AN ACT to amend the administrative code of the city of New York, in
relation to requiring plan examiners to approve all applications and
inspections
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. Section 28-105.5 of the administrative code of the city of
New York, as amended by section 11 of part A of local law number 141 of
the city of New York for the year 2013, is amended to read as follows:
§ 28-105.5 Application for permit. All applications for permits shall
be submitted on forms furnished by the department. Applications shall
include all information required by this code, other applicable law or
the rules of the department. The applicant shall list any portions of
the design that have been approved for deferred submittal in accordance
with section 28-104.2.6. The application shall set forth an inspection
program for the project. An application for a permit shall be submitted
no later than 12 months after the approval of all required construction
documents (other than those documents approved for deferred submittal).
ALL PERMIT APPLICATIONS, INCLUDING AMENDED PERMIT APPLICATIONS FOR ITEMS
ELIGIBLE FOR DEFERRED SUBMITTAL PURSUANT TO SECTION 28-104.2.6 OF THIS
CHAPTER, WITH THE EXCEPTION OF PERMIT APPLICATIONS FOR COOPERATIVES AND
CONDOMINIUMS, SHALL BE REVIEWED AND APPROVED BY A PLAN EXAMINER PRIOR TO
ITS ISSUANCE BY THE COMMISSIONER.
§ 2. This act shall take effect immediately and shall apply to any
application or inspection made after such effective date.
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets