazard, it's very clear that this is

       5      a discreet assignment.  There's no linkage to any

       6      future work or assignment.

       7             This is a -- you know, we came to them.

       8             "Sandy" occurred.  We needed to address this

       9      issue as quickly as possible.

      10             We came to them, we assembled a team of,

      11      both, outside consultants and internal people at

      12      NYPA, to make a -- to do a thorough analysis, and to

      13      be able to advise, firstly, the Moreland Commission;

      14      and, eventually, as we complete our analysis, the

      15      Governor's Office.

      16             UNKNOWN SENATOR:  And then, finally, sir,

      17      will the recommendations of Lazard be shared with

      18      the Legislature, or will that be part of a larger --

      19             GIL C. QUINIONES:  No.

      20             When everything is complete, and done, you

      21      know, that's our intention.

      22             UNKNOWN SENATOR:  Okay.  Thank you so much.

      23             SENATOR MARCELLINO:  Okay, that's the last

      24      question that I have.

      25             I wish to thank the panel for coming, and for







                                                                   91
       1      your indulgence.

       2             And, look forward to receiving a copy of that

       3      report, and, we'll be in communication.

       4             Thank you very much.

       5             We'll take about a minute break, and then

       6      we'll bring up the next panel.

       7             GIL C. QUINIONES:  Thank you very much.

       8                  (Pause in the proceeding.)

       9                  (The hearing resumed, as follows:)

      10             SENATOR MARCELLINO:  All right, if we can --

      11             Mr. Technician?

      12             Okay.

      13             I recall the Committee back to order.

      14             And the next panel will be:

      15             David Daly, vice president, LIPA transition,

      16      Public Service Enterprise Group;

      17             And, Neal Lewis, who is the -- a board

      18      member -- a sitting board member of the Long Island

      19      Power Authority.

      20             Mr. Daly.

      21             DAVID DALY:  Good morning.

      22             My name is David Daly.  I'm vice president,

      23      LIPA transition, for PSE&G Long Island, a

      24      Public Service Enterprise Group company.

      25             I want to thank Chairs Marcellino and







                                                                   92
       1      Ranzenhofer, and the Committee members, for the

       2      opportunity to appear before you this morning.

       3             I'm the lead executive responsible for

       4      managing the PSE&G Long Island's transition, and the

       5      operation-services agreement we have with

       6      Long Island Power Authority.

       7             As you may be aware, PS Long Island is

       8      scheduled to assume responsibility for management of

       9      LIPA's T&D system on January 1, 2014.

      10             In the time allotted, I'll make very brief

      11      comments about the background of my company, and our

      12      core competencies, how we plan to deliver high

      13      levels of service, and improve customer satisfaction

      14      for Long Island's 1.1 million electric customers.

      15             PSE&G is one of the nation's largest energy

      16      companies, and we're also a neighbor.

      17             We own Public Service Electric and Gas,

      18      New Jersey's oldest and largest electric/gas

      19      utility.

      20             PSE&G serves 2.2 million electric and

      21      1.8 million gas customers in a 2,600-mile --

      22      -square-mile area similar to Long Island's

      23      territory.

      24             We joined the New York business community in

      25      1999 when our electric-generation business, PSE&G







                                                                   93
       1      Power, acquired the Albany steam station, an aging

       2      450-megawatt electric-generating plant located just

       3      south of Albany in Bethlehem, New York, and

       4      transformed the facility into a state-of-the-art

       5      Bethlehem Energy Center.

       6             In the process, we doubled the site's

       7      electric generating capacity while making dramatic

       8      reductions in air and water and environmental

       9      impacts.

      10             We'd be happy to have you over to the site at

      11      any time.

      12             In total, PSE&G has approximately 25 --

      13      29 billion in assets; 10,000 men and women.  About

      14      two-thirds of our employees are represented by

      15      unions, and we have a very strong relationship with

      16      our unions, which we're very proud of.

      17             What may be of particular importance to

      18      Long Island's residents and this Committee, is our

      19      work has gained considerable recognition by national

      20      independent organizations for system reliability,

      21      storm response, and customer satisfaction.

      22             We've been cited as America's most reliable

      23      electric utility 5 out of last 8 years, and the most

      24      reliable utility in the mid-Atlantic region for

      25      11 straight years.







                                                                   94
       1             The Edison Electric Institute, the industry's

       2      national trade association, cited PSE&G for

       3      outstanding work after "Hurricane Irene" and

       4      "Superstorm Sandy."

       5             And on the customer-service front, J.D. Power

       6      and Associates recently ranked PSE&G second in the

       7      eastern U.S. region for residential-customer

       8      satisfaction.

       9             It is this track record and experience and

      10      expertise associated with it that we intend to bring

      11      to Long Island.

      12             As you may know, LIPA selected PSE&G

      13      Long Island in December of 2011, after a two-year

      14      competitive procurement process, to manage its

      15      electric T&D system for a ten-year period.

      16             There were over 90 competitors in that

      17      process.

      18             The operation-services agreement has been

      19      approved by the New York Attorney General and the

      20      State Comptroller.

      21             And very importantly, the operating agreement

      22      with LIPA's structure in a way that aligns our

      23      interests with LIPA's.

      24             We receive a flat fee for providing

      25      management services, with the potential to earn







                                                                   95
       1      incentives for the achievement of significant

       2      improvements in customer satisfaction and other

       3      important reliability metrics.

       4             For example, there are incentives in the

       5      contract, and our plan is to achieve significant

       6      improvements in customer satisfaction and customer

       7      operations to achieve a first-quartile ranking

       8      within five years.

       9             And any cost savings or efficiencies that are

      10      achieved in the process flow right back to

      11      Long Island.

      12             In short, our success is closely linked to

      13      our improving the customer experience.

      14             PSE&G has created a Long Island subsidiary

      15      called "PSE&G Long Island," dedicated to managing

      16      its responsibilities here.

      17             This subsidiary, its management team, and all

      18      the assets required will be located on Long Island.

      19             Our management team will live on Long Island,

      20      and we will be visible and available.

      21             PSE&G and its family of companies have a long

      22      history of involvement in the communities we serve,

      23      and it's one of our core values we intend to bring

      24      to Long Island.

      25             As I noted, we bring to this task a very







                                                                   96
       1      established proven record of performance,

       2      reliability, and customer satisfaction.

       3             We've been hard at work at the transition for

       4      over a year.  We understand the challenges, we've

       5      identified specific areas for improvement.

       6             With LIPA's approval, we will make

       7      recommendations in several areas:

       8             First, in improvements in customer service

       9      and customer satisfaction.  That will include a new

      10      call center and state-of-the-art technologies,

      11      enhanced customer communications, and best-in-class

      12      QA/QC customer processes;

      13             Second, a proven storm-restoration process,

      14      that I had described earlier, has been recognized on

      15      many occasions.  That includes state-of-the-art

      16      outage management technology, and enhanced storm

      17      planning and management structures, and logistics

      18      planning;

      19             Thirdly, we'll introduce best practices into

      20      T&D maintenance and operations;

      21             And, finally, we'll bring PSE&G's proven

      22      analytical tools, including Lean Six Sigma, and

      23      other processes, including our balanced scorecard

      24      process, to optimize team T&D management.

      25             In the area of customer operations, we're







                                                                   97
       1      implementing over 80 recommendations to improve

       2      service and customer satisfaction.

       3             LIPA has already approved our recommendation

       4      to replace existing call-center technologies, and we

       5      have plans to implement a new CIS system and a new

       6      enterprise resource-planning system.

       7             We've also proposed a new outage management

       8      system, one of the key technologies involved in

       9      storm restoration, that will more quickly and

      10      accurately assess damage, direct work crews, and

      11      provide critical information on status.

      12             Our experience in New Jersey during

      13      "Superstorm Sandy" provides some guidance on how

      14      technology processes, planning, and other things

      15      come together to benefit customers.

      16             "Sandy" knocked out electric service to

      17      almost 2 million of our 2.2 million electric

      18      customers.

      19             About a third of our stations -- switching

      20      stations were knocked out, 40 percent of our

      21      substations, and 33 percent of our transmission

      22      lines.

      23             1,000 out-of-state workers arrived in

      24      advance, and that workforce grew to over 4,500.  We

      25      were able to make sure all of these workers were







                                                                   98
       1      housed, fed, and their vehicles had fuel.  They knew

       2      where they were going, had work orders in hand, and

       3      got on the road with little wasted time.  They never

       4      ran out of material and supplies.  We never ran out

       5      of poles, transformers, wires, or fuel.

       6             We restored electric service to 1 million

       7      customers in 3 days.

       8             Over the two-week period that included the

       9      nor'easter that hit on the heels of "Sandy," we

      10      restored power to 2.1 million customers.

      11             That is more than any storm in the history of

      12      any electric utility in the country.

      13             We accomplished all these restorations

      14      efficiently, and I think this speaks to our

      15      storm-restoration process.

      16             We accomplished all of these 2.1 million

      17      restorations at a cost of $295 million.

      18             All through this process, we worked

      19      diligently and as much as accurately possible to

      20      provide information to customers, officials, the

      21      news media, and other stakeholders.

      22             Prior to the storm, we did 700 preemptive

      23      calls with the municipal officials to establish

      24      points of contact, daily conference calls with

      25      municipal officials, and, municipal/bi-municipal







                                                                   99
       1      work plans were developed.

       2             Ralph LaRossa, our chief operating officer,

       3      myself, and other senior executives met with over

       4      100 state legislators and mayors during the storm.

       5             We had daily conference calls with

       6      Governor Christie.

       7             Newspaper, radio, Internet, e-mail blasts,

       8      and social media were also part of our communication

       9      strategy.

      10             In short, and to wrap up, it is this kind of

      11      effort, planning, logistics, up-to-date technology,

      12      proven processes and procedures, analytics, and

      13      communications, bound together by a relentless focus

      14      on the customer and PSE&G Long Island, that we are

      15      bringing to task to manage the electric system.

      16             We know what needs to be done, and we look

      17      forward to the opportunity to serve the people of

      18      Long Island.

      19             Thank you very much.

      20             I'm happy to take your questions.

      21             SENATOR MARCELLINO:  Thank you, Mr. Daly.

      22             Before we go to Mr. Lewis, I just want to

      23      point out to the audience, that members will be

      24      coming and going because of committees assignments

      25      that are going.  There are various subcommittees







                                                                   100
       1      being -- are meeting now.  They have appointments

       2      that have to be met.

       3             We're in the budget-review process, and many

       4      of them are serving on various subcommittees.  So,

       5      they'll be in and out of this room, as it goes.

       6             In the meantime, you're stuck with me, and

       7      Senator LaValle, and that's a pretty good duo.

       8             Mr. Lewis.

       9             NEAL LEWIS:  Thank you, Chairman Marcellino,

      10      and Senator LaValle.

      11             I really appreciate this opportunity to speak

      12      to the Committee today on this very important topic

      13      of the future of the Long Island Power Authority.

      14             Before I begin, let me state that I, of

      15      course, do not speak here today as the official

      16      representative or officer of the Long Island Power

      17      Authority; but, instead, I speak as an individual

      18      who is an appointed volunteer member of the LIPA

      19      Board of Trustees.

      20             I might point out, also, that nobody at LIPA

      21      reviewed these comments.  These are my words alone

      22      that I have submitted to you.

      23             My suggestions for the future of LIPA starts

      24      with the ServCo business model.

      25             As you know, this model was developed by the







                                                                   101
       1      LIPA executive team, LIPA Board of Trustees, and the

       2      Brattle Group.

       3             And I believe that the Brattle Group was very

       4      professional, very thorough; really did a

       5      comprehensive analysis.  They brought utility

       6      expertise to that analysis, and they were

       7      unconflicted in the work that they did.

       8             I think that their work should be given great

       9      weight.

      10             Unfortunately, the media coverage of this

      11      issue since the events involving the restoration

      12      after "Sandy" have really done a disservice to

      13      Long Islanders by not explaining the ServCo model.

      14             I hope, today, we can start to change the

      15      debate, and allow this option to get fair

      16      consideration.

      17             I want to be absolutely clear, that I am not

      18      here today to say that the old structure of LIPA

      19      should be maintained, going forward.

      20             I fully respect and support all those who

      21      call for reform of LIPA.

      22             I simply believe that the ServCo model is the

      23      best reformed model that could be implemented among

      24      the choices available.

      25             And I also suggest some additional reforms







                                                                   102
       1      that I want to point out today.

       2             In my opinion, ServCo presents the

       3      opportunity to get the best of both worlds, both

       4      public and private.

       5             With ServCo, Long Island will retain public

       6      power, with a publicly appointed board that controls

       7      policy, adopts budgets, and sets out to achieve high

       8      standards of investment in the system to promote

       9      high reliability.

      10             The board will not be driven to increase

      11      profits by selling more electricity and, instead,

      12      can focus on the most cost-effective option of

      13      promoting energy efficiency.

      14             LIPA has, over the last decade, established

      15      itself as a leader in New York State, and

      16      nationally, in promoting efficiency and renewables.

      17             Under ServCo, this can continue.

      18             Local control over the significant

      19      investments in clean energy will be retained on

      20      Long Island by LIPA.

      21             With public power, the ServCo business model,

      22      LIPA will continue to qualify for low-interest

      23      municipal bonding rates and for FEMA reimbursements

      24      for major storms.

      25             Also, as a not-for-profit, LIPA does not pay







                                                                   103
       1      income taxes, and can qualify for its sales-tax

       2      exemptions.

       3             And, finally, no payments will be made to

       4      shareholders.

       5             Of course, it has been well reported that the

       6      Brattle Group estimated that all these different

       7      savings could result in as much as 20 percent lower

       8      rates under ServCo as compared to privatization.

       9             ServCo also captures the best benefits of a

      10      private utility without the downside of selling the

      11      system off to a private company.

      12             With ServCo, LIPA will benefit from the

      13      talent, expertise, and experience of the managers of

      14      a major private utility who has been providing --

      15      who will be providing service under contract for a

      16      specific time period.

      17             And I believe you just heard some of the

      18      impressive qualifications that the PSE&G team brings

      19      to this equation.

      20             A vital factor to consider is that LIPA is in

      21      desperate need of upgrading its computer systems.

      22             If you consider all the upgrades that will be

      23      necessary, several different systems, in the coming

      24      years, the costs can be in the tens, or even

      25      hundreds, of millions of dollars.







                                                                   104
       1             There are municipalities around the country

       2      that have set out to purchase major computer systems

       3      and encountered many expensive difficulties.

       4             There are no guarantees that we will not

       5      experience similar problems with our computer

       6      upgrades, but having the expertise and experience of

       7      the PSE&G and Lockheed Martin managements to oversee

       8      those complicated upgrades substantially reduce

       9      those risks.

      10             And those risks was the main focus of the

      11      Brattle Group analysis.

      12             In my opinion, the LIPA board has done an

      13      excellent job of adopting a much improved business

      14      model, and choosing a highly qualified company to

      15      carry out operations under the new system which

      16      would begin January of next year.

      17             I would like to point out that the

      18      Moreland Commission, in their interim report, did

      19      not consider the ServCo model as one of the three

      20      possibilities when evaluating options for the future

      21      of LIPA.

      22             The bifurcation problem, which was the main

      23      theme of the Moreland Commission report, I want to

      24      say on this one, that bifurcation is not a problem

      25      during "blue sky" conditions.







                                                                   105
       1             I simply don't believe that there is a reason

       2      why public-private partnerships can't work.

       3             However, I do agree with the

       4      Moreland Commission, on page 17, where they said,

       5      that:

       6             "The LIPA and National Grid hybrid model is

       7      simply unworkable in the context of a storm event."

       8             I agree on that point.

       9             During a storm, we should not have a

      10      bifurcated system.

      11             So during the storm, LIPA should direct that

      12      the contractor steps up and speaks directly to the

      13      public, to elected officials, during the time of the

      14      storm.

      15             The bifurcation problem, basically, will be

      16      solved under the arrangements we have made with this

      17      contract, and as we're moving forward, starting on

      18      January 1st of next year.

      19             Now, I was going to skip the rest of this

      20      page 5, but I do want to point out that, in the next

      21      paragraph here, the PS -- the Moreland Commission

      22      report, on page 26, says that:

      23             "The bulk of the owner-manager relationship

      24      remains the same."

      25             And one of the gentlemen from NYPA that was







                                                                   106
       1      sitting here, repeated that statement just moments

       2      ago.

       3             This is a mistaken assumption that the

       4      Moreland Commission is making.

       5             So I have three criticisms of the

       6      Moreland Commission:

       7             I believe, as I'm going to address in a

       8      moment, that they engaged in group think on their

       9      analysis of the problem;

      10             I believe that they chose not to evaluate --

      11      I don't believe, but it's obvious -- they chose not

      12      to evaluate the ServCo model;

      13             And on this point, they're making the

      14      mistaken assumption that bifurcation will be a

      15      problem during major storms in the future.

      16             Now, why they did this, is because they only

      17      read the contract.

      18             They did not read the Contract Administrative

      19      Manual, in part, because it is does exist yet.  It's

      20      still in the transitional development phase.

      21             I raised this issue at the last meeting of

      22      the LIPA Board of Directors.

      23             I asked that our general counsel address what

      24      was stated on page 26 of the Moreland Commission,

      25      and she indicated to the board that she will look







                                                                   107
       1      into this.

       2             Since that meeting, I've gotten a little more

       3      information, and I have a better understanding of

       4      where the Moreland Commission made their false

       5      interpretation.

       6             Because they only have the contract, they

       7      don't have these other documents that are still

       8      being developed.

       9             But what they're missing out on, is the many,

      10      many conversations that took out -- took place

      11      during the Brattle analysis process.

      12             And during those conversations, there was a

      13      very strongly felt feeling on the part of the

      14      trustees that, in the future, the LIPA executives

      15      should not be running press conferences and sending

      16      out press releases during the middle of a storm.

      17             That should be the responsibility of the

      18      contractor.

      19             And the intention is, that starting

      20      January 1st, that exactly will be the arrangement.

      21             I want to speak -- and the last paragraph on

      22      this page does this, I want to speak to the point

      23      that Senator LaValle raised about the

      24      bifurcated-structure concern, and whether we saw a

      25      different structure during the blizzard.







                                                                   108
       1             And my response to that is, what we saw

       2      during the blizzard is very close to what would be

       3      the structure for future storms, under the contract

       4      with PSE&G, and under the new ServCo model.

       5             LIPA would, essentially, stand down when it

       6      comes to major communication efforts, and the

       7      contractor would step up.

       8             Again, this still needs to be worked out over

       9      the period of the next several months, but, what we

      10      saw during the blizzard was the scenario where

      11      National Grid stepped up.

      12             And I can tell you that LIPA staff was still

      13      very much involved in that storm.

      14             And I spoke with one of those people that

      15      were very much involved, and they explained to me --

      16      he explained to me that he felt very strongly that

      17      he saw improved communications of information

      18      flowing through the -- through National Grid that

      19      did not take place during "Sandy".

      20             So what I'm saying here is, while I criticize

      21      the Moreland Commission's conclusions, I do agree

      22      with their point about the weakness of a bifurcated

      23      structure.

      24             And then, frankly, I think the board, as a

      25      whole, although I hesitate to speak for the board,







                                                                   109
       1      but we did vote unanimously in favor of the ServCo

       2      model, and strong opinions were expressed, that

       3      going forward, during major storms, we will not have

       4      a bifurcated structure.  We will have a clear

       5      understanding that the people doing the direct work

       6      are the ones that will be communicating directly

       7      with the public.

       8             There was a comment, also, that it -- that

       9      you couldn't solve this problem, in terms of the

      10      bifurcated structure, because it has to do with more

      11      than the parties.

      12             Yes, it has to do more with the parties; it

      13      has to do with the contract.

      14             The contract is coming to an end at the end

      15      of this year, and we have a new arrangement that

      16      will be taking place afterwards.

      17             Now, there is a misalignment of interests in

      18      the current MSA.

      19             There are reasons to break from the current

      20      contract and go with the ServCo model, that have

      21      something to do with storm response.

      22             Storm response wasn't the only issue, by any

      23      means, that was being considered.

      24             One of the issues which was touched upon just

      25      a moment ago, was the performance of the call







                                                                   110
       1      center.

       2             The call center under the current model

       3      creates a conflict in interests and incentives,

       4      where the for-profit company has an interest in

       5      running the call center in such a way to keep costs

       6      down; whereas, LIPA wants to see the call center

       7      provide to our customers, a good experience.

       8             Those two interests are not aligned.

       9             Under the new ServCo model, and it's just so

      10      frustrating --

      11             And I appreciate, Chairman Marcellino, your

      12      effort to explain to people, the complexity of some

      13      of the aspects of this relationship.

      14             -- people just don't get this, that ServCo is

      15      not a continuation of the current structure.

      16             It's a fundamental improvement of the hybrid

      17      model, and it really will dramatically change the

      18      performance of LIPA's service to the public in the

      19      future.

      20             So in the future, there will be no

      21      incentives, where his team will be saying:  Well, if

      22      we cut the number of people in the call center, you

      23      know, we're going to have to speed up how quickly we

      24      handle calls, but we can boost our profits.

      25             There will be no incentives like that in the







                                                                   111
       1      structure, because the budget for the ServCo

       2      subsidiary is kept separate from the payments made

       3      to PSE&G.

       4             A substantial improvement under the current

       5      flawed model.

       6             I believe that the case for dismantling LIPA

       7      has not been demonstrated, and this is where I

       8      believe the Moreland Commission engaged in group

       9      think.

      10             The Moreland Commission interim report does

      11      not contain any analysis of the facts in comparison

      12      to other storms or other utilities or metrics,

      13      whatsoever, to demonstrate that LIPA's rate of

      14      outage restoration after "Sandy" was a failure that

      15      warrants complete privatization and dismantling of

      16      the operations.

      17             I would like to suggest that one of the key

      18      metrics to consider, is the number of repairs that

      19      need to be made, not just the number of outages.

      20             And we also need to take into consideration

      21      that this storm occurred with a major storm surge

      22      that was unprecedented in Long Island history;

      23             That it came with a nor'easter during their

      24      restoration effort;

      25             And, that there's certain unique aspects of







                                                                   112
       1      Long Island's grid design, where wires run through

       2      backyards rather than primarily along streets, that

       3      make it more time-consuming to effectuate

       4      restoration.

       5             On the question of a metric of comparing

       6      repairs, if you look at "Hurricane Gloria," what we

       7      saw was, 11 days to achieve restoration and

       8      9,000 repairs that were done.

       9             If you look at this storm, it was 14 days to

      10      receive -- to achieve 99.5 percent restoration and

      11      up to, approximately, 40,000 repairs.

      12             I should point out that the LIPA board is

      13      meeting tomorrow, and Mr. Bruckner [ph.] is giving

      14      us a report tomorrow.  So this number of 40,000, I

      15      think, we'll get a more firm number tomorrow.

      16             But if you use those numbers, what this

      17      means, is that if LILCO were still running things

      18      today -- or, a few months ago, and they restored

      19      power after "Sandy" at the same rate that they did

      20      after "Gloria," then it could have taken about

      21      45 days to achieve power restoration.

      22             So where is the metrics that demonstrate that

      23      LIPA's performance in restoration time was such a

      24      horrendous failure that we have to throw the baby

      25      out with the bath water, so to speak?







                                                                   113
       1             I want to speak to reliability.

       2             There have been claims made that the LIPA

       3      system was maintained in such a way that it was,

       4      essentially, at the state of falling apart when the

       5      storm hit, and that's why the damage was so severe,

       6      rather than accepting that this was an historic

       7      storm of incredible magnitude; perhaps the most

       8      damaging weather event to hit Long Island in --

       9      clearly, in modern times, if not since the glaciers.

      10             And please excuse me for that, Senator.

      11             SENATOR MARCELLINO:  I wasn't here.

      12             NEAL LEWIS:  Okay.

      13                  [Laughter.]

      14             NEAL LEWIS:  Let me state for the record,

      15      emphatically, the LIPA grid was, either, the single

      16      most, or among the most, reliable grids in

      17      New York State for any above-ground utility on the

      18      day that "Sandy" hit.

      19             This claim by me is based upon established

      20      metrics that are regularly reported to the LIPA

      21      Board of Trustees.

      22             I brought with me 20 copies of the PowerPoint

      23      handout from the LIPA Trustee meeting from May 24,

      24      2012.

      25             And if, Chairman, you deem it appropriate,







                                                                   114
       1      I'd like to make this a part of the record as an

       2      exhibit, and I would encourage that people look to

       3      the second-to-last page, Slide Number 7, which shows

       4      that three major well-established metrics --

       5             I'm sure these are metrics probably used in

       6      New Jersey and other parts of the country.

       7             -- three major metrics of SAIFI, CAIDI, and

       8      SAIDI.  I'm not sure if I got the pronunciations

       9      right.  They're all acronyms.

      10             LIPA was number one for the time period being

      11      recognized here, and this is a common occurrence

      12      with LIPA's performance of the grid.

      13             So, reliability has been a top priority and

      14      goal of LIPA, and real accomplishments have been

      15      made.

      16             The former president of National Grid,

      17      Bob Catell, has said at a number of public events

      18      that the LIPA grid is a gold-plated system.

      19             And I think that those words should echo in

      20      our minds when we hear talk of selling off this

      21      system.

      22             I'm going to skip the issues of the flood

      23      surveys, and go to the other reforms I'd like to

      24      suggest.

      25             The other reforms I'd like to suggest is,







                                                                   115
       1      rather than all appointments to the LIPA board being

       2      in the hands of the leadership in Albany, I believe

       3      that local government should have an opportunity to

       4      appoint people to the LIPA Board of Trustees.

       5             This will provide coordination with local

       6      governments on tree-clearing on -- of roads, which

       7      is a critical issue after a storm, and on other

       8      issues, and on overall emergency planning.

       9             I believe the county executives of the two

      10      counties should have appointments, the 10 largest

      11      towns should have appointments, and then the smaller

      12      towns and the villages and the two cities should get

      13      a certain number of rotated appointments.

      14             My second additional suggestion, is that we

      15      should have a unified emergency response under the

      16      OEM.

      17             I believe that the annual hurricane drill

      18      that LIPA holds should be held at the two county

      19      offices of the Emergency Management, and LIPA should

      20      be more clearly integrated into the function and

      21      command structure of the OEMs.

      22             In my opinion, both county OEMs performed

      23      well during "Superstorm Sandy," and it makes sense

      24      to build upon what worked.

      25             The OEMs are well equipped with







                                                                   116
       1      communication capabilities that can be relied upon

       2      during storms and in other crises, and I therefore

       3      believe that working with them is a good way to

       4      improve communications during the next major storm.

       5             I would also like to make a recommendation

       6      that builds upon some of the work that came out of

       7      the Senate after "Tropical Storm Irene," having to

       8      do with coordination with municipalities.

       9             And on this one, I recommend that we develop

      10      formalized memorandums of understanding, or,

      11      "MOUs," to be adopted by LIPA and Long Island

      12      municipalities, that should anticipate specific

      13      series of different contingencies, set out

      14      responsibilities between the parties, and they

      15      should be enforceable.

      16             And lastly of my reforms that I'd like to

      17      suggest in addition to the ServCo model, I believe

      18      that we should, simply by law, provide for a PSC

      19      review of LIPA, and end the debate about that issue.

      20             I think it's been an overblown issue, and I

      21      think that if it can bring an air of accountability

      22      and improve public confidence in the system, then we

      23      should simply -- we should simply do it, in my

      24      opinion.

      25             The -- I believe there's a strong basis to







                                                                   117
       1      believe that the ServCo business model approved by

       2      the board of trustees, and the State -- this went

       3      through several layers of review -- will deliver the

       4      best results for Long Islanders who want reliable,

       5      affordable electric service that is delivered by a

       6      corporate structure well designed to respond to

       7      major storms, and to advance public-policy goals,

       8      such as being the leader in promoting energy

       9      efficiency and renewables.

      10             I also believe that the ServCo model can be

      11      further enhanced, by giving local government

      12      officials who work with LIPA the ability to appoint

      13      trustees, by unifying emergency planning and

      14      responses by LIPA with the existing offices of

      15      Emergency Management, by adopting MOUs to establish

      16      clear agreements for tree-clearing from roads with

      17      local governments, and, lastly, by subjecting LIPA

      18      to PSC review.

      19             That's the end of my abbreviated version of

      20      prepared comments, and I do hope my whole comment --

      21      written comments get into the record.

      22             SENATOR MARCELLINO:  Your comments will be

      23      part of the record, as all of the comments,

      24      including the PowerPoint presentation that you made.

      25             And I thank you both for your testimony.







                                                                   118
       1             Just a question for both of you.

       2             I'm a consumer.  I live in the LIPA area.

       3             My house was without power for two weeks.

       4      14 days.

       5             I had to call in to LIPA to tell them my

       6      house was without power.

       7             They didn't know it.

       8             They had no idea of the fact that my house

       9      was without power.

      10             The cable company, whose power lines use the

      11      same poles, traveled into my house pretty much the

      12      same way that the LIPA lines do, can tell me if I'm

      13      on their system or not; when I'm on, when I'm off,

      14      what I'm watching.

      15             They can fix my cable problem, if I have a

      16      problem, over the phone.

      17             They can deal with all of that from, I don't

      18      know what distance, but they're certainly not in my

      19      house at the time.

      20             Yet I had to call LIPA to let them know that

      21      the power line was down.

      22             It took them 14 days to get to my house.

      23             I'm not surrounded by a million trees.

      24             The transformer, yes, it's in the rear yard,

      25      no doubt about that.







                                                                   119
       1             The line was taken down by a fallen tree in a

       2      neighbor's yard.

       3             All that's true.

       4             But the system of communication between LIPA

       5      and the customer simply is nonexistent, as the

       6      process goes right now.

       7             There is no communication, and I don't

       8      understand that.

       9             Will this change under the new agreement with

      10      PSE&G, or under the ServCo model that you're talking

      11      about?

      12             NEAL LEWIS:  This is a technology question.

      13             I defer.

      14             DAVID DALY:  Yeah, I mean, I would -- there's

      15      a couple of issues that we've made recommendations

      16      around, one of them has to do with technology.

      17             And one of the most important technologies in

      18      storm-outage situations is a system called an

      19      "outage management system."

      20             The system that's in place today is a very

      21      old mainframe-based system.

      22             It results in work being done with

      23      footboards, and on a much more manual basis than

      24      modern systems.

      25             These types of systems bring you a couple of







                                                                   120
       1      things:

       2             First, at the beginning of a storm event,

       3      they give you a much more -- a much quicker and a

       4      much more accurate assessment of where the damage

       5      is; number one.

       6             Number two, as the storm's progressing, you

       7      have thousands and thousands of crews out performing

       8      work.

       9             Starting at 7:00 in the morning, check in at

      10      1:00 in the afternoon, you check in at 10:00 at

      11      night.

      12             These modern outage management systems are a

      13      mechanism to understand what work is getting

      14      accomplished.

      15             The crews are out in the field accomplishing

      16      the work and statusing it, not through a manual

      17      process, but in the system, comes back.

      18             And, so, you have a much better understanding

      19      of where to send the crews, because you know the

      20      damage up front much quicker.  And once they're out

      21      there at their statusing work, hour to hour, day to

      22      day, typically, you check in twice a day during a

      23      storm event around how much progress we've made.

      24             And what that gives is, the management --

      25      storm-restoration management team, realtime







                                                                   121
       1      information about where the damage is, and what the

       2      status is.

       3             I think that one of the issues we've seen,

       4      is that with the technologies that is in place there

       5      today.

       6             Now, we've made this recommendation, we

       7      intend to have it in place in the next 12 months,

       8      is that you're at a little bit of a handicap in

       9      really understanding where to send the crews, and

      10      more importantly, as work is getting accomplished

      11      and getting updated, being able to stand up at a

      12      press conference or in a communications forum and

      13      give an accurate picture of what work we

      14      accomplished today; is this circuit back or not?

      15             So, there is -- there is a piece of this

      16      related to this outage management system, and we are

      17      correcting that.

      18             Secondly, somewhat driven by the availability

      19      of the system, one of the processes we use at PSE&G

      20      that we intend to replicate here --

      21             And by the way, we intend to replicate our

      22      entire storm process on Long Island.

      23             -- is a process where, for each municipality,

      24      we have an individual conference-call meeting each

      25      morning and we provide them with a three-day plan.







                                                                   122
       1             That meeting starts one-on-one with each

       2      municipality, with:

       3             How many customers are out today?

       4             What crews are going to be in your town

       5      today, tomorrow, and the next day?

       6             So it's a story that starts with, for

       7      example, and I'm making these numbers up, you have

       8      14,500 customers out today.  We're going to have

       9      X amount of crews in your town today.  By tomorrow,

      10      you're going to be down from 14,000 to 12,000.  The

      11      next day down 8,000, the next day down to 4,000.

      12             So we do a rolling three-day picture of what

      13      is happening in that town, and they can watch and

      14      trend this piece coming down.

      15             And the combination of those two things

      16      gives us a great deal of information about what

      17      the current status is.

      18             Just one other piece, though, which is, you

      19      don't have on Long Island smart meters.

      20             Smart meters, sometimes called

      21      "AMI advanced meters," are the only source, when you

      22      get down to the very last meter, to have the

      23      information coming back automatically to the utility

      24      about whether a customer is back or not.

      25             I think some of the problems that you







                                                                   123
       1      experienced are not as much related to having

       2      smart meters in place.  And the implementation of

       3      smart meters is really a public-policy issue about

       4      whether or not that makes sense.

       5             They make sense, they have a lot of -- they

       6      bring a lot of benefits.

       7             To make them work, you need to put in place

       8      pricing schemes which charge people more for

       9      electricity at this time of day versus another time

      10      of day, so there are implications for what makes

      11      them economic and make them work.

      12             But, there's two pieces to your question.

      13             I think the lion's share of the concern you

      14      just expressed, we will be addressing through the

      15      outage management system that we're installing and

      16      our communications processes that I've just been

      17      describing.

      18             SENATOR MARCELLINO:  I'm just -- you guys

      19      were sitting here when I was questioning the

      20      previous panel.

      21             My concern is, the providing of the service

      22      without a rate increase; without costing the

      23      taxpayer, the ratepayer, an exorbitant amount of

      24      money.

      25             As you heard from Assemblyman Graf, we pay a







                                                                   124
       1      lot of money for the power.  We're paying huge

       2      amounts of money at every level of government.

       3      The government is paying the electric bills, a

       4      huge amount of money that goes into the tax base,

       5      goes into the property-tax base.

       6             And he's right, it's an inhibition to

       7      business.

       8             How are you going to change that system?

       9             I understand in the PSE&G contract, there are

      10      performance standards which would enhance the

      11      efficiency of the system.

      12             Now, how -- can you go through a little bit

      13      of that?  Is that -- what that system is?

      14             And, Neal, I'd look to like at -- you seem to

      15      be implicating that Moreland is more -- has pretty

      16      much bought into private.  Privatization, that

      17      they're looking at nothing else but privatization.

      18             NEAL LEWIS:  Well, I do want to say --

      19             SENATOR MARCELLINO:  I'd like to get both

      20      those questions answered, though.

      21             NEAL LEWIS:  Right.

      22             -- on the -- it's fascinating that the way in

      23      which Moreland is looking at privatization does seem

      24      to be different than Brattle, because Brattle said

      25      that the biggest savings that comes from







                                                                   125
       1      privatization, they show some savings in certain

       2      categories, and then increased costs in other

       3      categories, and when it all washes out, it's a

       4      significant increase.

       5             Brattle was emphatic that it did not make

       6      sense to continue to analyze privatization after a

       7      certain point.  It wasn't even a close call.

       8             The -- but on the positive side for

       9      privatization, the number one -- biggest improvement

      10      is cutting taxes.

      11             Basically what they're operating under is an

      12      assumption that a private utility is going to

      13      aggressively fight to reduce the property taxes, and

      14      fight to reduce the pilot payments.

      15             After that, they talk about labor.

      16             And I think you may be hearing a little bit

      17      later from some other speakers on this topic, but

      18      LIPA had the -- the workforce that services the

      19      electric system on Long Island -- we all know they

      20      worked primarily under National Grid's name -- is

      21      much smaller than what existed years ago.

      22             And it's really a troubling thought to think

      23      that a major way that privatization can keep costs

      24      down is going to be to fight the taxes and cut

      25      labor, and, how does that enhance performance during







                                                                   126
       1      a storm?

       2             And those tax cuts, by the way, are going

       3      to be made up for, likely, by tax increases.

       4             You know, if LIPA pays less in a certain

       5      community, then those communities are going to have

       6      to make up for it.

       7             It was the Legislature that required LIPA to

       8      pay those taxes.

       9             And when we compare LIPA's rates to other

      10      utilities, it's often said it's among the highest,

      11      but let's be clear what we're talking about.

      12             If you compare it to the rest of the country,

      13      50 percent of the country gets their electricity

      14      from coal, which is dirty, but it's also cheap.

      15             So comparing us to those is really unfair.

      16             If you compare it to other public utilities,

      17      the other public utilities don't pay for the

      18      property taxes.

      19             Our property tax payments by LIPA are larger

      20      than our debt service on the debt that we have that

      21      we hear so much about.

      22             If you compare it to public utilities on

      23      Long Island, Rockville Center, Freeport, they get --

      24      they don't pay the property taxes.  And they also

      25      get -- NYPA was sitting here -- NYPA sends







                                                                   127
       1      electricity to Freeport, or it's done in a very, you

       2      know, complicated way, but the bottom line is, they

       3      get low-cost electricity because of NYPA.

       4             So comparing these prices of rates --

       5             SENATOR MARCELLINO:  And LIPA can't do that?

       6             NEAL LEWIS:  Well, under the --

       7             SENATOR MARCELLINO:  I think that was

       8      Assemblyman Graf's point.

       9             LIPA can't do that?

      10             NEAL LEWIS:  Well, just a changing of that

      11      law, you know, if you guys can get that law changed,

      12      it's in the law right now that none of the

      13      hydropower can come to Long Island.

      14             So, if we could get some of that, that would

      15      go a long way.

      16             DAVID DALY:  And to your initial piece, on

      17      the cost and on the performance, we intend to bring

      18      excellence in operations from New Jersey and

      19      replicate it on Long Island.

      20             There are three main buckets that we intend

      21      to make significant improvements in, that we think

      22      will immediately begin to move the metric for --

      23      described in one moment.

      24             Technology, I just described the OMS system.

      25             There's a couple other customer-facing







                                                                   128
       1      technologies.

       2             Number one, technology.

       3             SENATOR MARCELLINO:  Can you speak up a

       4      little bit, please?

       5             You have to speak up a little bit, or move

       6      the microphone closer to you.

       7             DAVID DALY:  Number two --

       8             So, technology, number one.

       9             Number two, replicating work processes from

      10      PSE&G in customer operations in T&D.

      11             Particularly in the customer operation side,

      12      on our customer-satisfaction processes:

      13             How we listen to the customer;

      14             How we deal with customer complaints;

      15             How we take that information, develop

      16      targeted initiatives, dedicate resources, use

      17      advanced models for developing targeted

      18      initiatives.

      19             How we have an approach, which is, use every

      20      customer complaint as an opportunity for

      21      improvement, and where we engineer out process

      22      deficiencies based upon what we learn in surveys and

      23      from customer complaints.

      24             And then, thirdly, the storm process.

      25             So, technology, some key process changes in







                                                                   129
       1      customer ops in T&D, and storm.

       2             When you look at the incentive structure that

       3      we have under the contract, there's 29 metrics

       4      covering cost metrics, customer satisfaction, and

       5      reliability.

       6             And Mr. Lewis just talked a moment ago

       7      about reliability on the system.

       8             The assets that are in place on Long Island

       9      are in good shape.  They have been invested in over

      10      the years, so the physical assets -- the

      11      substation, the breakers, the wires -- are in

      12      sound condition.

      13             The employees that are in place at

      14      National Grid, that we will bring over as part of

      15      our company, are a highly trained, highly skilled,

      16      dedicated workforce.

      17             So, we have good resources, we have good

      18      assets.  We're going to bring process.

      19             In terms of the metrics, on the cost side,

      20      our intention is to keep costs flat.

      21             Our challenge is to do that while taking

      22      reliability and keeping it where it is --

      23             Because as Mr. Lewis just said, reliability

      24      is good, based on the assets, and based on the

      25      fact that you have a good workforce.







                                                                   130
       1             -- keeping reliability where it is, but

       2      taking customer satisfaction from what is

       3      essentially the basement today, and bringing it up

       4      to top quartile.

       5             You bring the customer up to the top

       6      quartile, and reliability stays up there, costs,

       7      relatively flat.

       8             In our structure, there is a gate that we

       9      have to get through to earn any incentive

      10      compensation.  Regardless of what happens with

      11      reliability and customer service, if we don't make

      12      our budgets, we get no incentive compensation.

      13             So that is a gating function at the beginning

      14      of the incentive structure, that they must be

      15      accomplished no matter what happens on the other

      16      two.

      17             So, we're very confident that -- we're not

      18      going turn this aircraft carrier around on a dime.

      19      We have a one-year plan, a three-year plan, a

      20      five-year plan.

      21             Within five years, we will have a utility

      22      on Long Island that is a best-in-class utility

      23      across all areas of cost, reliability, customer

      24      service.

      25             And we're very confident we'll get there, and







                                                                   131
       1      we think the incentives are set up to get us there

       2      without raising cost significantly.

       3             As I said, we're going to keep reliability

       4      where it is, move customer, keep costs flat.

       5             NEAL LEWIS:  If I could add one other point

       6      regarding rates, it's unlikely the rates are

       7      going to come down, although, it's just, sort of,

       8      keep them from going up further.

       9             But one thing we can do, is reduce bills.

      10             So, a business that's struggling to pay the

      11      high rates we have for electricity on Long Island

      12      can reduce its bills, and that's what really matters

      13      to them.

      14             And the way to do that is through the

      15      efficiency programs.

      16             And LIPA has an efficiency program, which if

      17      you look at the chart for funding of it, it just

      18      goes up rather dramatically.

      19             This year, we're at $120 million.  It's

      20      perhaps the strongest efficiency program of any

      21      municipal utility in the country.

      22             And as the years go forward, it's going to

      23      be that much stronger, and it's going to gear more

      24      and more into the commercial sector.

      25             So with the strategy that you just heard,







                                                                   132
       1      about how we can keep the rates steady where they

       2      are, and then combine that with efforts to provide

       3      incentives to help commercial customers improve

       4      efficiency at their operations, they can see

       5      significant reductions in their bills, not in

       6      their rates.

       7             And this is, I think, the right strategy to

       8      deal with the issue of the high rates that we pay

       9      for electricity on Long Island.

      10             SENATOR MARCELLINO:  I have just one last

      11      comment, and I'll turn it over to my colleagues.

      12             My criticism of LIPA, it's legion, but in my

      13      mind, they've done a lousy job in maintaining their

      14      own infrastructure.

      15             There are poles in my neighborhood where the

      16      bottom is -- the base of the pole is just rotted

      17      away.  It's being held up by the wires, not by the

      18      pole.

      19             So when they cracked, when they broke down

      20      during Sandy, no big surprise.

      21             When the tree that took them down, it was

      22      their own weight and the weakness of the pole.

      23             Minimal putting stuff underground.  You can't

      24      put it all underground, I understand that, that's

      25      not a panacea by any means, but a lot of it can go







                                                                   133
       1      underground, and should be.

       2             The tree trimming, it's almost non-existent.

       3             What they do is almost cosmetic, at best,

       4      along certain avenues, but they don't get into back

       5      yards, they don't get into people's -- and I know

       6      that's not simple, but it's not being done in any

       7      effective way.

       8             You can walk down any -- go down any street

       9      in any neighborhood you want, and you can see

      10      trees hanging over lines, sitting there, where a

      11      strong wind or an aging branch with some snow on it

      12      is going to take the whole system down.

      13             They're not doing that now.

      14             So, there's a lot of that that I would look

      15      to see, if PSE&G does take over, and then, if this

      16      whole thing moves forward, under whatever system,

      17      that that sort of thing has to go forward.  That

      18      there has to be some uniformity.

      19             I don't necessarily agree with Bob Catell

      20      that this was -- that this is a gold-plated system.

      21             It may have been at one time, but I don't

      22      think it is anymore.

      23             So I think there's -- there's a tremendous

      24      amount of work, going forward.

      25             But key element of this whole thing, and I







                                                                   134
       1      know that may not be the simplest thing:

       2             We have an excellent workforce, they do a

       3      job.  I'm glad to hear that you would bring them

       4      over and keep these people, and I'd hate to see the

       5      fact they would go away.

       6             I'd also hate to see the fact, going forward,

       7      that we be looking at the closure of more power

       8      plants, going forward.

       9             We're -- there's two in my district that are

      10      going.

      11             I know Senator LaValle has a problem in

      12      Port Jefferson, other areas as well, where tax

      13      certioraris being filed where they want to close

      14      power plants, that impact on school districts, on

      15      municipalities, towns, and villages, is huge.

      16             So that poses problems, going forward.

      17             I'd like to see, you know, in any plant, some

      18      forward-thinking as to what's there, what's going to

      19      happen to these plants.

      20             The youngest of the big ones is North Port,

      21      and I think that the youngest power plant you've got

      22      of its size was built in 1978.

      23             So, we have an aging infrastructure, and I

      24      think we have to look at that as well.  And that has

      25      to be taken into consideration of any plan, going







                                                                   135
       1      forward.

       2             DAVID DALY:  Just to -- on the -- certain

       3      programmatic -- aside from capital investments in

       4      the substation-part asset, certain programmatic

       5      expense items, including pole inspections and tree

       6      trimming, are two characteristics of best-in-class

       7      utilities.

       8             Poles, typically, are inspected on an

       9      eight-year cycle.  You go out and do an inspection,

      10      and you assign a condition assessment.  Poles that

      11      are in the worst condition get replaced immediately,

      12      but there is a rigorous adherence to an

      13      eight-year cycle.

      14             Similarly with trees, on our system it's a

      15      four-year cycle.  We employ one of the best-in-class

      16      practices in the industry on trees, where we

      17      don't just take our system and divide it by four,

      18      and then trim a quarter of the system every year,

      19      but we have vegetation-optimization models which

      20      understand, where the growth is, what the outage

      21      history has been in those areas, and we target the

      22      investment.

      23             So one of the characteristics of excellence

      24      in operations is sticking very rigorously to

      25      preventive maintenance, programmatic-type







                                                                   136
       1      programs, pole inspections, tree trimming,

       2      et cetera.

       3             And you can count on the fact that that's how

       4      we run our operation.

       5             NEAL LEWIS:  And if I could just add on the

       6      issue of the old power plants, Paul DeCotis, one

       7      of LIPA's vice presidents that deals with power

       8      markets, went through a very extensive process,

       9      very professionally conducted.

      10             There were some people who disagreed.

      11             Some of the environmental groups said, you

      12      know, they didn't want to see a strategy to do

      13      anything with old power plants.

      14             But, he brought that process through, and it

      15      provides -- it's a complicated thing, but it

      16      provides a series of what they call "off ramps,"

      17      where a series of decisions will be made about

      18      repowering.

      19             I think the board has at least got a major

      20      accomplishment in the sense that that contract was

      21      completed.  It may not have been approved by the

      22      State yet, but it was, at least, the new PSA with

      23      National Grid was completed, and it sets in motion

      24      opportunities for repowering and evaluating these

      25      old plants, which I think is long overdue.







                                                                   137
       1             I do have real concerns, under

       2      privatization, what happens to repowering.

       3             Repowering is not free.

       4             So, I could see a private company choosing

       5      not to repower the old plants, and just sort of

       6      running them until they're completely too old to be

       7      worth continuing.

       8             So, I do think the repowering issue is one of

       9      the issues that needs to be addressed in this

      10      privatization discussion.

      11             SENATOR MARCELLINO:  Senator LaValle.

      12             SENATOR LAVALLE:  Thank you.

      13             Mr. Daly, you heard discussion that we had

      14      with the prior panel.

      15             DAVID DALY:  Yes.

      16             SENATOR LAVALLE:  And it seemed that Moreland

      17      talked about privatization.

      18             You are involved with a contract, although,

      19      if it is negated, you come away 7 million to the

      20      good.

      21             But, right now, you are proceeding as if you

      22      are going to be part of the ServCo model and begin

      23      operating in January of 2014?

      24             DAVID DALY:  Yes.

      25             And just -- I actually need to correct the







                                                                   138
       1      previous speaker on the question of the termination.

       2             Under the contract, there is no

       3      "termination for convenience" clause.

       4             There are two reasons that LIPA could

       5      cancel this contract:

       6             One of them is, if we were in breach of the

       7      contract.  And there's six or seven events of

       8      default that put us in breach.

       9             But LIPA did include in the contract a

      10      provision that said, if at any time over the

      11      ten-year period they went to privatization, or to

      12      municipalization, that they could terminate the

      13      agreement without any penalty.

      14             And that the only issue that would come up

      15      then, is that we would be paid -- PSE&G would be

      16      paid any unpaid cost to date, which would be --

      17      because we're being paid on a monthly basis, would

      18      not amount to much, and any unwinding costs.

      19             The $7 million -- I wish there was a

      20      $7 million fee, but I'm afraid there isn't.

      21             The $7 million fee that was being referred to

      22      is actually in another section of the contract which

      23      involves, if PSE&G had the change in control, then

      24      LIPA has the opportunity, within 30 days, to

      25      terminate the agreement.







                                                                   139
       1             If they do, we have to pay a $7 million fee.

       2             That fee occurs in 2014, and it actually

       3      ramps down all the way to zero by 2020, but that's

       4      a fee that we pay LIPA if we have a change in

       5      control.

       6             So just to be clear, LIPA did have the

       7      thought that they might move to municipalization or

       8      privatization, and they can terminate the agreement

       9      with no penalty; just, paying us our out-of-pocket

      10      costs, and making us whole, which would amount to --

      11      wouldn't amount to very much.

      12             With respect to your question:

      13             Absolutely, we are -- we've been there for a

      14      year.  We had a two-year transition.

      15             The first year was focused on understanding

      16      how work is getting done today, and what we need to

      17      do to implement, to bring the PSE&G -- to replicate

      18      the PSE&G process in 2013.

      19             So, that was our due-diligence phase.

      20             We have a very detailed work plan, and we are

      21      implementing -- I mentioned, for example, in the

      22      customer-operations area, in my testimony, that

      23      we're implementing 80 recommendations to improve

      24      customer service in 2013.

      25             But, we are marching on that plan, and we'll







                                                                   140
       1      be ready on January 1, 2014.

       2             SENATOR LAVALLE:  As you know, we're -- we're

       3      at a point in time where there's a lot of discussion

       4      about privatization.

       5             It has come to my attention that a lot of the

       6      utilities, including your own, have been approached

       7      for, "Are you interested in privatization?"

       8             Some of the utilities have -- I mean, this is

       9      all rumor, of course -- have said no.

      10             Where are you in all of this?

      11             I know you've been approached.

      12             DAVID DALY:  And if you would forgive me, you

      13      know, we are concentrating on the transition to be

      14      ready.

      15             With regard to the privatization, as I think

      16      one of the previous speakers says, you know, from

      17      a strategic point of view, we evaluate all

      18      opportunities, but, I'm really not in a position to

      19      discuss, you know, our position on that.

      20             But -- so I would appreciate it if you would

      21      forgive me, but --

      22             SENATOR LAVALLE:  Yeah, but you have been

      23      approached?

      24             I mean, I'm right about that?

      25             DAVID DALY:  Depends on what -- what do you







                                                                   141
       1      mean by "being approached"?

       2             SENATOR MARCELLINO:  It's the definition of

       3      is?

       4                  [Laughter.]

       5             SENATOR MARCELLINO:  It all depends on what

       6      the definition of is, is?

       7             Okay.

       8                  [Laughter.]

       9             DAVID DALY:  I mean, I would say that we've

      10      had conversations which probably went like this

      11      one, which would say, you know:

      12             We're concentrating on what we're doing.

      13             We do understand that there's a public-policy

      14      discussion going on that we are not involved in that

      15      is happening in parallel.

      16             We're not letting it distract us.

      17             To the extent it results in a change in the

      18      structure -- as I said, the contract allows for

      19      that -- we would evaluate it.

      20             And -- but I'm really not at liberty to say

      21      much more.

      22             So, yes, I would say we've had, you know,

      23      discussions about the fact that this is happening in

      24      parallel.

      25             SENATOR LAVALLE:  Okay.







                                                                   142
       1             Just skip to another issue:

       2             I know -- I don't know whether you yourself

       3      were at the meeting at Stony Brook, where we had a

       4      discussion with LIPA, National Grid, and you had

       5      representatives at that meeting, dealing with

       6      communication.

       7             And Senator Marcellino is absolutely right,

       8      he doesn't realize the depth of the problem.

       9      Certainly, your people do.

      10             At that meeting at Stony Brook, with people

      11      from B&L, and those discussions are continuing, on

      12      how we can improve the communications system.

      13             I remember making a comment, that it reminded

      14      me of days gone by when my brother and I were

      15      young, and we played around with tin cans and a

      16      string that we waxed, and we would communicate

      17      between rooms.

      18             It is -- it is, really, very, very bad.

      19             And it depends -- the system as it exists,

      20      depends on Senator Marcellino and other ratepayers

      21      calling up --

      22             DAVID DALY:  Yes.

      23             SENATOR LAVALLE:  -- and saying, "I've got a

      24      broken wire."

      25             And, in the age of sensors, and he







                                                                   143
       1      adequately described what is done, and we've all

       2      experienced that with Cablevision, that you can --

       3      that they know what's going on and can fix it with

       4      the individual who is the complainant.

       5             So this requires, on your part, a big

       6      investment, I would imagine?

       7             DAVID DALY:  It's a very significant

       8      investment.  It's called "advanced metering

       9      infrastructure."

      10             Two years ago, there was 13 million

      11      customers in the United States on that type of

      12      system.  Today there's about 40 million.  It's

      13      probably going to double in the next three or

      14      four years.

      15             But, it's a very significant investment.

      16      It's probably between 500 million and a billion

      17      dollars.

      18             So, it really becomes a public-policy

      19      issue.

      20             We -- it brings benefits, as I said

      21      earlier.

      22             It is very hard to make them -- to make the

      23      economics work on those systems if you do not

      24      implement it along with what's called "time-of-use

      25      pricing."  And that has a lot of concerns --







                                                                   144
       1      raised a lot of concerns in a lot of areas.

       2             But, it's a technology that is very

       3      expensive, that's coming, it's growing.  And, it's

       4      certainly an option on the table.

       5             And we did, as part of our transition work,

       6      put together an assessment of what that might look

       7      like, what it would cost.

       8             And, so, it's something that could be

       9      considered, but, it really is something that needs

      10      to be decided, from a public-policy point of view,

      11      first and foremost.

      12             SENATOR LAVALLE:  Right.

      13             DAVID DALY:  Because you're absolutely right,

      14      we -- the system that is there, these -- now, as I

      15      said before, the outage management system that you

      16      have versus the one that we're going to put in,

      17      which is probably more of 20- or 30-million-dollar

      18      investment, not 500 to a billion, will get you a

      19      very, very big improvement in your communications

      20      today.

      21             But, what you're talking about is -- is, that

      22      kind of investment, and it was principally

      23      implemented in California, initially, and now it's

      24      been growing around the country.

      25             SENATOR RANZENHOFER:  I would hope that you







                                                                   145
       1      would monitor the meetings that are going on.  I

       2      know you have people --

       3             DAVID DALY:  Yes.

       4             SENATOR LAVALLE:  -- that are in attendance

       5      at Stony Brook, with B&L.

       6             I was glad to hear, because, you know, part

       7      of any system, the strength of the system depends on

       8      its employees.

       9             And, there may be management problems, and

      10      wrong protocols, but I would say that, and

      11      Senator Zeldin pointed out, one of many people who

      12      really did a great job.

      13             DAVID DALY:  Yes.

      14             SENATOR LAVALLE:  And we don't give enough

      15      attention to the people who are up on the buckets,

      16      fixing lines, and at some peril.

      17             Repowering is critically important --

      18             DAVID DALY:  Yes, it is.

      19             SENATOR LAVALLE:  -- to the membership of the

      20      Long Island delegation, I could say that.  You know,

      21      it's very, very important.

      22             And, I just want to remind everyone that, for

      23      a couple of years, and there were vetoes there,

      24      there was a LaValle-Sweeney bill, or, a

      25      Sweeney-LaValle bill, to enhance the oversight by







                                                                   146
       1      the PSC, with LIPA.

       2             And you indicated you favored --

       3             NEAL LEWIS:  Yes, I do.

       4             SENATOR LAVALLE:  -- that.

       5             NEAL LEWIS:  Yes, I do.

       6             I think the concern over the years has

       7      been, that LIPA's ability to do rate increases

       8      without that oversight has helped when it goes to

       9      the bond market, to keep its bonds lower, because

      10      those people buying the bonds see that LIPA has

      11      the ability.

      12             SENATOR ZELDIN:  Right.

      13             NEAL LEWIS:  But, I just -- I just think from

      14      all the conversations I've had with people, and

      15      the meetings I sat through, that I think that's just

      16      an overstated benefit, and it doesn't overcome the

      17      downside of the perception that the board, and LIPA

      18      as a utility, is not subject to oversight.

      19             And, so, I think that the advantages

      20      outweigh that.

      21             So I absolutely agree with your bill, and I

      22      think that that's the way we should go as part of a

      23      package.

      24             And, frankly, on a point that

      25      Senator Marcellino made, if we could somehow, I







                                                                   147
       1      think -- you know, if we could resolve some of these

       2      other big issues so we could all start to move

       3      forward, and have a five-year plan to be a

       4      best-in-class utility, that, to me, makes a lot of

       5      sense, so the other big issues, maybe trying to

       6      resolve some of these certioraris, as a package, and

       7      let's get these issues moving forward.

       8             And the day that you do a repowering of any

       9      existing plant, you immediately cut in half the

      10      greenhouse-gas emissions coming out of that plant

      11      for the same amount of electricity it generates.

      12             So, I'm with you on that.

      13             SENATOR LAVALLE:  Well, the reason we have

      14      hearings, is to have an open discussion and a

      15      dialogue, and, we need to hear more, and there will

      16      be people who will be testifying.

      17             But the ServCo model, you know, people have

      18      to go out and advocate for that, and show that we

      19      can have reliability.

      20             NEAL LEWIS:  Right.

      21             SENATOR LAVALLE:  We can have stability in

      22      our rate structure.

      23             But you have to go out, and other people on

      24      the island have to go out, and -- and do that.

      25             NEAL LEWIS:  Yeah.







                                                                   148
       1             SENATOR LAVALLE:  And I commend

       2      Senator Marcellino for this hearing, because it

       3      gives people an opportunity, Mr. Daly, to hear

       4      from you, and what you hope to achieve as part of

       5      that ServCo model, I think puts something on the

       6      table that needs exploration, maybe some

       7      fine-tuning, so --

       8             And thank you for testifying.

       9             DAVID DALY:  Just on your comment on the

      10      employees, I did mention, and I mentioned to

      11      Senator Zeldin at the break, we have assessed the

      12      employee population that we'll bring over,

      13      approximately 2,200 employees.  And they are very

      14      well trained, very well skilled, dedicated

      15      employees, so we're very happy to bring them over.

      16             And it is -- one of the parts of our

      17      culture is the importance we place on the employee,

      18      and their safety, and their well-being.

      19             So, we're looking very forward to working

      20      with them, bringing over both the IBEW 1049

      21      workforce, management.

      22             Senator Zeldin mentioned some folks at LIPA

      23      itself.

      24             There are some talent there that we intend to

      25      put to use, and put some good leadership, and some







                                                                   149
       1      good structure, some good processes, a little bit of

       2      technology, and we put it all together, and we have

       3      a best-in-class utility.

       4             SENATOR LAVALLE:  Thank you.  I appreciate

       5      that.

       6             SENATOR ZELDIN:  Well, if I could actually

       7      pick up right where we're leaving off:

       8             Do you have an idea of -- I mean, you

       9      mentioned 2,200 people coming over, but what do you

      10      envision, if we were to move to privatization, what

      11      does the workforce look like in total numbers?

      12             DAVID DALY:  I haven't looked at the

      13      privatization.

      14             What -- so, the number, just to be clear,

      15      Senator, was the -- we're setting up a separate

      16      entity called "ServCo," and that's an entity that

      17      has between twenty-two and twenty-three hundred.

      18             The privatization model, I have not looked at

      19      that model in detail.

      20             SENATOR ZELDIN:  I guess then, generically,

      21      how -- what size a workforce do we need?

      22             I mean, what -- one of the problems that we

      23      are experiencing, is that, when we get hit hard,

      24      like "Sandy," where you have as many people without

      25      power as there were, is it -- there just aren't







                                                                   150
       1      enough -- there just aren't enough people.

       2             And if, you know, we're trying to pull --

       3      support from, you know, the Hudson Valley or the

       4      city or New Jersey or Connecticut, and they're

       5      getting hit as well, then you have to reach even

       6      further, and that might take some time when they're

       7      driving from Alabama or, you know, California, to

       8      get across the country.

       9             So, like, what's the stabilized workforce?

      10             I mean, what should we be advocating for?

      11             DAVID DALY:  Yeah, twenty-two,

      12      twenty-three hundred is the stabilized workforce.

      13      That's in the range.

      14             By the way, when we put that organization

      15      design together, we benchmarked it, and it

      16      benchmarks at top quartile in terms of staffing

      17      level.  It's right at the top quartile measure.

      18             It's not top decile.  It's right on the

      19      border between the first and the second quartile.

      20             So, we designed it to a top-quartile staffing

      21      level, and it's just under 2,300.

      22             So -- but to get to your question on the

      23      storm, you need a lot more than I mentioned.

      24             At PSE&G, during "Sandy," we had up to

      25      5,000 employees.







                                                                   151
       1             We're going to replicate our storm process,

       2      and that involves, in terms of people, and

       3      staffing, making use of our skilled resources within

       4      that group, the balance of that 2,200 group, and

       5      then alliances with local and regional

       6      contractors; and then, lastly, the mutual aid

       7      between utilities.

       8             So it's a combination of those factors that

       9      get put together, pre-plan, particularly in the

      10      contract side, right-of-first-refusal

      11      arrangements.  And, we're very confident that we

      12      don't have any issues with resources.

      13             SENATOR ZELDIN:  I mean, is that a -- that,

      14      2,200-, 2,300-person number, is that a -- it seems

      15      to be a reduction from where we were, say, during

      16      "Hurricane Gloria."

      17             DAVID DALY:  During where, Senator?

      18             SENATOR ZELDIN:  I mean, if you go back,

      19      looking historically, you know, looking back to the

      20      '80s, you know, when we got hit by

      21      "Hurricane Gloria," the workforce was probably a lot

      22      higher than that.

      23             DAVID DALY:  Yeah, I -- just to be clear, the

      24      twenty-two, twenty-three hundred is your "blue sky"

      25      steady state staffing.







                                                                   152
       1             During any storm event, the most important

       2      aspect of an effective storm response is very

       3      quickly assessing the damage up front.

       4             That's what the outage management system

       5      helps you do.

       6             With a very quick assessment of what the

       7      damage is, you can understand, communicate to

       8      people, a realistic expectation of response times,

       9      and you can then plan how many resources you need:

      10      Do I need 3,000 more on top of the 2,200, or do I

      11      need 6,000 more?

      12             So, part of the storm process is, very

      13      quickly, getting the damage assessment, not running

      14      out and starting to put things up first.

      15             Just take your time, in terms of getting it

      16      right, in terms of what the damage is within the

      17      first 12 to 24 hours, and then you plan from there.

      18             So, the 2,200 is your steady state.  And

      19      depending on the size of the storm, it all -- it

      20      will flex, from -- from -- anywhere from, getting it

      21      done with the twenty-two hundred, up to, you know,

      22      four or five thousand, six thousand, additional.

      23      And that would be very storm-dependent.

      24             SENATOR ZELDIN:  You discussed the 12 to

      25      24 hours after a storm hit.







                                                                   153
       1             And, you know, I have -- I've had a unique

       2      perspective with these storms in the last couple of

       3      years, in that, you field complaints from

       4      constituents who just want to get their power back

       5      on, but then you're also coordinating, you know,

       6      with LIPA.

       7             And, you learn where the assets are at that

       8      particular time, and, you know, they might be

       9      driving from Alabama, or they might be working at a

      10      substation.

      11             And I mentioned substations because, you

      12      know, it is a -- the best source of getting the most

      13      amount of people up in the quickest amount of time

      14      is to get some of these flood substations going

      15      again.

      16             And I get it.

      17             One of the problems with that is -- and

      18      it's -- and I'm -- you need to do that, and you need

      19      to do that right away, because you need to get as

      20      many people up running right away.

      21             The only problem with that to keep in mind,

      22      and wanting additional assets, is because people

      23      on the street aren't seeing trucks.  And you have

      24      to explain to all of them that -- you know, that

      25      they are working.







                                                                   154
       1             And the -- you know, the perception is, it is

       2      reality.

       3             And I think that, moving forward, while it's

       4      very important to have all of the resources you need

       5      to be getting the substations up and running, you

       6      have to have additional assets on top of that.

       7      You need trucks moving around, because when you

       8      wait, you know, two or three days before people

       9      start seeing trucks in their neighborhood, they

      10      think you're ignoring them, and then they get really

      11      pissed off.

      12             And, then, just one other small point is:

      13             The -- LIPA chose to give assets to the

      14      towns, and let the towns give discretion as to

      15      where in the town those assets should go.

      16             It causes problems for us on Long Island

      17      where we have so many villages.  And some of our

      18      villages may not, you know, have the best

      19      relationship with the town.

      20             I mean, they, essentially, petitioned to

      21      break away from the town.

      22             So, you just have to keep that in mind, and

      23      making sure that, if for whatever reason that that

      24      is continued, that you're also considering the fact

      25      that it may not be going to hardest-hit area.







                                                                   155
       1             I represent the village of Mastic Beach, for

       2      example, hit very hard during "Sandy," and they were

       3      lobbying the Town of Brookhaven to get them assets,

       4      and they shouldn't have to, to the extent that they

       5      were.

       6             And I think that, you know, that could -- you

       7      could help that part of the process.

       8             And then, communication, is just -- it's so

       9      important.

      10             Customer service:  At the end of the day,

      11      once you work at all of the economics, as far as

      12      whatever model we go to, I think that the real

      13      success -- I mean, when I say "working out the

      14      economics," rate -- the rates being held, but,

      15      customer service and response time, people feel --

      16      people have felt like calling LIPA is a waste of

      17      their time, where they're getting someone on the

      18      other end of phone who's saying, "We don't know."

      19             And, that's -- they're calling you up --

      20      they're calling LIPA up -- they were calling LIPA

      21      up, helpless.  They haven't seen -- you know,

      22      they're, five, six days without power.

      23             The last thing they want to be told is,

      24      "We don't know."

      25             So, I think that if we can get better at that







                                                                   156
       1      too, that can almost -- almost guarantee success.

       2             So if you work out the economics, and you

       3      had good customer service, we're in great shape.

       4             DAVID DALY:  Yeah, and as I said, the very

       5      first step in effective storm response is

       6      understanding the damage so that you can provide an

       7      accurate restoration time; number one.

       8             And then, number two, the process I described

       9      where, municipality and village, town, by town, we

      10      provide, every morning, a three-day look ahead, that

      11      tells them what resources are going to be in their

      12      town that day, and what their numbers are gonna

      13      look like, coming down.

      14             We don't necessarily, under our process,

      15      allocate resources all over the place.  We do a

      16      prioritization.

      17             We obviously have hospitals.

      18             One of the things that we're very proud of

      19      is, during "Sandy," there was not one hospital that

      20      had to evacuate.  We had all the hospitals back.

      21             But, we operate under a hierarchy, to get

      22      everybody back in the fastest possible way.

      23             But the combination of giving accurate

      24      restoration, which is a function of damage

      25      assessment, and the function of that technology,







                                                                   157
       1      and, giving ongoing updates on a three-day

       2      look-ahead, that are accurate.

       3             Even if after three days, I'm only going

       4      from 14 to 12, to 8, the fact they can see the

       5      slope, and then maybe it's flat for a day, and then

       6      it -- but that information being accurate is a huge

       7      driver of customer-satisfaction improvement.

       8             And we will definitely be bringing that as

       9      well.

      10             NEAL LEWIS:  And, Senator I, would add that,

      11      as a trustee, I would think that there needs to be a

      12      real fresh look at this whole question of tree

      13      clearing from roads after a truly major storm.

      14             So I think that, when we're not talking about

      15      storms on the scale of "Superstorm Sandy," it's a

      16      different issue.

      17             But when it's on that scale, I absolutely

      18      agree with the villages and towns that complained

      19      about the fact that they need to get trees out of

      20      the road.  It's a hazard.

      21             You know, people need to be able to get down

      22      the road, all the emergency reasons, and whatnot,

      23      and they have a wire in the road, and they need a

      24      professional to be able to say, "That wire is dead

      25      and it's safe to move the tree."







                                                                   158
       1             We have to come up with a better way to

       2      handle that kind of situation.

       3             And, what Mr. Hervey [ph.] came up with

       4      after "Irene," and implemented in this storm, was an

       5      attempt.

       6             I feel we haven't had a real good evaluation

       7      of what was good and bad about that.

       8             It did seem to work a little bit better in

       9      some towns; but, obviously, clearly, did not work

      10      at all, really, as an improvement in other towns.

      11             And I believe that, as trustees, we have to

      12      raise an issue about:  Look, we can't allow trees

      13      sitting in roads just because there's a dead wire

      14      next to them, for days on end.

      15             That's not acceptable.

      16             And maybe you don't -- you clearly don't need

      17      a linesman, as a really highly trained person that

      18      can do the repair, to be able to come out and say,

      19      "That line is dead, so you can clear the road."

      20             So I think we need a better strategy for how

      21      to handle those; and, that, I believe, needs to be

      22      developed in communication with the towns.

      23             And that's why I'm suggesting the idea that

      24      there should actually be formal MOUs with the

      25      towns, with the villages, with the county, to really







                                                                   159
       1      work out, at:

       2             At this level of damage, this is the

       3      strategy;

       4             At this higher level of damage, this will be

       5      the strategy.

       6             And, I hope that we can build on, you know,

       7      the lessons learned from these last two storms

       8      and come up with a better answer, because I don't

       9      think it's satisfactory where we are right now, with

      10      the notion that trees lay in streets for several

      11      years because -- for several days, because there's

      12      a wire alongside of them or intertangled with them.

      13             SENATOR ZELDIN:  Well, I thank you both for

      14      being here.

      15             You just brought new -- I just had a

      16      flashback, when my wife was pregnant, and I was in

      17      Iraq, and she was making me read, "Know What To

      18      Expect When You're Expecting."

      19             And, it helped prepare me, I guess, to be a

      20      parent.

      21             But towns and villages need to also know what

      22      assets are available when the storms's about to

      23      hit, and they know who they need to call, and they

      24      don't need to be making deals a couple days later.

      25             So, thank you.







                                                                   160
       1             SENATOR MARCELLINO:  And, again, I thank you

       2      for testifying.

       3             But just a reminder, that a lot of the

       4      questions we're asking, a lot of the comments

       5      about communication, I remember, because we held a

       6      hearing after "Irene," and then the very same

       7      questions, and the same type of answers, Yes, we'll

       8      improve communication.  Yes, we'll have better

       9      response time. -- it didn't happen.

      10             I saw a T-intersect -- a top part of a pole

      11      dangling over a road, held by the wires, for three

      12      days.  And it was a major north-south intersection

      13      in the town of Oyster Bay.

      14             So, three days it was hanging.

      15             Can't do that.

      16             Took them 2 1/2 days to clear

      17      South Oyster Bay Road, which is another major

      18      north-south road in the town of Oyster Bay, with a

      19      tree lying right across the road, with cars having

      20      to go over the tree.

      21              I mean, there were tangled lines in there.

      22      Three days, they couldn't get clearance that the

      23      lines were dead.

      24             It caused the traffic over it to get

      25      north-south, people had to get to work and get out







                                                                   161
       1      of the community.

       2             So, clearly, there are serious problems with

       3      this.

       4             I don't know if privatization clears that

       5      up or not, or your ServCo clears that up, but it's

       6      the same kind of problem we had with "Irene."

       7             It doesn't seem we're learning.

       8             So, whatever goes on, we'd like to see a

       9      learning curve on your parts improved.

      10             You know what I'm saying?

      11             It's got to happen that way; otherwise, the

      12      consumers are going to turn on you <snaps fingers>

      13      like that.

      14             Again, I thank you for your testimony.  We

      15      appreciate it.

      16             SENATOR MARCELLINO:  Can we have the next

      17      group up, Shelly Sackstein and Cynthia Kouril.

      18             Our next speakers are:

      19             Shelly Sackstein, chairman and CEO of

      20      Action Long Island, Chairman of the Suffolk County

      21      LIPA Oversight Committee, and a former board of

      22      trustee member of LIPA;

      23             And, Ms. Cynthia Kouril, Esq., former

      24      counsel, Inspector General for New York City

      25      Department of Environmental Protection; former







                                                                   162
       1      special assistant, U.S. Attorney General,

       2      Southern District of New York.

       3             Ms. Kouril.

       4             Again, can we summarize as much as possible,

       5      as I see a very thick tome in front of you.

       6             CYNTHIA KOURIL, ESQ.:  Oh, no.  This is in

       7      case you had questions.

       8             I'm not going to read it all.

       9             SENATOR MARCELLINO:  I have questions, but

      10      you're scaring the heck out of me with the thickness

      11      size of that book.

      12                  [Laughter.]

      13             SENATOR MARCELLINO:  Go right ahead.

      14             SHELLY SACKSTEIN:  I began my career as

      15      capital construction council for the New York City

      16      Parks and Recreation, where I gained experience in

      17      government procurement and construction contracting.

      18             Thereafter, I was recruited to be counsel to

      19      the Inspector General for the New York City

      20      Department of Environmental Protection.

      21             Most people think DEP is the tree-hugger

      22      agency.

      23             It is not.

      24             DEP is a municipal utility.  It's actually

      25      two municipal utilities: the water department and







                                                                   163
       1      the sewer department.

       2             Utilities have special problems when dealing

       3      with contract partners, because those contractors

       4      believe they have a negotiation advantage because

       5      the utility fears an outage.

       6             Consequently, they're not as fearful as they

       7      should be of cancellation of their contracts.

       8             While at DEP IG, we made more than our fair

       9      share of administrative, civil, and criminal cases.

      10             The Attorney General of the United States

      11      issued a finding that I possessed unique expertise

      12      in public construction, public-benefit contracts,

      13      and procurement not found within the Department of

      14      Justice, and cross-designated me to be a Special

      15      Assistant United States Attorney in the

      16      Southern District of New York where our criminal

      17      cases would be prosecuted.

      18             When my DOJ commission expired, I was

      19      promoted to the position of examining attorney in

      20      the New York City Department of Investigations.

      21             In private practice, I advised contractors on

      22      how to comply with the terms of complicated

      23      multi-million dollar public-improvement contracts,

      24      and I also do independent private-sector Inspector

      25      General audits, investigations, and reviews.







                                                                   164
       1             Over the course of a more than 25-year

       2      career, I have immersed myself in the world of

       3      contract compliance, and the detection and

       4      prevention of waste, fraud, and abuse.

       5             It is this perspective, that, and living on a

       6      cul-de-sac that borders on nature preserve, and

       7      where the power seems to go out every time a

       8      butterfly flaps its wings, that informs and colors

       9      my view about LIPA and its future.

      10             Some things about the infrastructure:

      11             As Governor Cuomo said in his State of the

      12      State message, quote:

      13             "New York's grid is aging.  59 percent of the

      14      state's generating capacity and 84 percent of its

      15      transmission facilities were put into operation

      16      before 1980, and 40 percent of the state's

      17      transmission lines will require replacement within

      18      the next 30 years.  This need represents an

      19      opportunity to upgrade the transmission system to

      20      distributed smart-grid network."

      21             What is a "smart grid"?

      22             A "smart grid" is an electrical grid that

      23      uses information and communications technology to

      24      gather and act upon information, such as information

      25      about the behavior of the suppliers and consumers in







                                                                   165
       1      an automated fashion, to improve the efficiency;

       2      most importantly, the reliability, the economics,

       3      and the sustainability of the production and

       4      distribution of electricity.

       5             It can level peak demand by turning off power

       6      to non-essential devices, like washing machines,

       7      during -- and turning it back on when demand eases.

       8             A self-healing smart grid, if built with

       9      redundant overlap, can be analyzed to -- analogize,

      10      rather, to a traffic circle with several entrances.

      11      If one route is blocked or broken, electricity can

      12      still enter through the other routes.

      13             A smart-grid brownout can prevent the sort of

      14      demand cascade blowouts that you sometimes see

      15      during heatwaves.

      16             Importantly, there are federal matching funds

      17      that can mitigate almost half the cost of

      18      implementing smart-grid technology.

      19             Governor Cuomo also endorsed microgrid

      20      technology in his State of the State message.

      21             A "microgrid" is when you have small cluster

      22      of users around a small generation facility.

      23             Similar infrastructure demands are sometimes

      24      made on housing developments or large industrial

      25      facilities that are not capable of being serviced by







                                                                   166
       1      existing water-treatment plants.

       2             Sometimes, in order to secure a needed

       3      variance, the developer must agree to build a

       4      water-treatment plant to service new construction.

       5             You could make a similar requirement in

       6      microgrid electricity transmission, and that will

       7      become more and more doable as solar and wind

       8      generation become more efficient.

       9             Privatizing LIPA:

      10             The call to privatize LIPA without more

      11      detail makes absolutely no sense.

      12             LIPA was originally created as a mechanism to

      13      save a private company.

      14             Additionally, right now, most of the things

      15      that we are complaining about, with respect to the

      16      current system, are the effects of having a private

      17      company, National Grid, that is, essentially,

      18      running roughshod over LIPA, and not really subject

      19      to sufficient oversight from LIPA.

      20             In 1998, LIPA assumed ownership of the

      21      electric transmission and distribution systems that

      22      had previously been owned by privately held LILCO.

      23             This occurred because of the financial crisis

      24      in LILCO caused by LILCO not operating the Shoreham

      25      nuclear plant.







                                                                   167
       1             LIPA began its life $7 billion in debt, which

       2      was the cost of the assets plus assuming the debt

       3      from Shoreham.

       4             Simultaneously, KeySpan hired the former

       5      LILCO employees, and took over national gas

       6      operations from LILCO and Brooklyn Union Gas.

       7             LIPA entered into two major contracts with

       8      KeySpan:

       9             One, the power-supply agreement, which paid

      10      KeySpan, both, for the electricity it generated, and

      11      for keeping over investor-owned power plants so that

      12      LIPA can meet certain peak-capacity thresholds;

      13             And, two, the management-services agreement,

      14      under which KeySpan was to manage the former LILCO

      15      employees as they operated the system, including

      16      billing and customer relations.

      17             The power-supply agreement causes LIPA to pay

      18      rates at a cost-plus basis, and also to pay property

      19      taxes and other costs of operating these plants, to

      20      the benefit of the private investors.

      21             The whole idea behind LIPA, was for LIPA to

      22      be able to borrow money at a -- much more

      23      inexpensively because it could issue government

      24      bonds.

      25             The problems with LIPA are several:







                                                                   168
       1             One, the contracts currently in existence --

       2      not the new ServCo, but the existing contracts --

       3      are drawn in such a way as to give a subsidy to the

       4      investors in the generators, and do not provide

       5      enough detail in the performance standards for

       6      KeySpan;

       7             Two, LIPA began its life as a funding

       8      mechanism to raise debt, and not much thought was

       9      put into how LIPA would manage or oversee KeySpan;

      10             Three, LIPA became a patronage mill largely

      11      staffed with people with no experience running a

      12      utility, no experience with contract compliance, and

      13      no experience with forensic audit.

      14             In the early things -- in the early years,

      15      things drifted along by dint of routine.  The same

      16      individuals who had been LILCO employees reported to

      17      the same work locations and did the same work they

      18      had always done.

      19             Momentum and habit carried things for a few

      20      years.

      21             Also, the people administering the contract

      22      for KeySpan lived here on Long Island and were

      23      affected as anyone else by the performance

      24      standards.

      25             However, in 2007, KeySpan was acquired by







                                                                   169
       1      National Grid and, suddenly, the decisions were

       2      being made in London.

       3             The decline of tree trimming and tree

       4      maintenance was observed by me, anecdotally, almost

       5      at once.

       6             After "Hurricane Irene," LIPA hired

       7      Vantage Consulting to do a study of why things went

       8      so badly.

       9             Vantage -- the Vantage reports stated that

      10      one of the main reasons for the failure in

      11      communications and was not having accurate outage

      12      information was the faulty outage management system.

      13             And there was a lot of discussion about that

      14      in the previous panel, so I'm going to skip the rest

      15      of this.

      16             On January 7, 2013, "Bloomberg Business

      17      News" reported that LIPA's debt was still

      18      $7 billion, with assets of $4 billion.

      19             "Bloomberg" also reported that, quote:

      20             "In October 2011, strategic review of LIPA by

      21      the Brattle Group concluded that privatization may

      22      raise costs by 438 million a year because an

      23      investor-owned utility can't issue tax-exempt bonds.

      24      Cost of capital for the privatized utility would be

      25      10.73 percent compared to LIPA's current cost of







                                                                   170
       1      capital of about 5 percent, it concluded."

       2             The same Brattle Group report examined four

       3      possibilities:

       4             One, maintain the status quo;

       5             Two, privatize;

       6             Three, a full municipalization;

       7             And, three --

       8             SENATOR MARCELLINO:  Excuse me.

       9             Sir, would you mind?

      10             CYNTHIA KOURIL, ESQ.:  -- And, four --

      11             SENATOR MARCELLINO:  No.  Go back and sit

      12      down, please.

      13             CYNTHIA KOURIL, ESQ.:  -- competitive

      14      outsourcing, which it dubbed "ServCo."

      15             The status quo was rejected because, pretty

      16      much, everybody is miserable with the status quo.

      17             Privatization was also rejected as

      18      economically nonviable.

      19             Full municipalization was considered

      20      desirable, but Brattle determined that LIPA

      21      currently lacked the in-house expertise and

      22      experience to run the system directly.

      23             The ServCo model emerged as the default

      24      winner, because it would give LIPA the time to

      25      develop or hire in-house experience and expertise,







                                                                   171
       1      paving the way to a future successful transition to

       2      a full municipal utility.

       3             Why would you want to municipalize?

       4             According to the January 2013 issue of

       5      "Public Power Magazine," municipal power companies

       6      have consistently provided power at much lower rates

       7      than privately owned power companies since this

       8      magazine began keeping records in 1946.

       9             The LIPA Board of Trustees approved the

      10      ServCo model as an interim step towards

      11      municipalization, and I agree with that decision.

      12             PSE&G has won the bid, and that ServCo

      13      contract is out there, waiting to begin at the end

      14      of the year.

      15             Additionally, there's a second contract,

      16      which was discussed by the last panel.  It's a

      17      two-year transition contract.

      18             In order to privatize, you're, essentially,

      19      going to undo all the work that's been done for a

      20      year, and have to start a new two-year transition

      21      period in order to privatize.  It's going to result

      22      in chaos.

      23             Some recommendations:

      24             LIPA needs it's own IG.

      25             In my extended written remarks, which I have







                                                                   172
       1      also submitted for the record, I recount multiple

       2      examples of fraud, waste, and abuse personally

       3      observed by me.

       4             Testimony taken in the Nassau County

       5      Legislature after "Hurricane Irene" contains more

       6      examples.

       7             An audit conducted by the State Comptroller's

       8      Office after "Hurricane Earl" has even more

       9      astonishing examples and the dollar amounts are

      10      staggering.

      11             After Hurricane -- oh, I'm going to leave

      12      this out.

      13             I had a section in here about logging in the

      14      Welwyn Preserve.  It turned out those were not LIPA

      15      crews.

      16             In all these events, where are the civil

      17      litigations to recoup the money from the fraud,

      18      waste, and abuse?

      19             Where are the criminal cases to provide

      20      accountability and to deter future wrongdoing?

      21             Unless LIPA tasks and empowers an

      22      inspector general to preserves evidence and build

      23      those cases, you're not going to have them.

      24             An IG can also design procedures and

      25      strategies to deter waste, fraud, and abuse before







                                                                   173
       1      they occur.

       2             Second:  LIPA needs a compliance unit.  It

       3      actually needs two compliance units; one unit to do

       4      the day-to-day compliance work with the new PSE&G

       5      ServCo contract, and another devoted to storm outage

       6      and other emergency contracts.

       7             Obviously, these units will have to work

       8      collaboratively and symbiotically with the new IG.

       9             Most importantly, LIPA needs a CEO.

      10             This position has been vacant for years, and

      11      an interim, or acting, CEO does not have the clout

      12      needed to make real, change, or even to enforce an

      13      existing contract.

      14             The CEO position must be filled, and filled

      15      promptly.

      16             The new CEO must be a person who's committed

      17      to contract compliance, transparency, and

      18      accountability, and full communication with the

      19      rate-paying public in collaboration with local

      20      governments.

      21             He or she must have a vision for the

      22      modernization and hardening of the transmission and

      23      distribution system to meet that future.

      24             I have other and much more prosaic

      25      recommendations in my extended written remarks,







                                                                   174
       1      which I have omitted in the interest of time.

       2             SENATOR MARCELLINO:  Thank you.

       3             Mr. Sackstein.

       4             SHELLY SACKSTEIN:  Yes?

       5             SENATOR MARCELLINO:  You're on.

       6             SHELLY SACKSTEIN:  I want to thank you for

       7      holding these hearings, Senator, and I'm delighted

       8      to be here.

       9             I think we need to just focus our attention,

      10      as best we can, on the issue of the structure of

      11      LIPA.

      12             There are a lot of issues that we can look

      13      back at, in terms of the storms, storm hardening,

      14      but the structure of LIPA is the issue that's on the

      15      table at the present time, and I think that's where

      16      the focus needs to really stay.

      17             The folks from the Moreland Commission had

      18      come up with the recommendation of privatization for

      19      LIPA.

      20             I think that, earlier today, Ms. Calcaterra

      21      had made a comment about the $100 million worth of

      22      profits that would be going to a privatized

      23      organization, so that the $7 million that was going

      24      to be some sort of an upset fee would be minuscule

      25      in relation to the profits that would be realized.







                                                                   175
       1             We all understand what the value is of a

       2      structured municipal-type entity for LIPA.

       3             We've all learn the same things, like, no

       4      dividends; no taxes; lower-cost borrowing; a whole

       5      host of issues that are very, very important when it

       6      comes to running LIPA as a full municipal entity.

       7             But for the moment, it appears as though the

       8      only thing that we're looking at is LIPA under its

       9      current structure, which is only owning the

      10      T&D system.

      11             Now, the T&D system is, as Neal pointed out

      12      previously, in quoting Bob Catell, "gold-plated,"

      13      and probably the best in the state of New York, if

      14      not in the country.

      15             And we must not lose that T&D system, and we

      16      well could.

      17             So, a lot of money has gone into it.

      18             And now we're hearing that, under a

      19      privatized model, the possibility exists that there

      20      will be a sale of that.

      21             And I think what Mr. Quiniones said was,

      22      there would be no rate increase.

      23             But I think it's important to note that you

      24      can accomplish that objective, and they may well be

      25      looking at that, by reissuing bonds that could







                                                                   176
       1      encumber our children and grandchildren for the next

       2      40 years.

       3             So I don't think that that making a promise

       4      of keeping the rates lower, but saddling our kids

       5      for a long time, is necessarily the approach that

       6      I'd like to take.

       7             I'd like to think that we would -- could

       8      consider instead, a model that would include LIPA

       9      owning, not just the T&D system, which is a very

      10      valuable asset, and I'll come back to that later,

      11      but owning, also, the generating capacity that is

      12      currently in the hands of Grid, under a municipal

      13      entity, and the gas part of the system.

      14             We talk about bifurcating the system,

      15      creating a problem, which it may well.

      16             So I think we ought to look at taking under

      17      the umbrella of LIPA, in a municipal approach, the

      18      entire system.

      19             Now, certainly, LIPA can do that by getting

      20      into negotiations with Grid and acquiring it, but

      21      LIPA also enjoys the benefit, being a municipal

      22      entity, of having the condemnation powers of the

      23      State of New York, which they could exercise.

      24             Now, under those condemnation powers, the way

      25      Steve List [ph.] wrote the LIPA statute, LIPA can







                                                                   177
       1      enter into this condemnation procedure, and then it

       2      goes into the courts to determine the value.

       3             But if LIPA doesn't like the value that is

       4      determined by the court, LIPA can walk away from

       5      that finding, in terms of value.

       6             So I think what we need to look at is, not

       7      this current asset that's owned, which is the T&D

       8      system, this very valuable T&D system, but we need

       9      to look at taking over the entire system under a

      10      reconstituted management team at LIPA that can

      11      run as a company.

      12             Now, LIPA has, in my opinion, over the years,

      13      been a wasted asset, as far as the ratepayers of

      14      Long Island are concerned.

      15             It could have done things and run things a

      16      lot better, but, as you had pointed out, it never

      17      had a CEO.

      18             Now, I say it never had a CEO because, while

      19      I worked with Ritchie Kessler when I was a LIPA

      20      trustee, he was not a utility person.

      21             Kevin Law was not a utility person.

      22             The company has never been run as a company.

      23             It doesn't have to make a profit, but it does

      24      have to run more effectively.

      25             And the easiest way to bring it un -- in







                                                                   178
       1      under control, is to have it under one entity, LIPA;

       2      one system -- transmission, distribution, generating

       3      and gas and electric; all tied together under a

       4      municipal structure.

       5             That is the only structure that has never

       6      been tried on Long Island.

       7             We've tried privatization under LILCO, we've

       8      tried a ServCo-type model with LIPA, and we've never

       9      had a fully municipalized system.

      10             I believe that that would probably be a

      11      system that would work most effectively.

      12             Now, let's come back to the T&D system for a

      13      second.

      14             There have been some rumored, or at least

      15      things that you can see in the newspaper, that

      16      suggested the sale of the system could bring in

      17      $3 1/2 billion.

      18             $3 1/2 billion is probably less than the

      19      ratepayers have already invested in the system.

      20             But let's not lose sight of something,

      21      because everybody is starting to talk about a

      22      smart grid.

      23             Let's not lose sight of the potential revenue

      24      stream that may be coming from that T&D system later

      25      down the road when they start to transmit data







                                                                   179
       1      through that system.

       2             A revenue stream that hasn't even been

       3      considered at this point because the technology is

       4      just emerging.

       5             Why should we give up a system that we

       6      invested, that the ratepayers now own, and give up a

       7      future revenue stream, just try to bail out

       8      something at this particular point in time, into a

       9      model that we've tried previously, which is

      10      privatization?

      11             So I'd like to think that we can broaden our

      12      scope, increase the horizon.  It's a much bigger

      13      lift, but it's the one model that has never been

      14      tried; and it's a fully municipalized system here on

      15      Long Island.

      16             So I think that's something to consider.

      17             And, frankly, I pay for that system.

      18             You pay for that system.

      19             Everybody on Long Island pays for that

      20      system.

      21             Why shouldn't I own what I'm paying for?

      22             And perhaps, under that structure, we could

      23      no longer have a system that creates an environment,

      24      where the folks who are working there, the 1049, and

      25      all the other folks, are pawns in a process, that







                                                                   180
       1      not -- it's got to end.

       2             We own it, we keep it.

       3             Now, you talk to -- we heard things about

       4      repowering just as well.

       5             If LIPA owned that system, the entire system,

       6      not just the T&D, but the transmission and

       7      distribution, the generating, and the gas system,

       8      under a repowering scenario that we can envision, we

       9      could repower those power plants.

      10             Those power plants would be owned by the

      11      ratepayers who are paying for them.

      12             Those power plants could be leased out under

      13      a bid process to independent power producers, who

      14      could come in there then, to try and bid.  And the

      15      lowest bidder would get those power plants under a

      16      lease, that would be property owned by LIPA.

      17             We finally have, for the first time on

      18      Long Island, competition, not privatization.

      19             So there are lot of different directions that

      20      we need to look at, but the focus has got to be on

      21      structure.

      22             And the old structures didn't work.

      23             The only structure that hasn't been tried is

      24      a fully municipalized structure.

      25             I'd like to also think that maybe, Lazard,







                                                                   181
       1      that is doing this study to determine whether or not

       2      we should privatize, should be excluded from any

       3      potential financing opportunities that would -- that

       4      might emerge from their recommendations.

       5             I think that would, perhaps, be a very

       6      important consideration.

       7             So, a unified structure, competition through

       8      ownership by the ratepayers.

       9             We, probably --

      10             And I say this a great deal of respect for

      11      the folks with PSE&G.

      12             -- wouldn't need someone to come in from

      13      New Jersey to manage our system, or somebody from

      14      California to come in and manage our system.

      15             We need to put people in place at LIPA in a

      16      management structure that can run that system.

      17             That's never happened [unintelligible].

      18             I think we need to look at it from that

      19      perspective.

      20             Look, I could give you 20 pages of testimony,

      21      but I'm only going to give you 25 years of

      22      experience, having worked on this issue, and paying

      23      for it, as we all are, very dearly.

      24             And it shouldn't be that way.

      25             I'm going to read something to you that I







                                                                   182
       1      think is very interesting, because it also speaks to

       2      the issue of privatization.

       3             It will take just a minute, because we all

       4      want to get back and finish the rest of our days.

       5             "The emergency restoration manuals were

       6      fraught with inconsistencies and inaccurate

       7      information.

       8             "Emergency restoration manuals failed to

       9      adequately address the special needs of segments of

      10      Suffolk County's population and neighborhoods.

      11             "Plan testing is deficient, and the only

      12      thing that -- that was only an in-house exercise.

      13      It totally failed to provide area-specific

      14      information to the public and the media and

      15      government at entities."

      16             Then it says:

      17             "LILCO must do a much better job of

      18      communicating with its customers."

      19             And on the cover it says:

      20             "The Report of the Suffolk County Commission

      21      established, per legislative resolution" da da da,

      22      "to study Long Island Lighting Company's response to

      23      'Hurricane Gloria.'"

      24             So how much have we learned?

      25             Now here's a real concern, because here we







                                                                   183
       1      talk about what currently exists today.

       2             And I'm looking now at a

       3      current --"current" -- restoration manual.

       4             "The procedure specifies the means by which

       5      notifications are to be made to LIPA and KeySpan

       6      personnel who staff the restoration information

       7      center."

       8             "KeySpan personnel."  Current manual.

       9             Who's reading the current manual?

      10             And, last, but not least, it says, that:

      11             "If a staging area is needed for off-island

      12      crews" --

      13             Okay?

      14             -- "for off-island crews, the Roslyn

      15      substation should be utilized, and you should call

      16      the following telephone number."

      17             This is from the current restoration manual.

      18             And it says, "Call XXX-XXXX."

      19                  [Laughter.]

      20             SHELLY SACKSTEIN:  There's no number.

      21             So what I'm saying is, if this is what we're

      22      operating under today, if this is what we operated

      23      under before, what lessons have we learned, and who

      24      is reading the current restoration manual?

      25             Because Carl Marcellino said at our meeting







                                                                   184
       1      on January the 27th, "There will be another storm.

       2      It will come.  Mother Nature will repeat herself."

       3             Who's watching the store?

       4             The ratepayers care.

       5             And I think this is the first chance that the

       6      ratepayers have to win, because the ratepayers have

       7      lost over and over again.

       8             They talk about us being run over by the bus

       9      the first time, backed over by the bus the second

      10      time.

      11             And you know it; it was an illegal

      12      management-services agreement that got extended.

      13             And here we sit today with what actually

      14      Long Island had said was going to happen.  We bid

      15      the contract out, and it cost us less money, years

      16      later.

      17             And so I say to you:  Carl, this is not an

      18      easy one, but the structure has to change to a model

      19      that has never been tried on Long Island.

      20             And I would say that, "we," meaning, actual

      21      Long Island, have taken that public position to

      22      fully municipalize the system.

      23             We have met with the folks from the

      24      Long Island Progressive Coalition, and they agree

      25      with us.







                                                                   185
       1             We're pretty sure that the folks from the

       2      Sierra Club, who are part of our coalition, will

       3      come on board.

       4             I'd like to think that the folks from the

       5      AARP will join us just as well.

       6             And we are intending to hold informational

       7      meetings, with your help, on Long Island.  We'd like

       8      to cohost those meetings along with our Albany

       9      delegation.  And we'd like the public to come in,

      10      and let's start a process of informing them of what

      11      really went on all these years.

      12             What is LIPA?

      13             What did it do?

      14             What could it have done?

      15             And let's get them involved in the process,

      16      because Larry Schwartz should not have to come to

      17      Long Island to find out how we feel.

      18             We should be calling from Long Island to let

      19      the Governor know how we feel.

      20             Larry Schwartz and the Governor work for the

      21      people of Long Island.

      22             And I'm delighted that the Governor

      23      recognizes that there is a problem with the current

      24      structure.

      25             We don't necessarily agree with privatizing,







                                                                   186
       1      which is what I hear the Governor wanting to do, but

       2      he's only thinking in terms of the T&D system.

       3             Perhaps when he hears about the broader

       4      concept, he might look at it, and say:  You know,

       5      that might be something that I can buy into and

       6      support.

       7             And with the support of our delegation, and

       8      with the support of the residents and the ratepayers

       9      of Long Island, letting him know how we feel,

      10      perhaps we can get the Governor to come on board

      11      with us, and say:  That's the approach I want to

      12      take for the residents and the ratepayers of

      13      Long Island.

      14             It's time for the ratepayers of Long Island

      15      to win.

      16             And I thank you for taking the time.

      17             SENATOR MARCELLINO:  Shelly, this model that

      18      you're talking about, municipalization, bringing the

      19      entire structure, from the utilities, the plants,

      20      the gas generation, all the rest that, under one

      21      entity, LIPA, isn't free, even if you do the

      22      condemnation process.

      23             There is a value to these things that would

      24      be determined, either through some -- probably by

      25      the courts, because I would assume they would







                                                                   187
       1      resist.  I don't know that National Grid would want

       2      to sell it or give it away, so there would have to

       3      be some kind of an evaluation.

       4             How do we pay for that?

       5             SHELLY SACKSTEIN:  Well, you know, I agree

       6      with you, there's a cost, but at the same time,

       7      we're paying for it today.

       8             We're paying for those plants, we just don't

       9      own them.

      10             We're paying for those gas systems, we just

      11      don't own them.

      12             We've already paid for the T&D system, we do

      13      own it.

      14             SENATOR MARCELLINO:  We'd still continue to

      15      pay for the municipalization because they charge us

      16      for the use of the power, so we'd still be paying a

      17      bill.

      18             It wouldn't be free just because we owned it.

      19             SHELLY SACKSTEIN:  Correct.

      20             SENATOR MARCELLINO:  In addition to that,

      21      you'd have to pay the company; you'd have to pay

      22      Grid for its gas entities, you'd have to pay them

      23      for the power plants.

      24             You'd have to pay somebody.  These guys

      25      aren't going to give this stuff away.







                                                                   188
       1             How would we fund it?

       2             SHELLY SACKSTEIN:  Well, financing it, we

       3      know the answer to that question:  That goes on the

       4      backs of the ratepayers via bonds.

       5             But let's come back to the issue of, how do

       6      you determine --

       7             SENATOR MARCELLINO:  In addition to the

       8      Shoreham debt, which still has to be dealt with.

       9             SHELLY SACKSTEIN:  That's the first time we

      10      get run over by the bus.

      11             SENATOR MARCELLINO:  Yeah, but, that bus is

      12      still running.

      13             SHELLY SACKSTEIN:  It's still there.

      14             SENATOR MARCELLINO:  The wheels are still

      15      turning.

      16             SHELLY SACKSTEIN:  It's still there.

      17                  [Laughter.]

      18             SHELLY SACKSTEIN:  And the Governor is

      19      proposing to refinance that debt, because he's

      20      not -- nobody is going to walk away from it.  We

      21      can't go bankrupt.  It's there.

      22             And, again, we look at refinance; it will get

      23      stretched out over 40 years, and my children and my

      24      grandchildren are going to pay for it, and your

      25      family's going to pay for it.







                                                                   189
       1             But let's come back to the question of value,

       2      how much will we have to pay for those plants?

       3             When the original deal was struck, there was

       4      an option to purchase those plants built into the

       5      original agreement, but there was no dollar amount.

       6             At the time the price was put on the table,

       7      we walked away from it, meaning LIPA.

       8             I was no longer a LIPA trustee, because had I

       9      been, we would have gone through the condemnation

      10      20 years ago, because that's what we put on the

      11      table with Ritchie at the time.

      12             When the option was walked away from, they

      13      extended the option period, and, again, no price was

      14      agreed on.

      15             And we walked away from the option again.

      16             I have not had conversations with

      17      National Grid.  I would be delighted to, to find out

      18      how much they would want for it, but let the

      19      negotiations begin with the condemnation, and we'll

      20      figure out the rest.

      21             But let me ask you this, Senator:

      22             We would be delighted to try and determine

      23      what the costs would be.  Will somebody help us?

      24             Because, you see, I know what's happening

      25      here today.







                                                                   190
       1             This is a whole new kettle of fish that I've

       2      just laid out on the table.  And, please don't

       3      expect me to have all the answers, but I'd be

       4      delighted to go into them.

       5             And let's have NYPA go looking into it,

       6      because NYPA's only looking at that little kernel:

       7      the T&D system.

       8             Let them -- they're not even considering

       9      municipalization.

      10             And now let's talk about municipalization in

      11      the broadest of possible senses, because all of the

      12      benefits that enure to the people, that we've all

      13      learned to tick off one at a time, in terms of the

      14      benefits of a municipal entity, minus the

      15      $100 million that Ms. Calcaterra was talking about

      16      this morning, all of those benefits could extend,

      17      should extend, will extend, to an overall

      18      consolidated system under the umbrella of one

      19      central management not looking to make a profit.

      20             And I'd be delighted to find out what it

      21      would cost us.  And I'd ask them to do the same.

      22             SENATOR MARCELLINO:  It's a question pose to

      23      the both of us, to this Committee here, and -- and

      24      to the Moreland people, to let them consider that,

      25      because I don't think they have.







                                                                   191
       1             But, they seem to be pushing towards the

       2      privatization aspect of it.  That seems to be the

       3      Governor's recommendation.

       4             I don't know if it's hard-and-fast, but that

       5      seems to be his leaning.

       6             At the very least, he wants a change in the

       7      basic structure of LIPA, we all know that.

       8             SHELLY SACKSTEIN:  Correct.

       9             And, you know, I wouldn't agree necessarily

      10      that what he said was, hard-and-fast, and you said

      11      it also, on privatization.

      12             Rather, he reacted to that situation that

      13      took place on Long Island, and he basically said:  I

      14      got to change something.  The structure has to

      15      change.

      16             And for that, I would say:  Thank you,

      17      Governor, because we would have said that 20 years

      18      ago, the structure had to change.

      19             Now let's think of it in a broader sense,

      20      because all the benefits --

      21             SENATOR MARCELLINO:  Shelly, do you think

      22      under municipalization there would be a lowering of

      23      rates, or --

      24             SHELLY SACKSTEIN:  Lower the rates?

      25             SENATOR MARCELLINO:  Would they be lower, or







                                                                   192
       1      would they just be flatlined?

       2             SHELLY SACKSTEIN:  You know, it depends upon:

       3             How you structure the transaction;

       4             How far out you spread the deal;

       5             How inexpensively you can issue the bonds.

       6             I don't have an answer to that.

       7             But what I would say is, what I've heard LIPA

       8      say for -- even LILCO:  I want to decrease the

       9      increase in the increase.

      10             SENATOR MARCELLINO:  Yeah, I understand where

      11      you're going.

      12             But my concern --

      13             SHELLY SACKSTEIN:  It's bizarre.

      14             SENATOR MARCELLINO:  Yeah, it is bizarre, but

      15      my concern is, the whole thing is bizarre.

      16             But as I said, my concern is, that we have a

      17      level of bonds that have to be dealt with, the

      18      Shoreham debt.  That doesn't go away under any

      19      system.

      20             So we're dealing with that.

      21             Your end of it is going to be funded through

      22      bonds issued.  It's the only way it's going to

      23      happen.

      24             So, there would be another level of bonding

      25      brought into the play.







                                                                   193
       1             So now the ratepayers are going to be paying

       2      off two levels of bonding in the rates, in addition

       3      to the cost of power, in addition to the maintenance

       4      of the system and paying the utility workers.

       5             So, we seem to be building costs into the

       6      system, and I don't see the situation where we're

       7      lowering costs.

       8             If you disagree with me, jump in, either one.

       9             CYNTHIA KOURIL, ESQ.:  If I may, there were

      10      two comments that were made in the first panel that

      11      I thought were very telling.

      12             One was this notion that privatization was

      13      somehow going to bring these synergies from being

      14      able to ship things, you know, when you have two

      15      companies near each other.

      16             Well, if that were true, we would be seeing

      17      that already, since National Grid already exists

      18      nearby in Massachusetts.  If this synergy of

      19      shifting, buying telephone poles and cable in bulk,

      20      and shipping to the northeast in bulk, was going to

      21      happen, it would have happened already.

      22             So you're not going to see any additional

      23      cost savings from these phantom synergies.

      24             And the other thing I found very telling, was

      25      this notion that, if it's privatized, and the State







                                                                   194
       1      gets left holding the bag with the LIPA bonds, the

       2      notion -- because we keep conflating two different

       3      things: the bill that the customer gets versus the

       4      rates.

       5             And they make this promise, Oh, well, we'll

       6      freeze the rates for X amount of years.

       7             But the gentleman at the end in the first

       8      panel said something very telling:  You're going to

       9      put a surcharge on the bill.

      10             You can keep the rates the same, but your

      11      bill's gonna go through the roof because there's

      12      going to be surcharges to pay those orphan bonds.

      13             So, the cost to the customer is going to go

      14      up dramatically, and there's nothing in the

      15      privatization plan that's going to solve that.

      16             The other thing, and I alluded to this in the

      17      beginning of my remarks:

      18             The Moreland Commission's analysis was of the

      19      existing disaster; that is, the National Grid

      20      contract.

      21             And that contract has -- and I almost feel

      22      like the LIPA people have given up, because it's

      23      almost over.

      24             You know, they're limping to the finish line

      25      of that contract, and I think they've put their







                                                                   195
       1      hopes in the new contract that begins January 1st.

       2             If you only analyze the existing

       3      National Grid contract, of course you say, Oh, we

       4      can't do this anymore.  Public-private doesn't work

       5      because that contract is a disaster.

       6             And the renegotiation of that contract in

       7      2006, took a bad contract and made it a zillion

       8      times worse.

       9             And the settlement agreement in 2006 was a

      10      travesty.

      11             And the analysis of those documents, my eyes

      12      almost fell out of my head.

      13             So to say, Well, we don't want to continue

      14      the status quo, I don't think there's anybody,

      15      anywhere, that wants to continue the status quo,

      16      because the current situation with the National Grid

      17      contract is an abomination.

      18             The ServCo contract and, admittedly, the

      19      manuals aren't written yet, but there are -- at

      20      Exhibits 4 and 5, there are the outlines of what's

      21      going to go into those manuals.

      22             And if you look at the topics in those

      23      manuals, it looks like there is a possibility of

      24      writing good oversight and good contract compliance,

      25      and good waste, fraud, and abuse prevention into







                                                                   196
       1      those manuals.

       2             And those -- that's something that's

       3      happening now.

       4             Additionally, if you look at Exhibit --

       5      Appendix 8, which is the metrics by which PSE&G will

       6      be compensated, the gentleman from PSE&G is correct,

       7      the their incentives are better aligned with LIPA

       8      and ratepayers in this contract.

       9             There is some fairly complicated math hoops

      10      you have to jump through to figure out how the

      11      metrics work, but they're actually there, where

      12      they've never been there before.

      13             So if you wanted to do meaningful contract

      14      compliance, the tools are there in this new

      15      contract, where they were never there before.

      16             Before, there were just goals -- these are

      17      the things you have to do -- but no explanation of

      18      how you get there.

      19             Now there's very detailed explanations of,

      20      how we will determine whether or not you're getting

      21      there, and whether you're getting there by the right

      22      path.

      23             So if you had a meaningful contract oversight

      24      by LIPA, and people at LIPA who knew how to do

      25      contract oversight, you actually could force good







                                                                   197
       1      production out of this contract.

       2             SHELLY SACKSTEIN:  You know, the real dilemma

       3      also is, as you said before, the clock is ticking.

       4             "The clock is ticking."

       5             The storm -- the next storm will come.  A

       6      contract will expire, the contract will begin.  The

       7      computer system has to get put in.

       8             We have to make some decisions, and I'd like

       9      to think that we probably could be in a position to

      10      make those decisions based upon the studies that

      11      have been done year after year after year by

      12      experts.

      13             Now, taking nothing away from Moreland, but,

      14      that's not the same as the Brattle folks who got

      15      paid a lot of money, and put a lot of time in

      16      specific issue of structure.

      17             Not response to the storm, but structure.

      18             We really -- it's -- I don't want to be

      19      precipitous, but we have to move with all dispatch

      20      because time is of the essence.

      21             This needs moving on, and -- and we're

      22      caught.

      23             And, you know, once, again, the ratepayers

      24      are going to get stuck, and it's sad.

      25             I would start with you tomorrow, if you could







                                                                   198
       1      help us to put the resources in place, to start to

       2      look at this issue of full municipalization, and

       3      something that's in the best interests of the

       4      ratepayers.

       5             What does it cost?

       6             How long would it take?

       7             How do we do it?

       8             I don't know.

       9             But I know, but I know it's certainly worthy

      10      of exploration, because it's the only untested model

      11      that exists in the energy history, and would be

      12      writing the energy future of the island.

      13             And that's important.

      14             SENATOR MARCELLINO:  I hear you.

      15             CYNTHIA KOURIL, ESQ.:  To bolster what Shelly

      16      just said, it's not just Brattle Group.  It was FTI

      17      in 2005.  It was Navigant in 2010.

      18             It's not the opinion of one consultant.  This

      19      is -- and there were more in between those.

      20             This is consultant after consultant after

      21      consultant has rejected privatization.

      22             So, to suddenly bring this out as some sort

      23      of panacea, defies all logic.

      24             SENATOR MARCELLINO:  I hear you.

      25             Thank you for your testimony.







                                                                   199
       1             I do appreciate your time, do appreciate you

       2      coming.

       3             We will be in touch.

       4             CYNTHIA KOURIL, ESQ.:  Thank you.

       5             SHELLY SACKSTEIN:  Thank you.

       6             SENATOR MARCELLINO:  Thank you very much.

       7             Will the next panel come up, please:

       8      Donald Daley, Tom Rumsey, and Rick Gonzales.

       9             We're going to take a one-minute break.

      10             And I mean, one minute.

      11                  (Pause in the proceeding.)

      12                  (The hearing resumed, as follows:)

      13             SENATOR MARCELLINO:  Okay.  Can we call the

      14      meeting back to order, please.

      15             Everybody take their seats.

      16             Mr. Technical Man in the booth, are we okay?

      17             THE TECHNICIAN:  Yes.

      18             SENATOR MARCELLINO:  Thank you.

      19             Okay, we are back.

      20             Unfortunately, we are moving to the end, and

      21      I appreciate the fact that you guys have been very,

      22      very patient, and, we are interested in hearing,

      23      obviously, everything you have to say.

      24             I have to be at a meeting at four.

      25             We have two panels left to go.







                                                                   200
       1             Because, I'm sharing another committee that's

       2      meeting, and has to issue a report.

       3             So, if we could can proceed afoot, and if we

       4      could get through a summary of your positions, I

       5      would appreciate that.

       6             Our next testifiers are:

       7             Donald J. Daley, Jr., business manager of

       8      The International Brotherhood of Electrical Workers,

       9      Local 1049.

      10             These are the people who man the trucks and

      11      do the work during the worst of conditions;

      12             Tom Rumsey, vice president of external

      13      affairs, I'm assuming, Local 1099?  Same?

      14             TOM RUMSEY:  No.

      15             Actually, I'm with the New York ISO;

      16      Independent System Operator.

      17             SENATOR MARCELLINO:  Okay.

      18             DONALD J. DALEY, JR.:  We don't get dues from

      19      him.

      20             SENATOR MARCELLINO:  You don't get dues from

      21      him?

      22                  [Laughter.]

      23             SENATOR MARCELLINO:  You got to work on that.

      24             And, Rick Gonzales, chief operating officer

      25      of the New York Independent System Operator.







                                                                   201
       1             Okay?

       2             Gentlemen, who's going to be up?

       3             DONALD J. DALEY, JR.:  I'll start.

       4             Thank you, Senator.  I really appreciate you

       5      bringing this very critically important topic to

       6      light here.

       7             In addition, I hope I -- this is the first of

       8      many forums that speaks about this.

       9             Some of the decisions that are going to be

      10      made out of this are critically important and have

      11      great consequences.

      12             So, again, I thank you for that.

      13             As you said earlier, my name is Don Daley.

      14      I'm the business manager of Local 1049.  I represent

      15      2,600 utility workers that work for National Grid,

      16      as well as the contractors that work on the utility

      17      system in -- on Long Island.

      18             And I did submit a prepared oral statement.

      19      You have it.

      20             If you have any questions, I'd be glad to

      21      answer those.

      22             But in addition to that, I did supply you

      23      with some additional information that really just

      24      speaks to the same topics.  It just expands a little

      25      bit more on it.







                                                                   202
       1             Most of the conversation to date has been

       2      about what the future model is going to look like on

       3      Long Island.

       4             And we're discussing a private utility, a

       5      municipalized utility, and a public-private

       6      partnership.

       7             And you've heard the pros and cons of all.

       8             I'm sitting here, I don't have a position on

       9      which model, but I am saying that the conversation

      10      needs to go deeper than just what the model is.

      11             Currently, the ratepayers, both on gas and

      12      electric side, benefit from, both, synergy savings,

      13      and also the number of people who work on the

      14      utility during storms.

      15             All the people for National Grid are fully

      16      cross-trained to work during storms.  Okay?

      17             SENATOR MARCELLINO:  Now, what do you mean by

      18      "cross-trained?

      19             DONALD J. DALEY, JR.:  "Cross-trained"; our

      20      gas people will go out and do two-man restoration.

      21      They'll actually hang services.

      22             I'll go -- I think your question will be

      23      answered through this, if you can just hold one

      24      second?  Is that alright?

      25             SENATOR MARCELLINO:  Sure.  Be very quick.







                                                                   203
       1             DONALD J. DALEY, JR.:  But I also believe you

       2      need to start, and look at the history.

       3             And I gave you a chart.

       4             It was brought up earlier, 1985, it was

       5      5,900 utility employees at that time.

       6             In 1998, when the changes came about with a

       7      merge between Brooklyn Union and LILCO, there was

       8      approximately 4,600 workers.

       9             In 2006, when National Grid came aboard,

      10      there was 3,650 workers.

      11             Today, we have about 3,400 workers.  That's

      12      unionized and management employees.

      13             So, when we had a storm like "Gloria," there

      14      was 750,000 outages.  We had 5,900 people readily

      15      available and prepared and working on that storm

      16      before it actually hit.

      17             When "Sandy" hit, we had 3,400 workers

      18      working on that storm.

      19             The system on Long Island is much bigger.  It

      20      was 750,000 on the electric side.  It's now

      21      1.2 million.

      22             The gas system has grown as well.  There was

      23      250,000 gas customers back then.  There are 500,000

      24      now.

      25             So, we had 1 employee for every







                                                                   204
       1      170 gas/electric customers in 1985.

       2             Currently, we have 1 employee for 500 gas and

       3      electric employees [sic] right now.

       4             That needs to be looked at.

       5             And if we're looking at some of these models

       6      where there may be thought of saving money on labor,

       7      I can tell you right now, by these charts, the facts

       8      are here, there's no fat on the bone.

       9             You asked about:  What do they do?  What are

      10      they cross-trained to do?

      11             Okay?

      12             Our non-electrical storm workers work in

      13      two-man restoration.  They actually string wires.

      14      They're trained and qualified to string service

      15      wires.

      16             We also deliver material.  A lot of the

      17      material is delivered by non-electric people using

      18      National Grid equipment: National Grid forklifts,

      19      National Grid pickups, National Grid pole trailers.

      20             All this stuff will not be available in the

      21      next storm post 1/1/14 if we don't have one

      22      workforce where, at a minimum, an agreement to

      23      utilize those people, that have always been

      24      cross-trained and experienced to work storms,

      25      continue to do that 1/1/2'14.







                                                                   205
       1             In addition to that, we have foreign crew

       2      support.  We had almost 14,000 people come here from

       3      off-island.  Takes a lot of resources to make sure

       4      that they're -- they got the proper bedding, and all

       5      their other needs are met, their equipment, their

       6      kits, everything that they need.

       7             That's all done by non-electrical personnel

       8      today.

       9             Our call center:

      10             We heard a lot of issues surrounding

      11      communications.

      12             Typically, in our call center, we have

      13      175 call center representatives.

      14             During the storm, we had over 300, because we

      15      were able to utilize the National Grid gas and

      16      generation and shared employees to answer phones of

      17      emergency phone calls.

      18             Also, our fleet services worked on both gas

      19      and electric trucks.

      20             So, again, if we're talking about just

      21      carving out a number of employees, that's the first

      22      I heard today that it was 2,200.  That's the highest

      23      number that I've heard.

      24             All the numbers that I heard prior to today

      25      were, sixteen and seventeen hundred workers.







                                                                   206
       1             But if you take almost half that workforce

       2      out, they will not be available during storms.

       3             We have a survey of workers, all

       4      non-electrical workers: crew guides, physical

       5      assists.

       6             We actually load the poles from our gas side

       7      of the business, bring them and deliver them to

       8      where it's needed, dig the holes, are all done by

       9      our gas personnel.

      10             They will not be available during the next

      11      storm post 1/1/2014.

      12             Our facilities' people work on making sure

      13      that our low-lying areas are sandbagged.

      14             Stuff like that, all done by our generation

      15      folks.

      16             Again, not available in the next storm.

      17             Wire watching, traffic control; all these

      18      things people don't think about.

      19             When you think about a storm, you're thinking

      20      about hanging wire.

      21             A lot goes into it before you hang the wire.

      22             The reality is, we have 3,400 utility workers

      23      now that respond before the storm's here, right here

      24      on Long Island.

      25             If you carve out -- I heard 2,200.  If you







                                                                   207
       1      carve out 2,200, and that's the number, there's

       2      still 1,200 people that are cross-trained to work

       3      storms, that are experienced, and been doing it for

       4      many, many years.

       5             What's going to happen is, those people are

       6      going to be sitting home during the next storm.

       7             That makes absolutely no sense.

       8             I heard, Plan B is to get contractors.

       9             We're not putting a Lego set together.  We

      10      really need to know what we're doing out there.

      11             We have certain work practices, safety rules.

      12      You can't just do line work, and hire Joe Contractor

      13      who's never done it before, and have an experiment

      14      the next storm, while 1,200 trained people are going

      15      to be sitting home.

      16             There's a big problem with this.

      17             Whatever model you go to, if you don't have

      18      the full workforce that you have right now at least

      19      available during storms, that's a big problem here.

      20             We're not meeting the expectations now.

      21             If we take it and carve it in half, what are

      22      we going to look like then?

      23             We talked about, "Hurricane Earl," bringing

      24      in the 1,600 crews, off-island, sitting there.

      25             We saw "Newsday."







                                                                   208
       1             The front page of "Newsday," all the trucks

       2      sitting at the airport.  Not one outage,

       3      $30 million, because we relied on outside help to

       4      help us.

       5             Now we're going -- now the plan is, to take

       6      the inside workforce, cut it in half.

       7             You're going to be more reliant on outside

       8      crews.

       9             Not only that, it's not only the big storm

      10      that we deal with.  These 3,400 people deal with all

      11      those little storms, so you don't need to call

      12      anybody.

      13             Okay?

      14             So, going forward, half the workforce is a

      15      big deal.

      16             In addition to that, we have daily synergies

      17      because we're all one workforce.

      18             We have synergies in warehouse, our fleet

      19      services, facilities, clerical, meter reading,

      20      collections, call center, IT, billing, service

      21      connect and disconnect.

      22             Currently, the ratepayers on Long Island

      23      benefit from one man or woman coming to the house,

      24      when they want their service disconnected, to do

      25      both the gas and electric.







                                                                   209
       1             Now we're going to have two, with two

       2      appointments, to do that.

       3             Project management, legal, real estate,

       4      accounts payable, human resources, purchasing,

       5      claims, communications, public affairs, payroll,

       6      environmental services, security, training, health

       7      services.

       8             These are daily synergy savings that both our

       9      gas and electric ratepayers benefit from today, that

      10      we're going to lose if the workforce is broken in

      11      half.

      12             So I ask that you continue these hearings,

      13      and that we have some open dialogue, other forums,

      14      informational forums.

      15             Our ratepayers, your constituents, need to

      16      know how the change in the workforce is going to

      17      impact their rates, both on the gas and the electric

      18      side.

      19             SENATOR MARCELLINO:  Thank you.

      20             TOM RUMSEY:  Good afternoon,

      21      Chairman Marcellino.

      22             I'd like to start by thanking you for having

      23      the New York Independent System Operator here to

      24      testify.

      25             We did supply a more detailed written







                                                                   210
       1      testimony than I intend to go through today, and in

       2      that was a map that may be easier for you follow

       3      along when Rick gets on that map here in a few

       4      minutes.

       5             My name is Tom Rumsey.  I serve as the

       6      vice president of external affairs for the New York

       7      Independent System Operator, or, "NYISO."

       8             With me today is Rick Gonzales.  He is a

       9      senior vice president and chief operating officer

      10      for the NYISO.

      11             And his teams are responsible for operating

      12      the bulk electric system, New York's wholesale

      13      energy markets, as well as the short- and long-term

      14      planning for New York.

      15             I think it's important, there's a distinction

      16      between what we'll discuss today, in that, where we

      17      talk rates and energy prices, it's at the wholesale,

      18      not retail, which would be a shift from what we've

      19      heard earlier today, as well as the bulk system

      20      versus the distribution system.

      21             I'd like to start by providing a short

      22      overview of our organization, and how the

      23      Long Island Power Authority plays within that

      24      framework.

      25             I want to ask Rick to provide a high-level







                                                                   211
       1      overview of the current status of our electric grid,

       2      LIPA's unique position, and a quick discussion of

       3      the impacts of "Hurricane Sandy" on the Long --

       4      excuse me, on Long Island's bulk electric system.

       5             The NYISO is an independent and

       6      non-for-profit corporation that carries out three

       7      key functions for the state:

       8             Our primary mission is to reliably operate

       9      New York's bulk power system in accordance with all

      10      national, regional, and state reliability

      11      requirements.

      12             With the exception of the control center, the

      13      NYISO does not own any physical assets of the

      14      system;

      15             Additionally, we develop and administer

      16      New York's wholesale competitive market for

      17      electricity, to satisfy both actual and reserve

      18      electrical demand requirements.

      19             In conjunction with our stakeholders, we

      20      conduct extensive system-planning processes to

      21      determine the power demands of the future, and do so

      22      within a time frame that will allow market solutions

      23      to meet identified needs;

      24             Finally, we do participate as a technical

      25      non-voting member of the New York State Energy







                                                                   212
       1      Planning Board, and we've provided technical

       2      assistance to the Governor's Energy Highway Task

       3      Force.

       4             We operate under federal tariff agreements

       5      approved by the federal Energy Regulatory

       6      Commission, and are regulated by the New York State

       7      Public Service Commission.

       8             We conduct our grid operations and system

       9      planning functions in compliance with all national,

      10      regional, and state reliability standard

      11      organizations that oversee, and also audit, our

      12      processes.

      13             The NYISO is governed by an independent board

      14      of directors, and a committee structure comprised of

      15      representatives from every market sector,

      16      transmission and generation owners, other suppliers,

      17      end-use consumers, public power, and environmental

      18      parties.

      19             The Long Island Power Authority is among the

      20      market participants participating in our shared

      21      governance as part of the public power and

      22      environmental sector.

      23             LIPA is an owner of high-voltage power lines

      24      which are operated through coordination between our

      25      control center and LIPA's local control center on







                                                                   213
       1      Long Island.

       2             Although LIPA meets most of its power needs

       3      through contract agreements with power plants on

       4      Long Island, it also buys and sells a portion of its

       5      electrical needs through the NYISO's wholesale

       6      electricity markets.

       7             LIPA participates in the NYISO short- and

       8      long-term planning processes which determine the

       9      amount of generation capacity that must be located

      10      on island to reliably serve its forecasted peak

      11      demand plus required reserves.

      12             These processes also determine the future

      13      electric needs of the state, including Long Island,

      14      over a ten-year horizon.

      15             That's a very brief introduction of who we

      16      are, and how Long Island fits in, in respect to your

      17      time.

      18             I'd like to turn it over to Rick, and he can

      19      give you an equally high view of the grid, and how

      20      it works, and Long Island's position in that.

      21             Thank you.

      22             RICK GONZALEZ:  Thank you, Chairman.

      23                  [Visual presentation begins.]

      24             RICK GONZALEZ:  And today's first use of the

      25      prop here will -- should -- should help us.







                                                                   214
       1             The objective of my presentation is just to

       2      show how the Long Island Power Authority and the

       3      Long Island electrical needs are part of the larger

       4      state needs.

       5             And starting there, the geography of

       6      New York State complicates the operation of the

       7      grid.

       8             Obviously, Long Island is an island.

       9             Most of the demand of New York State, over

      10      50 percent is in the Long Island and New York City

      11      metropolitan areas, so, there's is a very high

      12      concentration of demand in those two areas.

      13             As far as resources, the supply resources,

      14      statewide, are very diverse.

      15             We have New York Power Authority's

      16      hydroelectric resources at Niagara Falls and on the

      17      St. Lawrence River, and their pump storage unit.

      18             There's coal-fired generation on Lake Erie

      19      and on Lake Ontario.

      20             And, there's a nuclear units complexes in the

      21      Rochester area, and an Oswego complex.

      22             Those resources are typically more efficient

      23      to operate than gas-fired generation or oil-fired

      24      generation such as on Long Island.

      25             There's also interconnections to the west of







                                                                   215
       1      New York.  That power is scheduled on, to move to

       2      New York if it's more economic, the provinces of

       3      Ontario, the provinces of Quebec.

       4             The larger interconnection to our south,

       5      what's commonly called the "Pennsylvania-New Jersey

       6      interconnection."

       7             And then to the east, we have the New England

       8      interconnection, although, their generation fleet is

       9      much like Long Island's or eastern New York's.

      10             What this all means, is that power flow is,

      11      typically, from the western part of our state, to

      12      the east; and from the north part of the state, to

      13      the south; and it all tries to meet the electrical

      14      needs of Long Island and New York City.

      15             There's been -- there's been, over the past

      16      20 or 30 years, historical bottlenecks to moving

      17      that economic power to the load centers.

      18             One is east of Utica.  More recently, one has

      19      developed south of Albany.

      20             But there's always been historical

      21      bottlenecks moving power into New York City, and on

      22      to Long Island.

      23             With respect to Long Island, there is

      24      seven interconnections to get to Long Island:

      25             Four are to the mainland New York system in







                                                                   216
       1      Queens and Westchester, two are to Connecticut, and

       2      one is to New Jersey.

       3             During "Hurricane Sandy," all the

       4      interconnections to the other states were lost, but

       5      reliability was maintained at the bulk power level

       6      through the main interconnections back to the

       7      New York -- back to Queens and Westchester.

       8             The point of these -- this discussion about

       9      the interconnections, is those historical

      10      bottlenecks have limited Long Island's access to the

      11      state's diverse resources.

      12             From a planning perspective, the State

      13      requires 17 percent installed reliability margin.

      14             That means we need to have 17 percent more

      15      resources than our forecast demand;

      16             And, both New York City and Long Island have

      17      locational requirements.

      18             New York City proper has an 86 percent

      19      locational requirement;

      20             But Long Island has an even higher one, at

      21      105 percent, which indicates the more restrictive

      22      transition limitations moving to Long Island.

      23             In our planning perspective, there is

      24      sufficient supply on Long Island, whether or not

      25      it's as economic as the other resources that are







                                                                   217
       1      throughout the state.

       2             So, there are no reliability issues that we

       3      see in the Long Island area.

       4             And, statewide, we don't have any resource

       5      supply issues until 2019.

       6             If there was a reliability issue, we would

       7      manage it through either the ISO's process, or LIPA

       8      would manage it directly and report that to us.

       9             And that concludes my prepared remarks.

      10             SENATOR MARCELLINO:  Thank you very much.

      11             If the State, as it looks to the future --

      12      [unintelligible] information, doing their thing, the

      13      Governor's made his -- his thoughts known, you've

      14      heard the testimony of the prior panels, what are

      15      the major issues that you think we should be looking

      16      at?

      17             TOM RUMSEY:  From our perspective, the energy

      18      industry is one that is a very long-cycle industry.

      19             And whether it's EPA restrictions or new

      20      regulations, or it's an energy highway, it's a very

      21      complex and interrelated system.

      22             The biggest concern I think that we would

      23      have, is that we need to make sure that there's

      24      enough time and thought put in, to understand all

      25      the potential, tertiary, secondary, effects, and







                                                                   218
       1      make sure that we plan through those.

       2             DONALD J. DALEY, JR.:  A big concern of ours

       3      is, as you saw from the charts, is the staffing

       4      levels.

       5             We've gone down, from 5,900 employees, to

       6      3,400 employees.  There's a big concern in regards

       7      to service, and providing -- well, the ability to

       8      get people back on during a storm.

       9             The working staff is a big problem.

      10             SENATOR MARCELLINO:  Have you guys had any

      11      conversations with PSE&G, as to staffing levels?

      12             DONALD J. DALEY, JR.:  Yes.

      13             Yes, I've had numerous conversations with

      14      PSE&G.  They're not to the point right now where we

      15      started identifying exactly the people that they

      16      feel they're going to need to run their T&D system.

      17             SENATOR MARCELLINO:  Do you think that

      18      "twenty-two, twenty-three hundred" number that they

      19      were talking about works?

      20             DONALD J. DALEY, JR.:  It's the highest

      21      number I've heard so far.

      22             May be twenty-three tomorrow.

      23             SENATOR MARCELLINO:  That's not quite what I

      24      asked.

      25             DONALD J. DALEY, JR.:  I believe that,







                                                                   219
       1      sufficiently, on the electric side of the business,

       2      yes.

       3             But, again, the ratepayers are not going to

       4      benefit from the synergies that they benefit from

       5      today.

       6             SENATOR MARCELLINO:  What if -- if LIPA's PSA

       7      contracts are not approved before the current ones

       8      expire, does NYISO feel they can coordinate

       9      enough -- get enough power to supply LIPA on the

      10      open market?

      11             RICK GONZALEZ:  There would have to be some

      12      form of PSA that would continue to supply the

      13      Long Island generation into the markets.

      14             There isn't enough transmission capability to

      15      support Long Island without local generations.

      16             So, that has to be a continued expectation.

      17             TOM RUMSEY:  I think the locational

      18      requirements need a little definition.

      19             That means, that you have 105 percent of

      20      their peak demand in generation and local resources

      21      available to serve their load, and that you don't

      22      rely up to that number on long lines of

      23      transmissions.

      24             So that local-generation requirement is

      25      105 percent in the New York area, in Long Island







                                                                   220
       1      itself.

       2             SENATOR MARCELLINO:  What are your thoughts

       3      on privatization?

       4             TOM RUMSEY:  I think it's a policy decision,

       5      and not really something that we view one way or the

       6      other.

       7             SENATOR MARCELLINO:  Wouldn't impact your

       8      ability to provide the power or serve it?

       9             TOM RUMSEY:  We have a number of structures

      10      in our market participants today, so, again, I don't

      11      think we view any specific direction as being an

      12      overly strong challenge or advantage.

      13             SENATOR MARCELLINO:  How would your members

      14      feel?

      15             DONALD J. DALEY, JR.:  Currently, under the

      16      existing model, they benefit from certain things

      17      they're not going to benefit in the private sector,

      18      many of the costs, the fixed costs.

      19             The variable cost is labor.

      20             And is always -- my concern is that, in

      21      privatization, there's going to be pressure to

      22      reduce labor costs.

      23             SENATOR MARCELLINO:  Do you think there would

      24      be more of reliance on outside crews?

      25             DONALD J. DALEY, JR.:  I would say at the







                                                                   221
       1      "2,200" number, during daily business, maybe not.

       2             SENATOR MARCELLINO:  What about when the

       3      storm hits?

       4             DONALD J. DALEY, JR.:  When a storm hits,

       5      we're down to 1,200.

       6             We starting 1,200 down, so...

       7             SENATOR MARCELLINO:  Okay, thank you.

       8             Appreciate your time, appreciate your

       9      testimony.

      10             Next panel, please.

      11             Charles Bell, program director for

      12      Consumer Union;

      13             Elizabeth Horan, a volunteer for AARP;

      14             And, Bill Ferris, the state legislative

      15      representative for AARP.

      16             ELIZABETH HORAN:  Good afternoon,

      17      Senator Marcellino.

      18             SENATOR MARCELLINO:  Good afternoon.

      19             ELIZABETH HORAN:  My name is Elizabeth Horan,

      20      and I'm an AARP member, and a lifetime resident of

      21      Long Island.

      22             I'm one of over 600,000 members in AARP.

      23             And with me today is, Bill Ferris,

      24      AARP-New York State legislative representative.

      25             And...







                                                                   222
       1             I've lived through many hurricanes, but last

       2      October, I saw "Superstorm Sandy" devastate and

       3      decimate much of Long Island, the Long Island I know

       4      and love.

       5             I live in Sound Beach on the north shore on

       6      Long Island, and my home was spared, but we were out

       7      of electricity for 12 days.

       8             Because the nor'easter quickly followed

       9      "Sandy," it got very cold very fast.

      10             I had to leave my home.

      11             When the temperatures reached the 50s, I knew

      12      it was time to go.  I returned every day or two to

      13      check the power status, as calls to LIPA got nothing

      14      but a phone message.

      15             As I said, I'm one of the lucky ones on

      16      Long Island, but I know so many people who lost so

      17      much.

      18             Many didn't get their power back for weeks.

      19             As a resident of Long Island, and a member of

      20      AARP, I would publicly like to thank you,

      21      Senator Marcellino, for holding this hearing, and

      22      for all your work and leadership to help the people

      23      on Long Island.

      24             It is my understanding that the Senate is

      25      trying to get the issue surrounding LIPA done right,







                                                                   223
       1      and in the best interests of the Long Island

       2      ratepayers.

       3             And I thank you for making that a priority.

       4             There is no question that LIPA must be

       5      reformed.

       6             AARP agrees with state leaders that LIPA's

       7      performance during "Superstorm Sandy," and its

       8      aftermath, was nothing short of disastrous.

       9             However, it is AARP's position that a change

      10      in ownership is not necessarily the only way to

      11      improve the service for LIPA customers.

      12             AARP has not yet taken a position for or

      13      against reprivatization of LIPA, because the

      14      association does not yet have all the facts

      15      regarding the impact on ratepayers' pocketbooks if a

      16      decision is made to reprivatize LIPA.

      17             However, AARP has a very simple view on this

      18      issue, which I support as an AARP member:

      19             How will privatization, at the end of the

      20      day, benefit the ratepayer, and how much will they

      21      pay on their future monthly energy bills?

      22             If privatizing LIPA is ultimately the road we

      23      take with no uncertainty, it should include a clear

      24      benefit to Long Island's ratepayers.

      25             It is my understanding from being briefed by







                                                                   224
       1      representatives from AARP, that published reports

       2      from rating organizations, like Fitch and Moody's,

       3      believe that privatization of LIPA could be

       4      expensive and may not result in ratepayer benefits.

       5             In addition, AARP has identified a report

       6      from 2010, that was prepared for LIPA by an

       7      organization called "Brattle Group," which found

       8      that privatizing would result in a rate increase,

       9      from 15 to 20 percent.

      10             As you know, Senator Marcellino, last thing

      11      Long Island needs is a double-digit rate increase,

      12      now, or in four years, when a proposed rate freeze

      13      would be lifted, a proposal I have read about in the

      14      news.

      15             AARP believes that we should be looking at

      16      other publicly owned utilities to see how the rates

      17      and storm performance of publicly owned and operated

      18      utilities, in fact, run their own operations compare

      19      with utilities that are investor-owned.

      20             AARP strongly believes that we need to keep

      21      examining the pros and cons of privatizing, as the

      22      Senate is doing here today, before any deal is

      23      struck on the future of LIPA.

      24             I would also like to touch on the need for an

      25      independent consumer advocate office in New York.







                                                                   225
       1             The State continues to grapple with the

       2      aftermath of "Superstorm Sandy," and we need for

       3      residential ratepayers to have representation.

       4             It is critical, as, potentially, hundreds of

       5      millions of dollars in rate hikes and accountability

       6      of utilities are being discussed.

       7             More than 40 states and the District of

       8      Columbia have independent State offices charged with

       9      the mission to represent residential utility-service

      10      customers in cases before state and federal utility

      11      regulatory commissions.

      12             In a recent "New York Times" article, the

      13      Governor's spokesman mentioned that they are

      14      thinking of an independent consumer advocate office

      15      for Long Island.

      16             AARP strongly believes that an independent

      17      utility consumer office should be created, not only

      18      for Long Island, but for all New Yorkers.

      19             Again, thank you for allowing me to speak

      20      today.

      21             We need to keep examining the pros and cons

      22      of privatization, as the Senate is doing here,

      23      before any deal is struck on the future of LIPA.

      24             Please make sure that the ratepayers get a

      25      fair deal in any plan that moves forward on







                                                                   226
       1      improving LIPA, and ensuring that all New York

       2      residents benefit from the establishment of an

       3      independent consumer advocate office.

       4             Thank you.

       5             SENATOR MARCELLINO:  Thank you.

       6             CHARLES BELL:  Hi, I'm Chuck Bell, programs

       7      director at Consumers Union, and we're the

       8      non-profit organization that publishes

       9      "Consumer Reports," based in Yonkers.

      10             I know it's been a long day, so I just want

      11      to say:

      12             We strongly agree with the points that have

      13      been made by AARP.

      14             In my written statements, we emphasize that

      15      we think consumer and ratepayer interests should be

      16      at the center of any decisions that are made about

      17      LIPA restructuring.

      18             And, we are particularly concerned about the

      19      possibility that restructuring could drive rates

      20      even higher, because of the higher costs of

      21      borrowing in the private markets, the need to pay

      22      return to investors, and the higher salaries for

      23      executives of these companies.

      24             We also feel that ratepayers are

      25      underrepresented in State policymaking.







                                                                   227
       1             If we were in any other state, we would

       2      probably have the state utility advocate here

       3      testifying about LIPA restructuring.

       4             New York has allocated less, on a per capita

       5      basis, to support our state utility advocate.

       6             So, for example, in New Jersey, much more,

       7      $7 million, is advocated; whereas, in New York, only

       8      about 2 million is advocated for those activities,

       9      even with all the issues that we have.

      10             I also emphasize the affordability concerns

      11      of Long Island ratepayers.

      12             You have an energy affordability gap of about

      13      $115 million there, which is what the amount that

      14      households are paying over the recommended 6 percent

      15      guideline for their income.

      16             They should not be paying more than 6 percent

      17      of monthly income for electricity.

      18             And that's truly a statewide problem that we

      19      have.

      20             And, so, we feel if we can increase the

      21      amount of resources devoted to utility advocacy,

      22      both, in the state at the state level, and by

      23      non-profit organizations, like the Public Utility

      24      Law Project, that that would be of great benefit to

      25      ratepayers.







                                                                   228
       1             At the state level, we had, at one point,

       2      over 30 people in the Consumer Protection Board

       3      developed -- devoted to utility-rate intervention,

       4      in the 1990s.

       5             And, today, we have maybe four or five people

       6      devoted to that function.

       7             So, we, as a non-profit, Consumer Groups see

       8      that as a huge loss.

       9             And, so, we hope that under whatever scenario

      10      is contemplated here, we can begin to rebalance the

      11      scales for consumers.

      12             And, we thank you for having this oversight

      13      hearing, because the issues you brought out today

      14      really need to be heard and discussed by the people

      15      of New York before any decisions are made in this

      16      matter.

      17             Thank you.

      18             SENATOR MARCELLINO:  Thank you.

      19             BILL FERRIS:  I just wanted to add one thing,

      20      from AARP's perspective.

      21             We're hearing more and more from our members

      22      on Long Island about the concerns of what they're

      23      seeing in the paper, what they're hearing about,

      24      what's going on with LIPA.

      25             And, we've heard already from them, that







                                                                   229
       1      they -- that paying their bill is a problem with

       2      many of our members.

       3             So, the issue of LIPA is becoming more and

       4      more front and center for them.

       5             And, you know, again, from AARP's

       6      perspective, we'd like to thank you for holding this

       7      hearing.

       8             It's very important to AARP, very important

       9      to our members on Long Island.

      10             So, thank you very much, Senator.

      11             SENATOR MARCELLINO:  Thank you.

      12             Do you folks have any thoughts about

      13      privatization?

      14             BILL FERRIS:  From AARP looking at

      15      privatization, we referenced in our testimony, in a

      16      report that we issued, that there -- and I think you

      17      heard it earlier today, there's been numerous

      18      reports, I believe, that LIPA actually contracted

      19      for, that there are concerns over privatization,

      20      especially on the aspect of the potential rate

      21      increase for the residential ratepayer.

      22             And that's what our concern is.

      23             We're very concerned about the increase in a

      24      monthly bill.

      25             As you know, many of our members are on a







                                                                   230
       1      fixed income, social security.  And, that increase,

       2      whether it's $2, $5, $10, it's an increase.  It's

       3      just part of an overall budget that many of our

       4      members, you know, moving forward, can't afford.

       5             So, we've looked at some of the studies, and

       6      we -- and I think you've mentioned it today, you

       7      know, the Senate's looking at those studies, the

       8      Brattle report, and other -- I think there was a

       9      study that came out today in "Newsday," referenced

      10      another study that raised concerns about

      11      privatization.

      12             So, we're looking at that.

      13             But, overall, we have not taken a position,

      14      but we do have a major concern, if the decision is

      15      to privatize LIPA, that there needs to be something

      16      done for the residential ratepayer, in that process.

      17             SENATOR MARCELLINO:  Okay.  Thank you very

      18      much.

      19             Appreciate you coming, appreciate your time.

      20             Thank you.

      21             BILL FERRIS:  Thank you.

      22             SENATOR MARCELLINO:  That concludes the

      23      hearing.

      24             We will refer it back.  We're going to read

      25      the notes.







                                                                   231
       1             If you want to look at this thing, as I said

       2      earlier in the meeting, a video of this entire

       3      hearing process, if you -- I suggest, later at

       4      night, after dinner, you can look at this, and

       5      you'll sleep well.

       6                  [Laughter.]

       7             SENATOR MARCELLINO:  The idea -- it's

       8      available on the website: the Senate website,

       9      Committee's website.

      10             And I thank you for attending.

      11             I thank the -- my -- the camera crew that's

      12      videotaping this whole thing; and, my staff,

      13      Debbie Peck Kelleher and Rob Parker, for putting

      14      this whole hearing together.

      15             Meeting's adjourned.

      16             Thank you.

      17                  [Applause.]

      18

      19

      20

      21

      22

      23

      24

      25







                                                                   232
       1                  (Whereupon, at approximately 3:14 p.m.,

       2        the public hearing held before the New York State

       3        Senate Standing Committee on Investigations and

       4        Government Operations and the Senate Standing

       5        Committee on Corporations, Authorities, and

       6        Commissions, concluded, and adjourned.)

       7

       8                             ---oOo---

       9

      10

      11

      12

      13

      14

      15

      16

      17

      18

      19

      20

      21

      22

      23

      24

      25