Summary

Provides that, prior to granting a certificate for the construction of an electric transmission line facility, the public service commission must find that the facility conforms to the most recent state energy plan and consider whether approval of the facility would cause adverse impacts on the state's environmental quality due to electric generation.

do you support this bill?

Bill Details

See Assembly Version of this Bill:
A1244
Versions:
S699
Legislative Cycle:
2013-2014
Current Committee:
Senate Energy And Telecommunications
Law Section:
Public Service Law
Laws Affected:
Amd ยง126, Pub Serv L
Versions Introduced in 2011-2012 Legislative Cycle:
S5626, A7399

Sponsor Memo

BILL NUMBER:S699

TITLE OF BILL:
An act
to amend the public service law, in relation to approval of electric
transmission line facilities

PURPOSE:
The purpose of this bill is to require the Public Service
Commission (PSC), to consult the most recent State Energy Plan (SEP)
before issuing a certificate of environmental compatibility and
public need ("certificate") for an electric transmission line.

SUMMARY OF PROVISIONS:
This bill amends paragraph (d) of subsection
(1) of section 126 of the public service law.

JUSTIFICATION:
This bill requires that in an Article VII proceeding on
an electric transmission line, the PSC must determine whether or not
the proposed facility, if built, would correspond with the most
recent energy plan, while considering the prospect of additional
environmental impacts that may be caused by increased electrical
generation as a result of such facility was improved. The legislation
is intended to prevent the approval of projects which may directly
result in increased electrical generation produced from dirty
sources, including coal that would impact the state's environment.

In September 2010, the PSC granted a certificate for the construction
of the Hudson Transmission Project. The eight-mile underground
transmission cable is intended to connect the New York Power
Authority's (NYPA) governmental customers to the PJM Interconnection,
the 13-state wholesale electrical market that serves, New Jersey,
Pennsylvania, Delaware and the District of Columbia. The PSC approved
the certificate despite testimony from various participants who
argued that the facility was unnecessary due to existing electrical
capacity in the New York Independent System Operator (NYISO)
wholesale electrical market. Additionally, the New York State
Department of Environmental Conservation (DEC) testified that HTP
would result in additional coal-fired in PJM.
Nearly half of PJM is produced in from coal fire generator, many of
which are located in Pennsylvania, a state upwind of New York. The
DEC testified that only 13 percent of NYISO power was generated from
coal.

The 2009 State Energy Plan included energy and transportation
strategies that would reduce emissions of greenhouse gases, including
the need to increase the amount energy produced by cleaner burning
and renewable resources. The PSC's decision regarding HTP appears to
be contradict policies enumerated in the Energy Plan.

LEGISLATIVE HISTORY:
2011-12: S.5626/A.7399 - Passed the Assembly - Held in Energy
and Telecomm

FISCAL IMPLICATIONS:


To be determined.

EFFECTIVE DATE:
This act shall take effect immediately.

view bill text
                    S T A T E   O F   N E W   Y O R K
________________________________________________________________________

                                   699

                       2013-2014 Regular Sessions

                            I N  S E N A T E

                               (PREFILED)

                             January 9, 2013
                               ___________

Introduced  by  Sen.  PARKER -- read twice and ordered printed, and when
  printed to be committed to the Committee on  Energy  and  Telecommuni-
  cations

AN ACT to amend the public service law, in relation to approval of elec-
  tric transmission line facilities

  THE  PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:

  Section 1. Paragraph (d) of subdivision 1 of section 126 of the public
service law, as added by chapter 272 of the laws of 1970, is amended  to
read as follows:
  (d)  in  the  case of an electric transmission line, (1) what part, if
any, of the line shall be located underground; (2)  that  such  facility
conforms  to [a long-range plan for expansion of the electric power grid
of the electric systems serving this state  and  interconnected  utility
systems,  which  will serve the interests of electric system economy and
reliability] THE MOST RECENT STATE ENERGY PLAN AS  ESTABLISHED  PURSUANT
TO  ARTICLE  SIX  OF THE ENERGY   LAW, WITH CONSIDERATION OF WHETHER THE
APPROVAL OF SUCH FACILITY WOULD CAUSE ADVERSE  IMPACTS  ON  THE  STATE'S
ENVIRONMENTAL  QUALITY  DUE  TO  AN INCREASE IN IN-STATE OR OUT-OF-STATE
ELECTRIC GENERATION;
  S 2. This act shall take effect immediately.




 EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
                      [ ] is old law to be omitted.
                                                           LBD02772-01-3

Comments

Open Legislation comments facilitate discussion of New York State legislation. All comments are subject to moderation. Comments deemed off-topic, commercial, campaign-related, self-promotional; or that contain profanity or hate speech; or that link to sites outside of the nysenate.gov domain are not permitted, and will not be published. Comment moderation is generally performed Monday through Friday.

By contributing or voting you agree to the Terms of Participation and verify you are over 13.