S T A T E O F N E W Y O R K
________________________________________________________________________
7613
I N S E N A T E
May 11, 2016
___________
Introduced by Sen. MARTINS -- read twice and ordered printed, and when
printed to be committed to the Committee on Judiciary
AN ACT to amend the general obligations law, in relation to payment on
construction contracts
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. Section 5-322.2 of the general obligations law is amended
by adding a new subdivision 2-a to read as follows:
2-A. THE CONTRACTOR SHALL PERIODICALLY, IN ACCORDANCE WITH THE TERMS
OF THE CONTRACT, SUBMIT TO THE OWNER OR OWNERS A REQUISITION FOR A
PROGRESS PAYMENT FOR THE WORK PERFORMED AND/OR MATERIALS FURNISHED TO
THE DATE OF THE REQUISITION, LESS ANY AMOUNT PREVIOUSLY PAID TO THE
CONTRACTOR. THE CONTRACTOR SHALL INCLUDE IN EACH SUCH REQUISITION A
REQUEST FOR PAYMENT FOR ALL WORK PERFORMED AND MATERIAL PROVIDED BY
SUBCONTRACTORS AND/OR MATERIALMEN FOR WHICH THE CONTRACTOR HAS RECEIVED
A REQUEST FOR PAYMENT AND WHICH THE CONTRACTOR HAS NOT REJECTED, IN
WHOLE OR IN PART. EACH SUBCONTRACTOR'S AND/OR MATERIALMAN'S REQUEST FOR
PAYMENT SHALL BE ACCEPTED OR REJECTED, IN WHOLE OR IN PART, BY THE
CONTRACTOR NOT LESS THAN THIRTY BUT NOT MORE THAN FORTY-FIVE DAYS
FOLLOWING THE DATE OF THE CONTRACTOR'S RECEIPT OF SAID SUBCONTRACTOR'S
AND/OR MATERIALMAN'S REQUEST FOR PAYMENT. IN THE EVENT THE CONTRACTOR
DETERMINES TO REJECT SUCH SUBCONTRACTOR'S AND/OR MATERIALMAN'S REQUEST
FOR PAYMENT, IN WHOLE OR IN PART, IT SHALL PROVIDE WRITTEN NOTICE OF THE
REJECTION TO THE APPLICABLE SUBCONTRACTOR AND/OR MATERIALMAN ACCOMPANIED
BY A REASONED ELABORATION IN SUPPORT OF THE CONTRACTOR'S REJECTION, IN
WHOLE OR IN PART, TOGETHER WITH A WRITTEN DESCRIPTION OF THE WORK, MATE-
RIALS, SUPPORTING DOCUMENTATION OR OTHER INFORMATION REQUIRED IN ORDER
FOR THE REQUEST FOR PAYMENT TO BE APPROVED; PROVIDED, HOWEVER, THE
CONTRACTOR SHALL INCLUDE IN ITS NEXT REQUISITION ANY PORTION OF SUCH
SUBCONTRACTOR'S OR MATERIALMAN'S REQUEST FOR PAYMENT WHICH IS NOT
REJECTED BY THE CONTRACTOR; AND NO SUCH NOTICE OR ELABORATION SHALL BE
REQUIRED FOR PURPOSES OF RETAINAGE AS AUTHORIZED BY THIS SECTION. THE
CONTRACTOR'S ACCEPTANCE OR REJECTION OF A REQUEST FOR PAYMENT FOR WORK
PERFORMED AND MATERIAL PROVIDED BY SUBCONTRACTORS AND/OR MATERIALMEN
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD15187-01-6
S. 7613 2
SHALL IN NO WAY AFFECT THE OWNER'S OR OWNERS' LEGAL RIGHTS TO APPROVE OR
REJECT, IN WHOLE OR IN PART, THE CONTRACTOR'S REQUEST FOR PAYMENT. THE
OWNER OR OWNERS SHALL, IN ACCORDANCE WITH THE TERMS OF THE CONTRACT,
APPROVE AND PROMPTLY PAY THE REQUISITION FOR THE PROGRESS PAYMENT LESS
AN AMOUNT NECESSARY TO SATISFY ANY CLAIMS, LIENS OR JUDGMENTS AGAINST
THE CONTRACTOR WHICH HAVE NOT BEEN SUITABLY DISCHARGED AND LESS ANY
RETAINED AMOUNT AS HEREAFTER DESCRIBED. THE OWNER OR OWNERS SHALL RETAIN
NOT MORE THAN FIVE PER CENTUM OF EACH PROGRESS PAYMENT TO THE CONTRACTOR
EXCEPT THAT THE OWNER OR OWNERS MAY RETAIN IN EXCESS OF FIVE PER CENTUM
BUT NOT MORE THAN TEN PER CENTUM OF EACH PROGRESS PAYMENT TO THE
CONTRACTOR PROVIDED THAT THERE ARE NO REQUIREMENTS BY THE OWNER OR
OWNERS FOR THE CONTRACTOR TO PROVIDE A PERFORMANCE BOND AND A LABOR AND
MATERIAL BOND BOTH IN THE FULL AMOUNT OF THE CONTRACT. THE OWNER OR
OWNERS SHALL PAY, UPON REQUISITION FROM THE CONTRACTOR, FOR MATERIALS
PERTINENT TO THE PROJECT WHICH HAVE BEEN DELIVERED TO THE SITE OR
OFF-SITE BY THE CONTRACTOR AND/OR SUBCONTRACTOR AND SUITABLY STORED AND
SECURED AS REQUIRED BY THE OWNER OR OWNERS AND THE CONTRACTOR PROVIDED,
THE OWNER OR OWNERS MAY LIMIT SUCH PAYMENT TO MATERIALS IN SHORT AND/OR
CRITICAL SUPPLY AND MATERIALS SPECIALLY FABRICATED FOR THE PROJECT EACH
AS DEFINED IN THE CONTRACT. WHEN THE WORK OR MAJOR PORTIONS THEREOF AS
CONTEMPLATED BY THE TERMS OF THE CONTRACT ARE SUBSTANTIALLY COMPLETED,
THE CONTRACTOR SHALL SUBMIT TO THE OWNER OR OWNERS A REQUISITION FOR
PAYMENT OF THE REMAINING AMOUNT OF THE CONTRACT BALANCE. UPON RECEIPT OF
SUCH REQUISITION THE OWNER OR OWNERS SHALL APPROVE AND PROMPTLY PAY THE
REMAINING AMOUNT OF THE CONTRACT BALANCE LESS TWO TIMES THE VALUE OF ANY
REMAINING ITEMS TO BE COMPLETED AND AN AMOUNT NECESSARY TO SATISFY ANY
CLAIMS, LIENS OR JUDGMENTS AGAINST THE CONTRACTOR WHICH HAVE NOT BEEN
SUITABLY DISCHARGED. AS THE REMAINING ITEMS OF WORK ARE SATISFACTORILY
COMPLETED OR CORRECTED, THE OWNER OR OWNERS SHALL PAY, IN ACCORDANCE
WITH THE TERMS OF THE CONTRACT, UPON RECEIPT OF A REQUISITION, FOR THESE
REMAINING ITEMS LESS AN AMOUNT NECESSARY TO SATISFY ANY CLAIMS, LIENS OR
JUDGMENTS AGAINST THE CONTRACTOR WHICH HAVE NOT BEEN SUITABLY
DISCHARGED. ANY CLAIMS, LIENS AND JUDGMENTS REFERRED TO IN THIS SECTION
SHALL PERTAIN TO THE PROJECT AND SHALL BE FILED IN ACCORDANCE WITH THE
TERMS OF THE APPLICABLE CONTRACT AND/OR APPLICABLE LAWS.
S 2. This act shall take effect on the ninetieth day after it shall
have become a law.