S T A T E O F N E W Y O R K
________________________________________________________________________
10446
I N A S S E M B L Y
May 27, 2016
___________
Introduced by M. of A. CUSICK -- read once and referred to the Committee
on Economic Development
AN ACT to amend the general business law, in relation to payment and
retainage in construction contracts
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. Section 756 of the general business law is amended by
adding a new subdivision 7 to read as follows:
7. "SUBSTANTIAL COMPLETION" MEANS THE STATE IN THE PROGRESS OF THE
PROJECT WHEN THE WORK REQUIRED BY THE CONSTRUCTION CONTRACT WITH THE
PROJECT OWNER IS SUFFICIENTLY COMPLETE IN ACCORDANCE WITH THE
CONSTRUCTION CONTRACT SO THAT THE PROJECT OWNER MAY OCCUPY OR UTILIZE
THE WORK FOR ITS INTENDED USE; PROVIDED FURTHER, THAT "SUBSTANTIAL
COMPLETION" SHALL APPLY TO THE ENTIRE PROJECT OR A PORTION OF THE ENTIRE
PROJECT IF THE CONSTRUCTION CONTRACT WITH THE PROJECT OWNER PROVIDES FOR
OCCUPANCY OR USE OF A PORTION OF THE PROJECT.
S 2. The opening paragraph of paragraph (a) of subdivision 2 of
section 756-a of the general business law, as amended by chapter 417 of
the laws of 2009, is amended to read as follows:
A contractor shall be entitled to invoice the owner for interim
payments at the end of the billing cycle. A contractor shall be entitled
to submit a final invoice for payment in full [upon the performance of
all the contractor's obligation under the contract] UPON REACHING
SUBSTANTIAL COMPLETION UNDER THE CONSTRUCTION CONTRACT.
S 3. Section 756-c of the general business law, as added by chapter
127 of the laws of 2002, is amended to read as follows:
S 756-c. Retention. By mutual agreement of the relevant parties an
owner may retain [a reasonable amount] NO MORE THAN FIVE PER CENTUM of
the contract sum as retainage. A contractor or subcontractor may also
retain [a reasonable amount] NO MORE THAN FIVE PER CENTUM for retainage
[so long as the amount does not] AND IN NO CASE SHALL RETAINAGE exceed
the actual percentage retained by the owner. Retainage shall be released
by the owner to the contractor no later than thirty days after the final
approval of the work under a construction contract. In the event that an
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD15589-01-6
A. 10446 2
owner fails to release retainage as required by this article, or the
contractor or subcontractor fails to release a proportionate amount of
retainage to the relevant parties after receipt of retainage from the
owner, the owner, contractor, or subcontractor, as the case may be,
shall be subject to the payment of interest at the rate of one percent
per month on the date retention was due and owing.
S 4. This act shall take effect immediately and shall apply to
contracts entered into on or after such effective date.