S T A T E O F N E W Y O R K
________________________________________________________________________
409
2009-2010 Regular Sessions
I N A S S E M B L Y
(PREFILED)
January 7, 2009
___________
Introduced by M. of A. KAVANAGH -- read once and referred to the Commit-
tee on Energy
AN ACT to amend the public service law, in relation to net energy meter-
ing
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. The public service law is amended by adding two new
sections 66-m and 66-n to read as follows:
S 66-M. NET ENERGY METERING FOR SOLAR, FUEL CELL, OR FARM WASTE ELEC-
TRIC GENERATING SYSTEMS. 1. DEFINITIONS. AS USED IN THIS SECTION, THE
FOLLOWING TERMS SHALL HAVE THE FOLLOWING MEANINGS:
(A) "CUSTOMER-GENERATOR" MEANS: (I) A CUSTOMER OF AN ELECTRIC CORPO-
RATION, WHO OWNS OR OPERATES SOLAR ELECTRIC GENERATING EQUIPMENT LOCATED
AND USED AT THE SAME SITE WHERE THE EQUIPMENT IS LOCATED; (II) A CUSTOM-
ER OF AN ELECTRIC CORPORATION, WHO OWNS OR OPERATES FARM WASTE ELECTRIC
GENERATING EQUIPMENT LOCATED AND USED AT HIS OR HER "FARM OPERATION," AS
SUCH TERM IS DEFINED IN SUBDIVISION ELEVEN OF SECTION THREE HUNDRED ONE
OF THE AGRICULTURE AND MARKETS LAW; AND (III) A CUSTOMER OF AN ELECTRIC
CORPORATION, WHO OWNS OR OPERATES FUEL CELL ELECTRIC GENERATING EQUIP-
MENT LOCATED AND USED AT THE SAME SITE WHERE THE EQUIPMENT IS LOCATED.
(B) "NET ENERGY METER" MEANS A NON-DEMAND, NON-TIME DIFFERENTIATED
METER THAT MEASURES THE REVERSE FLOW OF ELECTRICITY TO REGISTER THE
DIFFERENCE BETWEEN THE ELECTRICITY SUPPLIED BY AN ELECTRIC CORPORATION
TO THE CUSTOMER-GENERATOR AND THE ELECTRICITY PROVIDED TO THE CORPO-
RATION BY THAT CUSTOMER-GENERATOR.
(C) "NET ENERGY METERING" MEANS THE USE OF A NET ENERGY METER TO MEAS-
URE, DURING THE BILLING PERIOD APPLICABLE TO A CUSTOMER-GENERATOR, THE
NET AMOUNT OF ELECTRICITY SUPPLIED BY AN ELECTRIC CORPORATION AND
PROVIDED TO THE CORPORATION BY A CUSTOMER-GENERATOR.
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD01778-01-9
A. 409 2
(D) "SOLAR ELECTRIC GENERATING EQUIPMENT" MEANS A PHOTOVOLTAIC SYSTEM
THAT IS MANUFACTURED, INSTALLED, AND OPERATED IN ACCORDANCE WITH APPLI-
CABLE GOVERNMENT AND INDUSTRY STANDARDS, THAT IS CONNECTED TO THE ELEC-
TRIC SYSTEM AND OPERATED IN CONJUNCTION WITH AN ELECTRIC CORPORATION'S
TRANSMISSION AND DISTRIBUTION FACILITIES, AND THAT IS OPERATED IN
COMPLIANCE WITH ANY STANDARDS AND REQUIREMENTS ESTABLISHED UNDER THIS
SECTION.
(E) "FARM WASTE ELECTRIC GENERATING EQUIPMENT" MEANS EQUIPMENT THAT
GENERATES ELECTRIC ENERGY FROM BIOGAS PRODUCED BY THE ANAEROBIC
DIGESTION OF AGRICULTURAL WASTE, SUCH AS LIVESTOCK MANURE, FARMING
WASTES AND FOOD PROCESSING WASTES, THAT IS:
(I) MANUFACTURED, INSTALLED, AND OPERATED IN ACCORDANCE WITH APPLICA-
BLE GOVERNMENT AND INDUSTRY STANDARDS;
(II) CONNECTED TO THE ELECTRIC SYSTEM AND OPERATED IN CONJUNCTION WITH
AN ELECTRIC CORPORATION'S TRANSMISSION AND DISTRIBUTION FACILITIES;
(III) OPERATED IN COMPLIANCE WITH ANY STANDARDS AND REQUIREMENTS
ESTABLISHED UNDER THIS SECTION;
(IV) FUELED AT A MINIMUM OF NINETY PERCENT ON AN ANNUAL BASIS BY
BIOGAS PRODUCED FROM THE ANAEROBIC DIGESTION OF AGRICULTURAL WASTE SUCH
AS LIVESTOCK MANURE MATERIALS, CROP RESIDUES, AND FOOD PROCESSING WASTE;
AND
(V) FUELED BY BIOGAS GENERATED BY ANAEROBIC DIGESTION WITH AT LEAST
SEVENTY-FIVE PERCENT BY WEIGHT OF ITS FEEDSTOCK BEING LIVESTOCK MANURE
MATERIALS ON AN ANNUAL BASIS.
(F) "FUEL CELL ELECTRIC GENERATING EQUIPMENT" MEANS A SOLID OXIDE
(SOFC), MOLTEN CARBONATE (MCFC), PROTON EXCHANGE MEMBRANE (PEM), OR
PHOSPHORIC ACID (PAFC) FUEL CELL THAT IS MANUFACTURED, INSTALLED AND
OPERATED IN ACCORDANCE WITH APPLICABLE GOVERNMENT AND INDUSTRY STAND-
ARDS, THAT IS CONNECTED TO THE ELECTRIC SYSTEM AND OPERATED IN PARALLEL
WITH AN ELECTRIC CORPORATION'S TRANSMISSION AND DISTRIBUTION FACILITIES,
AND THAT IS OPERATED IN COMPLIANCE WITH ANY STANDARDS AND REQUIREMENTS
ESTABLISHED UNDER THIS SECTION.
2. INTERCONNECTION AND NET ENERGY METERING. AN ELECTRIC CORPORATION
SHALL PROVIDE FOR THE INTERCONNECTION OF SOLAR, FUEL CELL AND FARM WASTE
ELECTRIC GENERATING EQUIPMENT OWNED OR OPERATED BY A CUSTOMER-GENERATOR,
PROVIDED THAT FOR NET ENERGY METERING THE CUSTOMER-GENERATOR ENTERS INTO
A NET ENERGY METERING CONTRACT WITH THE CORPORATION OR COMPLIES WITH THE
CORPORATION'S NET ENERGY METERING SCHEDULE AND COMPLIES WITH STANDARDS
AND REQUIREMENTS ESTABLISHED UNDER THIS SECTION.
3. CONDITIONS OF SERVICE. (A) ON OR BEFORE THREE MONTHS AFTER THE
EFFECTIVE DATE OF THIS SECTION, EACH ELECTRIC CORPORATION SHALL DEVELOP
A MODEL CONTRACT AND FILE A SCHEDULE THAT ESTABLISHES CONSISTENT AND
REASONABLE RATES, TERMS AND CONDITIONS FOR NET ENERGY METERING TO
CUSTOMER-GENERATORS, ACCORDING TO THE REQUIREMENTS OF THIS SECTION. THE
COMMISSION SHALL RENDER A DECISION WITHIN THREE MONTHS FROM THE DATE ON
WHICH THE SCHEDULE IS FILED. EACH ELECTRIC CORPORATION SHALL MAKE SUCH
CONTRACT AND SCHEDULE AVAILABLE TO CUSTOMER-GENERATORS ON A FIRST COME,
FIRST SERVED BASIS, UNTIL THE TOTAL RATED GENERATING CAPACITY FOR SOLAR,
FUEL CELL, AND FARM WASTE ELECTRIC GENERATING EQUIPMENT OWNED OR OPER-
ATED BY CUSTOMER-GENERATORS IN THE CORPORATION'S SERVICE AREA IS EQUIV-
ALENT TO ONE PERCENT OF THE CORPORATION'S ELECTRIC DEMAND FOR THE YEAR
TWO THOUSAND SEVEN, AS DETERMINED BY THE DEPARTMENT.
(B) IN THE EVENT THAT THE ELECTRIC CORPORATION DETERMINES THAT IT IS
NECESSARY TO INSTALL A DEDICATED TRANSFORMER, TRANSFORMERS OR OTHER
EQUIPMENT TO PROTECT THE SAFETY AND ADEQUACY OF ELECTRIC SERVICE
PROVIDED TO OTHER CUSTOMERS, A CUSTOMER-GENERATOR SHALL PAY THE ELECTRIC
A. 409 3
CORPORATION'S ACTUAL COSTS OF INSTALLING THE TRANSFORMER, TRANSFORMERS
OR OTHER EQUIPMENT;
(I) IN THE CASE OF A CUSTOMER-GENERATOR WHO OWNS OR OPERATES SOLAR
ELECTRIC GENERATING EQUIPMENT, UP TO A MAXIMUM AMOUNT OF THREE HUNDRED
FIFTY DOLLARS.
(II) IN THE CASE OF A CUSTOMER-GENERATOR OR COMMERCIAL CUSTOMER WHO
OWNS OR OPERATES FARM WASTE ELECTRIC GENERATING EQUIPMENT LOCATED AND
USED AT HIS OR HER "FARM OPERATION," UP TO A TOTAL AMOUNT OF THREE THOU-
SAND DOLLARS PER "FARM OPERATION".
(III) IN THE CASE OF A CUSTOMER-GENERATOR OR COMMERCIAL CUSTOMER WHO
OWNS OR OPERATES FUEL CELL ELECTRIC GENERATING EQUIPMENT, THE FEE SHALL
BE ESTABLISHED BY THE COMMISSION.
4. RATES. AN ELECTRONIC CORPORATION SHALL USE NET ENERGY METERING TO
MEASURE AND CHARGE FOR THE NET ELECTRICITY SUPPLIED BY THE CORPORATION
AND PROVIDED TO THE CORPORATION BY A CUSTOMER-GENERATOR, ACCORDING TO
THESE REQUIREMENTS:
(A) IN THE EVENT THAT THE AMOUNT OF ELECTRICITY SUPPLIED BY THE CORPO-
RATION DURING THE BILLING PERIOD EXCEEDS THE AMOUNT OF ELECTRICITY
PROVIDED BY A CUSTOMER-GENERATOR, THE CORPORATION SHALL RECORD THE NET
AMOUNT OF ELECTRICITY PROVIDED TO IT BY THE CUSTOMER-GENERATOR AS A
CREDIT AT THE CORPORATION'S AVOIDED COST RATE. THE CREDIT PROVIDED TO
THE CUSTOMER-GENERATOR SHALL BE EQUAL TO THE COST OTHERWISE AVOIDED BY
THE ELECTRIC CORPORATION IN NOT HAVING TO PURCHASE SUCH ENERGY IN THE
COMPETITIVE MARKET OR GENERATE THE SAME THROUGH FACILITIES IT OWNS OR
CONTROLS.
(B) IN THE EVENT THAT THE AMOUNT OF ELECTRICITY PRODUCED BY A CUSTOM-
ER-GENERATOR DURING THE BILLING PERIOD EXCEEDS THE AMOUNT OF ELECTRICITY
USED BY THE CUSTOMER-GENERATOR, (I) FOR A CUSTOMER-GENERATOR WITH GENER-
ATING EQUIPMENT OF NOT MORE THAN TWENTY-FIVE KILOWATTS, THE CORPORATION
SHALL APPLY A CREDIT TO THE NEXT BILL FOR SERVICE TO THE CUSTOMER-GENER-
ATOR FOR THE NET ELECTRICITY PROVIDED AT THE SAME RATE PER KILOWATT HOUR
APPLICABLE TO SERVICE PROVIDED TO OTHER CUSTOMERS IN THE SAME SERVICE
CLASS WHICH DO NOT GENERATE ELECTRICITY ON SITE; (II) FOR A
CUSTOMER-GENERATOR WITH GENERATING EQUIPMENT OF MORE THAN TWENTY-FIVE
KILOWATTS, THE CORPORATION SHALL RECORD THE NET AMOUNT OF ELECTRICITY
PROVIDED TO IT BY THE CUSTOMER-GENERATOR AS A CREDIT AT THE CORPO-
RATION'S AVOIDED COST RATE. THE CREDIT PROVIDED TO THE CUSTOMER-GENERA-
TOR SHALL BE EQUAL TO THE COST OTHERWISE AVOIDED BY THE ELECTRIC CORPO-
RATION IN NOT HAVING TO PURCHASE SUCH ENERGY IN THE COMPETITIVE MARKET
OR GENERATE THE SAME THROUGH FACILITIES IT OWNS OR CONTROLS.
(C) AT THE END OF THE YEAR OR ANNUALIZED OVER THE PERIOD THAT SERVICE
IS SUPPLIED BY MEANS OF NET ENERGY METERING, THE CORPORATION SHALL
PROMPTLY ISSUE PAYMENT AT ITS AVOIDED COST TO THE CUSTOMER-GENERATOR FOR
THE VALUE OF ANY REMAINING CREDIT FOR THE EXCESS ELECTRICITY PRODUCED
DURING THE YEAR OR OVER THE ANNUALIZED PERIOD BY THE CUSTOMER-GENERATOR.
(D) WITH RESPECT TO CUSTOMER-GENERATORS THAT OWN OR OPERATE FARM WASTE
ELECTRIC GENERATING EQUIPMENT, IN THE EVENT THAT THE CORPORATION IMPOSES
CHARGES BASED ON KILOWATT, DEMAND ON CUSTOMERS WHO ARE IN THE SAME
SERVICE CLASS AS THE CUSTOMER-GENERATOR BUT WHICH DO NOT GENERATE ELEC-
TRICITY ON SITE, THE CORPORATION MAY IMPOSE THE SAME CHARGES AT THE SAME
RATES TO THE CUSTOMER-GENERATOR, PROVIDED, HOWEVER, THAT THE KILOWATT
DEMAND FOR SUCH DEMAND CHARGES IS DETERMINED BY THE MAXIMUM MEASURED
KILOWATT DEMAND ACTUALLY SUPPLIED BY THE CORPORATION TO THE
CUSTOMER-GENERATOR DURING THE BILLING PERIOD.
5. SAFETY STANDARDS. (A) ON OR BEFORE THREE MONTHS AFTER THE EFFECTIVE
DATE OF THIS SECTION, EACH ELECTRIC CORPORATION SHALL ESTABLISH STAND-
A. 409 4
ARDS THAT ARE NECESSARY FOR NET ENERGY METERING AND THE INTERCONNECTION
OF SOLAR, FUEL CELL OR FARM WASTE ELECTRIC GENERATING EQUIPMENT TO ITS
SYSTEM AND THAT THE COMMISSION SHALL DETERMINE ARE NECESSARY FOR SAFE
AND ADEQUATE SERVICE AND FURTHER THE PUBLIC POLICY SET FORTH IN THIS
SECTION. SUCH STANDARDS MAY INCLUDE BUT SHALL NOT BE LIMITED TO:
(I) EQUIPMENT NECESSARY TO ISOLATE AUTOMATICALLY THE SOLAR, FUEL CELL
AND FARM WASTE GENERATING SYSTEM FROM THE UTILITY SYSTEM FOR VOLTAGE AND
FREQUENCY DEVIATIONS; AND
(II) A MANUAL LOCKABLE DISCONNECT SWITCH PROVIDED BY THE CUSTOMER-GEN-
ERATOR WHICH SHALL BE LOCATED ON THE OUTSIDE OF THE CUSTOMER'S PREMISES
AND EXTERNALLY ACCESSIBLE FOR THE PURPOSE OF ISOLATING THE SOLAR, FUEL
CELL AND FARM WASTE ELECTRIC GENERATING EQUIPMENT.
(B) UPON ITS OWN MOTION OR UPON A COMPLAINT, THE COMMISSION, OR ITS
DESIGNATED REPRESENTATIVE, MAY INVESTIGATE AND MAKE A DETERMINATION AS
TO THE REASONABLENESS AND NECESSITY OF THE STANDARDS OR RESPONSIBILITY
FOR COMPLIANCE WITH THE STANDARDS.
(I) IN THE CASE OF A CUSTOMER-GENERATOR WHO OWNS OR OPERATES SOLAR,
FUEL CELL OR FARM WASTE ELECTRIC GENERATING EQUIPMENT LOCATED AND USED
AT THE SAME SITE WHERE THE EQUIPMENT IS LOCATED, AN ELECTRIC CORPORATION
MAY NOT REQUIRE A CUSTOMER-GENERATOR TO COMPLY WITH ADDITIONAL SAFETY OR
PERFORMANCE STANDARDS, PERFORM OR PAY FOR ADDITIONAL TESTS, OR PURCHASE
ADDITIONAL LIABILITY INSURANCE PROVIDED THAT:
(1) THE ELECTRIC GENERATING EQUIPMENT MEETS THE SAFETY STANDARDS
ESTABLISHED PURSUANT TO THIS PARAGRAPH; AND
(2) THE TOTAL RATED GENERATING CAPACITY (MEASURED IN KW) OF SOLAR,
FUEL CELL OR FARM WASTE ELECTRIC GENERATING EQUIPMENT THAT PROVIDES
ELECTRICITY TO THE ELECTRIC CORPORATION THROUGH THE SAME LOCAL FEEDER
LINE, DOES NOT EXCEED TWENTY PERCENT OF THE RATED CAPACITY OF THAT LOCAL
FEEDER LINE.
(II) IN THE EVENT THAT THE TOTAL RATED GENERATING CAPACITY OF SOLAR,
FUEL CELL OR FARM WASTE ELECTRIC GENERATING EQUIPMENT THAT PROVIDES
ELECTRICITY TO THE ELECTRIC CORPORATION THROUGH THE SAME LOCAL FEEDER
LINE EXCEEDS TWENTY PERCENT OF THE RATED CAPACITY OF THE LOCAL FEEDER
LINE, THE ELECTRIC CORPORATION MAY REQUIRE THE CUSTOMER-GENERATOR TO
COMPLY WITH REASONABLE MEASURES TO ENSURE SAFETY OF THAT LOCAL FEEDER
LINE.
6. ELECTRIC RESTRUCTURING. NOTWITHSTANDING THE PROVISIONS OF THIS
SECTION, INCLUDING, BUT NOT LIMITED TO PARAGRAPH (B) OF SUBDIVISION
THREE OF THIS SECTION, A CUSTOMER-GENERATOR SHALL COMPLY WITH ANY APPLI-
CABLE DETERMINATIONS OF THE COMMISSION RELATING TO RESTRUCTURING OF THE
ELECTRIC INDUSTRY.
S 66-N. NET ENERGY METERING FOR WIND ELECTRIC GENERATING SYSTEMS. 1.
DEFINITIONS. AS USED IN THIS SECTION, THE FOLLOWING TERMS SHALL HAVE THE
FOLLOWING MEANINGS:
(A) "CUSTOMER-GENERATOR" MEANS A CUSTOMER OF AN ELECTRIC CORPORATION,
WHO OWNS OR OPERATES WIND ELECTRIC GENERATING EQUIPMENT USED AT THE SAME
SITE ON WHICH THE EQUIPMENT IS LOCATED.
(B) "NET ENERGY METER" MEANS A METER THAT MEASURES THE REVERSE FLOW OF
ELECTRICITY TO REGISTER THE DIFFERENCE BETWEEN THE ELECTRICITY SUPPLIED
BY AN ELECTRIC CORPORATION TO THE CUSTOMER-GENERATOR AND THE ELECTRICITY
PROVIDED TO THE CORPORATION BY THAT CUSTOMER-GENERATOR.
(C) "NET ENERGY METERING" MEANS THE USE OF A NET ENERGY METER TO MEAS-
URE, DURING THE BILLING PERIOD APPLICABLE TO A CUSTOMER-GENERATOR, THE
NET AMOUNT OF ELECTRICITY SUPPLIED BY AN ELECTRIC CORPORATION AND
PROVIDED TO THE CORPORATION BY A CUSTOMER-GENERATOR.
A. 409 5
(D) "WIND ELECTRIC GENERATING EQUIPMENT" MEANS A WIND GENERATOR OR
GENERATORS THAT IS MANUFACTURED, INSTALLED, AND OPERATED IN ACCORDANCE
WITH APPLICABLE GOVERNMENT AND INDUSTRY STANDARDS, THAT IS CONNECTED TO
THE ELECTRIC SYSTEM AND OPERATED IN CONJUNCTION WITH AN ELECTRIC CORPO-
RATION'S TRANSMISSION AND DISTRIBUTION FACILITIES, AND THAT IS OPERATED
IN COMPLIANCE WITH ANY STANDARDS AND REQUIREMENTS ESTABLISHED UNDER THIS
SECTION.
2. INTERCONNECTION AND NET ENERGY METERING. AN ELECTRIC CORPORATION
SHALL PROVIDE FOR THE INTERCONNECTION OF WIND ELECTRIC GENERATING EQUIP-
MENT OWNED OR OPERATED BY A CUSTOMER-GENERATOR AND FOR NET ENERGY METER-
ING, PROVIDED THAT THE CUSTOMER-GENERATOR ENTERS INTO A NET ENERGY
METERING CONTRACT WITH THE CORPORATION OR COMPLIES WITH THE CORPO-
RATION'S NET ENERGY METERING SCHEDULE AND COMPLIES WITH STANDARDS AND
REQUIREMENTS ESTABLISHED UNDER THIS SECTION. THE CUSTOMER-GENERATOR
SHALL BE RESPONSIBLE FOR PAYMENT OF ONE-HALF OF THE EXPENSE OF SUCH
INTERCONNECTION ON WIND-ELECTRIC GENERATING EQUIPMENT WITH A RATED
CAPACITY OF MORE THAN TEN KILOWATTS.
3. CONDITIONS OF SERVICE. (A) ON OR BEFORE THREE MONTHS AFTER THE
EFFECTIVE DATE OF THIS SECTION, EACH ELECTRIC CORPORATION SHALL DEVELOP
A MODEL CONTRACT AND FILE A SCHEDULE THAT ESTABLISHES CONSISTENT AND
REASONABLE RATES, TERMS AND CONDITIONS FOR NET ENERGY METERING TO
CUSTOMER-GENERATORS, ACCORDING TO THE REQUIREMENTS OF THIS SECTION. THE
COMMISSION SHALL RENDER A DECISION WITHIN THREE MONTHS FROM THE DATE ON
WHICH THE SCHEDULE IS FILED. EACH ELECTRIC CORPORATION SHALL MAKE SUCH
CONTRACT AND SCHEDULE AVAILABLE TO CUSTOMER-GENERATORS ON A FIRST COME,
FIRST SERVED BASIS.
(B) IN THE EVENT THAT THE ELECTRIC CORPORATION DETERMINES THAT IT IS
NECESSARY TO INSTALL A DEDICATED TRANSFORMER OR TRANSFORMERS TO PROTECT
THE SAFETY AND ADEQUACY OF ELECTRIC SERVICE PROVIDED TO OTHER CUSTOMERS,
A CUSTOMER-GENERATOR SHALL PAY THE ELECTRIC CORPORATION'S ACTUAL COSTS
OF INSTALLING THE TRANSFORMER OR TRANSFORMERS;
(I) IN THE CASE OF A CUSTOMER-GENERATOR WHO OWNS AND OPERATES WIND
ELECTRIC GENERATING EQUIPMENT LOCATED AND USED AT THE SAME SITE WITH A
COMBINED RATE CAPACITY OF NOT MORE THAN TWENTY-FIVE KILOWATTS, UP TO A
MAXIMUM AMOUNT OF SEVEN HUNDRED FIFTY DOLLARS; AND
(II) IN THE CASE OF A CUSTOMER-GENERATOR WHO OWNS AND OPERATES WIND
ELECTRIC GENERATING EQUIPMENT LOCATED AND USED AT THE SAME SITE WITH A
COMBINED RATED CAPACITY EQUAL TO OR GREATER THAN TWENTY-FIVE KILOWATTS,
THE PUBLIC SERVICE COMMISSION SHALL DETERMINE A RATE SCHEDULE THAT IS
PROPORTIONATE WITH THE RATED CAPACITY OF THE GENERATING EQUIPMENT.
(C) AN ELECTRIC CORPORATION SHALL IMPOSE NO OTHER CHARGE OR FEE,
INCLUDING, BUT NOT LIMITED TO, BACK UP, STAND BY OR DEMAND CHARGES, FOR
THE PROVISION OF NET METERING TO A CUSTOMER-GENERATOR.
4. RATES. AN ELECTRIC CORPORATION SHALL USE NET ENERGY METERING TO
MEASURE AND CHARGE FOR THE NET ELECTRICITY SUPPLIED BY THE CORPORATION
AND PROVIDED TO THE CORPORATION BY A CUSTOMER-GENERATOR, ACCORDING TO
THE FOLLOWING REQUIREMENTS:
(A) IN THE EVENT THAT THE AMOUNT OF ELECTRICITY SUPPLIED BY THE CORPO-
RATION DURING THE BILLING PERIOD EXCEEDS THE AMOUNT OF ELECTRICITY
PROVIDED BY A CUSTOMER-GENERATOR, THE CORPORATION SHALL CHARGE THE
CUSTOMER-GENERATOR FOR THE NET ELECTRICITY SUPPLIED AT THE SAME RATE PER
KILOWATT HOUR APPLICABLE TO SERVICE PROVIDED TO OTHER CUSTOMERS IN THE
SAME SERVICE CLASS WHICH DO NOT GENERATE ELECTRICITY ON SITE.
(B) IN THE EVENT THAT THE AMOUNT OF ELECTRICITY PRODUCED BY A CUSTOM-
ER-GENERATOR DURING THE BILLING PERIOD EXCEEDS THE AMOUNT OF ELECTRICITY
USED BY THE CUSTOMER-GENERATOR, (I) FOR A CUSTOMER-GENERATOR WITH WIND
A. 409 6
ELECTRIC GENERATING EQUIPMENT OF NOT MORE THAN TWENTY-FIVE KILOWATTS,
THE CORPORATION SHALL APPLY A CREDIT TO THE NEXT BILL FOR SERVICE TO THE
CUSTOMER-GENERATOR FOR THE NET ELECTRICITY PROVIDED AT THE SAME RATE PER
KILOWATT HOUR APPLICABLE TO SERVICE PROVIDED TO OTHER CUSTOMERS IN THE
SAME SERVICE CLASS WHICH DO NOT GENERATE ELECTRICITY ON SITE; (II) FOR A
CUSTOMER-GENERATOR WITH WIND ELECTRIC GENERATING EQUIPMENT OF MORE THAN
TWENTY-FIVE KILOWATTS, THE CORPORATION SHALL RECORD THE NET AMOUNT OF
ELECTRICITY PROVIDED TO IT BY THE CUSTOMER-GENERATOR AS A CREDIT AT THE
CORPORATION'S AVOIDED COST RATE. THE CREDIT PROVIDED TO THE
CUSTOMER-GENERATOR SHALL BE EQUAL TO THE COST OTHERWISE AVOIDED BY THE
ELECTRIC CORPORATION IN NOT HAVING TO PURCHASE SUCH ENERGY IN THE
COMPETITIVE MARKET OR GENERATE THE SAME THROUGH FACILITIES IT OWNS OR
CONTROLS.
(C) AT THE END OF THE YEAR OR ANNUALIZED OVER THE PERIOD THAT SERVICE
IS SUPPLIED BY MEANS OF NET ENERGY METERING, THE CORPORATION SHALL
PROMPTLY ISSUE PAYMENT AT ITS AVOIDED COST TO THE CUSTOMER-GENERATOR FOR
THE VALUE OF ANY REMAINING CREDIT FOR THE EXCESS ELECTRICITY PRODUCED
DURING THE YEAR OR OVER THE ANNUALIZED PERIOD BY THE CUSTOMER-GENERATOR.
5. SAFETY STANDARDS. (A) ON OR BEFORE THREE MONTHS AFTER THE EFFECTIVE
DATE OF THIS SECTION, EACH ELECTRIC CORPORATION SHALL ESTABLISH STAND-
ARDS THAT ARE NECESSARY FOR NET ENERGY METERING AND THE INTERCONNECTION
OF WIND ELECTRIC GENERATING EQUIPMENT TO ITS SYSTEM AND THAT THE COMMIS-
SION SHALL DETERMINE ARE NECESSARY FOR SAFE AND ADEQUATE SERVICE AND
FURTHER THE PUBLIC POLICY SET FORTH IN THIS SECTION. SUCH STANDARDS MAY
INCLUDE, BUT SHALL NOT BE LIMITED TO:
(I) EQUIPMENT NECESSARY TO ISOLATE AUTOMATICALLY THE GENERATING SYSTEM
FROM THE UTILITY SYSTEM FOR VOLTAGE AND FREQUENCY DEVIATIONS; AND
(II) A MANUAL LOCKABLE DISCONNECT SWITCH PROVIDED BY THE CUSTOMER-GEN-
ERATOR WHICH SHALL BE LOCATED ON THE OUTSIDE OF THE CUSTOMER'S PREMISES
AND EXTERNALLY ACCESSIBLE FOR THE PURPOSE OF ISOLATING THE ELECTRIC
GENERATING EQUIPMENT.
(B) UPON ITS OWN MOTION OR UPON A COMPLAINT, THE COMMISSION, OR ITS
DESIGNATED REPRESENTATIVE, MAY INVESTIGATE AND MAKE A DETERMINATION AS
TO THE REASONABLENESS AND NECESSITY OF THE STANDARDS OR RESPONSIBILITY
FOR COMPLIANCE WITH THE STANDARDS.
(I) AN ELECTRIC CORPORATION MAY NOT REQUIRE A CUSTOMER-GENERATOR TO
COMPLY WITH ADDITIONAL SAFETY OR PERFORMANCE STANDARDS, OR PERFORM OR
PAY FOR ADDITIONAL TESTS, OR PURCHASE ADDITIONAL LIABILITY INSURANCE,
PROVIDED THAT:
A. THE ELECTRIC GENERATING EQUIPMENT MEETS THE SAFETY STANDARDS ESTAB-
LISHED PURSUANT TO THIS PARAGRAPH; AND
B. THE TOTAL RATED GENERATING CAPACITY (MEASURED IN KW) OF ELECTRIC
GENERATING EQUIPMENT THAT PROVIDES ELECTRICITY TO THE ELECTRIC CORPO-
RATION THROUGH THE SAME LOCAL FEEDER LINE, DOES NOT EXCEED TWENTY
PERCENT OF THE RATED CAPACITY OF THAT LOCAL FEEDER LINE.
(II) IN THE EVENT THAT THE TOTAL RATED GENERATING CAPACITY OF ELECTRIC
GENERATING EQUIPMENT THAT PROVIDES ELECTRICITY TO THE ELECTRIC CORPO-
RATION THROUGH THE SAME LOCAL FEEDER LINE EXCEEDS TWENTY PERCENT OF THE
RATED CAPACITY OF THE LOCAL FEEDER LINE, THE ELECTRIC CORPORATION MAY
REQUIRE THE CUSTOMER-GENERATOR TO COMPLY WITH REASONABLE MEASURES TO
ENSURE SAFETY OF THAT LOCAL FEEDER LINE.
6. ELECTRIC RESTRUCTURING. NOTWITHSTANDING THE PROVISIONS OF THIS
SECTION, A CUSTOMER-GENERATOR SHALL COMPLY WITH ANY APPLICABLE DETERMI-
NATIONS OF THE COMMISSION RELATING TO RESTRUCTURING OF THE ELECTRIC
INDUSTRY.
S 2. This act shall take effect immediately.