AN ACT to amend the state finance law, in relation to payment on public
works contracts
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. Subdivision 1 of section 139-f of the state finance law, as
added by chapter 769 of the laws of 1978, is amended to read as follows:
1. Payment by public owners to contractors. The contractor shall peri-
odically, in accordance with the terms of the contract, submit to the
public owner and/or [his] ITS agent a requisition for a progress payment
for the work performed and/or materials furnished to the date of the
requisition, less any amount previously paid to the contractor. THE
CONTRACTOR SHALL INCLUDE IN EACH SUCH REQUISITION A REQUEST FOR PAYMENT
FOR ALL WORK PERFORMED AND MATERIAL PROVIDED BY SUBCONTRACTORS AND/OR
MATERIALMEN FOR WHICH THE CONTRACTOR HAS RECEIVED A REQUEST FOR PAYMENT
AND WHICH THE CONTRACTOR HAS NOT REJECTED, IN WHOLE OR IN PART. EACH
SUBCONTRACTOR AND/OR MATERIALMAN REQUEST FOR PAYMENT SHALL BE ACCEPTED
OR REJECTED, IN WHOLE OR IN PART, BY THE CONTRACTOR NOT LESS THAN THIRTY
BUT NOT MORE THAN FORTY-FIVE DAYS FOLLOWING THE DATE OF THE CONTRACTOR'S
RECEIPT OF SAID SUBCONTRACTOR'S AND/OR MATERIALMAN'S REQUEST FOR
PAYMENT. IN THE EVENT THE CONTRACTOR DETERMINES TO REJECT SUCH SUBCON-
TRACTOR'S AND/OR MATERIALMAN'S REQUEST FOR PAYMENT, IN WHOLE OR IN PART,
IT SHALL PROVIDE WRITTEN NOTICE OF THE REJECTION TO THE APPLICABLE
SUBCONTRACTOR AND/OR MATERIALMAN ACCOMPANIED BY A REASONED ELABORATION
IN SUPPORT OF THE CONTRACTOR'S REJECTION, IN WHOLE OR IN PART, TOGETHER
WITH A WRITTEN DESCRIPTION OF THE WORK, MATERIALS, SUPPORTING DOCUMENTA-
TION OR OTHER INFORMATION REQUIRED IN ORDER FOR THE REQUEST FOR PAYMENT
TO BE APPROVED; PROVIDED, HOWEVER, THE CONTRACTOR SHALL INCLUDE IN ITS
NEXT REQUISITION ANY PORTION OF SUCH SUBCONTRACTOR'S OR MATERIALMAN'S
REQUEST FOR PAYMENT WHICH IS NOT REJECTED BY THE CONTRACTOR; AND NO SUCH
NOTICE OR ELABORATION SHALL BE REQUIRED FOR PURPOSES OF RETAINAGE AS
AUTHORIZED BY THIS SECTION. THE CONTRACTOR'S ACCEPTANCE OR REJECTION OF
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD14335-02-6
S. 7264 2
A REQUEST FOR A PAYMENT FOR WORK PERFORMED AND MATERIAL PROVIDED BY
SUBCONTRACTORS AND/OR MATERIALMEN SHALL IN NO WAY AFFECT THE PUBLIC
OWNER'S LEGAL RIGHTS TO APPROVE OR REJECT, IN WHOLE OR IN PART, THE
CONTRACTOR'S REQUEST FOR PAYMENT. The public owner shall in accordance
with the terms of the contract approve and promptly pay the requisition
for the progress payment less an amount necessary to satisfy any claims,
liens or judgments against the contractor which have not been suitably
discharged and less any retained amount as hereafter described. The
public owner shall retain not more than five per centum of each progress
payment to the contractor except that the public owner may retain in
excess of five per centum but not more than ten per centum of each
progress payment to the contractor provided that there are no require-
ments by the public owner for the contractor to provide a performance
bond and a labor and material bond both in the full amount of the
contract. The public owner shall pay, IN ACCORDANCE WITH THE TERMS OF
THE CONTRACT, upon requisition from the contractor, for materials perti-
nent to the project which have been delivered to the site or off-site by
the contractor and/or subcontractor and suitably stored and secured as
required by the public owner and the contractor provided, the public
owner may limit such payment to materials in short and/or critical
supply and materials specially fabricated for the project each as
defined in the contract. When the work or major portions thereof as
contemplated by the terms of the contract are substantially completed,
the contractor shall submit to the public owner and/or his agent a
requisition for payment of the remaining amount of the contract balance.
Upon receipt of such requisition the public owner shall approve and
promptly pay the remaining amount of the contract balance less two times
the value of any remaining items to be completed and an amount necessary
to satisfy any claims, liens or judgments against the contractor which
have not been suitably discharged. As the remaining items of work are
satisfactorily completed or corrected, the public owner shall promptly
pay, upon receipt of a requisition, for these remaining items less an
amount necessary to satisfy any claims, liens or judgments against the
contractor which have not been suitably discharged. Any claims, liens
and judgments referred to in this section shall pertain to the project
and shall be filed in accordance with the terms of the applicable
contract and/or applicable laws.
S 2. This act shall take effect immediately and shall apply to all
contracts advertised or solicited for bid by a public owner on or after
such effective date.