AN ACT to amend the state finance law, in relation to requiring contrac-
tors on public works projects to pay their subcontractors upon
completion of work
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. Subdivision 2 of section 139-f of the state finance law, as
amended by section 16 of part MM of chapter 57 of the laws of 2008, is
amended to read as follows:
2. Payment by contractors to subcontractors. [Within seven calendar
days of the receipt of any payment from the public owner] PAYMENT BY THE
CONTRACTOR TO A SUBCONTRACTOR OR MATERIALMAN SHALL NOT BE CONTINGENT
UPON PAYMENT BY AN OWNER TO THE CONTRACTOR. UPON COMPLETION OF THE
PERFORMANCE OF WORK OR MATERIALS SUPPLIED, the contractor shall pay each
of his subcontractors and materialmen the [proceeds from the] payment
representing the value of the work performed and/or materials furnished
by the subcontractor and/or materialman and reflecting the percentage of
the subcontractor's work completed or the materialman's material
supplied in the requisition approved by the owner and based upon the
actual value of the subcontract or purchase order less an amount neces-
sary to satisfy any claims, liens or judgments against the subcontractor
or materialman which have not been suitably discharged and less any
retained amount as hereafter described. Failure by the contractor to pay
any subcontractor or materialman [within seven calendar days of the
receipt of any payment from the public owner] UPON COMPLETION OF THE
PERFORMANCE OF WORK OR MATERIALS SUPPLIED shall result in the commence-
ment and accrual of interest on amounts due to such subcontractor or
materialman for the period beginning on the day immediately following
the [expiration of such seven calendar day period] COMPLETION OF THE
PERFORMANCE OF WORK OR MATERIALS SUPPLIED and ending on the date on
which payment is made by the contractor to such subcontractor or materi-
alman. Such interest payment shall be the sole responsibility of the
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD08676-01-5
A. 9965 2
contractor, and shall be paid at the rate of interest in effect on the
date payment is made by the contractor.
Notwithstanding any other provision of law to the contrary, interest
shall be computed at the rate established in paragraph (b) of subdivi-
sion one of section seven hundred fifty-six-b of the general business
law. [The contractor shall retain not more than five per centum of each
payment to the subcontractor and/or materialman except that the contrac-
tor may retain in excess of five per centum but not more than ten per
centum of each payment to the subcontractor provided that prior to
entering into a subcontract with the contractor, the subcontractor is
unable or unwilling to provide a performance bond and a labor and mate-
rial bond, both in the full amount of the subcontract, at the request of
the contractor. However, the contractor shall retain nothing from those
payments representing proceeds owed the subcontractor and/or materialman
from the public owner's payments to the contractor for the remaining
amounts of the contract balance as provided in subdivision one of this
section. If the contractor has failed to submit a requisition for
payment of the remaining amounts of the contract balance within ninety
days of substantial completion as provided in subdivision one of this
section, then any clause in the subcontract between the contractor and
the subcontractor or materialman which states that payment by the
contractor to such subcontractor or materialman is contingent upon
payment by the owner to the contractor shall be deemed invalid. Within
seven calendar days of the receipt of payment from the contractor, the
subcontractor and/or materialman shall pay each of his subcontractors
and materialmen in the same manner as the contractor has paid the
subcontractor, including interest as herein provided above. Nothing
provided herein shall create any obligation on the part of the public
owner to pay or to see to the payment of any moneys to any subcontractor
or materialman from any contractor nor shall anything provided herein
serve to create any relationship in contract or otherwise, implied or
expressed, between the subcontractor or materialman and the public
owner.]
S 2. This act shall take effect immediately.