S T A T E   O F   N E W   Y O R K
 ________________________________________________________________________
 
                                   1387
 
                        2021-2022 Regular Sessions
 
                             I N  S E N A T E
 
                             January 11, 2021
                                ___________
 
 Introduced  by  Sens. BROOKS, AKSHAR, GALLIVAN -- read twice and ordered
   printed, and when printed to be committed to the Committee on Procure-
   ment and Contracts
 
 AN ACT to amend the state finance law and the general municipal law,  in
   relation  to requiring full payment for delivered and accepted materi-
   als pertaining to public work projects; and to amend the general busi-
   ness law, in relation to prohibiting the retention of any payment  due
   and owing a material supplier for a construction project
 
   THE  PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
 BLY, DO ENACT AS FOLLOWS:
 
   Section 1. Subdivisions 1 and 2 of section 139-f of the state  finance
 law,  subdivision  1  as  added  by  chapter 769 of the laws of 1978 and
 subdivision 2 as amended by section 16 of part MM of chapter 57  of  the
 laws of 2008, are amended to read as follows:
   1. Payment by public owners to contractors. The contractor shall peri-
 odically,  in  accordance  with the terms of the contract, submit to the
 public owner and/or [his] ITS agent a requisition for a progress payment
 for the work performed and/or materials furnished to  the  date  of  the
 requisition,  less  any  amount  previously  paid to the contractor. The
 public owner shall in accordance with the terms of the contract  approve
 and promptly pay the requisition for the progress payment less an amount
 necessary to satisfy any claims, liens or judgments against the contrac-
 tor which have not been suitably discharged and less any retained amount
 as hereafter described. The public owner shall retain not more than five
 per centum of each progress payment, NOT INCLUDING ANY PAYMENT FOR MATE-
 RIALS  PERTINENT  TO THE PROJECT WHICH HAVE BEEN DELIVERED, ACCEPTED AND
 ARE COVERED BY A MANUFACTURER'S WARRANTY,  AND/OR  ARE  GRADED  TO  MEET
 INDUSTRY  STANDARDS,  to the contractor except that the public owner may
 retain in excess of five per centum but not more than ten per centum  of
 each progress payment, NOT INCLUDING ANY PAYMENT FOR MATERIALS PERTINENT
 TO  THE PROJECT WHICH HAVE BEEN DELIVERED, ACCEPTED AND ARE COVERED BY A
 
  EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
                       [ ] is old law to be omitted.
              
             
                          
                                                                            LBD03376-01-1
 S. 1387                             2
 
 MANUFACTURER'S WARRANTY, AND/OR ARE GRADED TO MEET  INDUSTRY  STANDARDS,
 to  the contractor provided that there are no requirements by the public
 owner for the contractor to provide a performance bond and a  labor  and
 material  bond both in the full amount of the contract. The public owner
 shall pay IN FULL, upon requisition from the contractor, for ALL materi-
 als pertinent to the project which have been delivered to  the  site  or
 off-site  by the contractor and/or subcontractor and suitably stored and
 secured as required by the public owner and  the  contractor  [provided,
 the  public  owner  may  limit such payment to materials in short and/or
 critical supply and materials specially fabricated for the project  each
 as  defined in the contract]. When the work or major portions thereof as
 contemplated by the terms of the contract are  substantially  completed,
 the contractor shall submit to the public owner and/or [his] ITS agent a
 requisition for payment of the remaining amount of the contract balance.
 Upon  receipt  of  such  requisition  the public owner shall approve and
 promptly pay the remaining amount of the contract balance less two times
 the value of any remaining items to be completed and an amount necessary
 to satisfy any claims, liens or judgments against the  contractor  which
 have  not  been  suitably discharged. As the remaining items of work are
 satisfactorily completed or corrected, the public owner  shall  promptly
 pay,  upon  receipt  of a requisition, for these remaining items less an
 amount necessary to satisfy any claims, liens or judgments  against  the
 contractor  which  have  not been suitably discharged. Any claims, liens
 and judgments referred to in this section shall pertain to  the  project
 and  shall  be  filed  in  accordance  with  the terms of the applicable
 contract and/or applicable laws.
   2. Payment by contractors to  subcontractors.  Within  seven  calendar
 days of the receipt of any payment from the public owner, the contractor
 shall  pay each of [his] ITS subcontractors and materialmen the proceeds
 from the payment representing the value of  the  work  performed  and/or
 materials furnished by the subcontractor and/or materialman and reflect-
 ing  the  percentage  of  the  subcontractor's  work  completed  or  the
 materialman's material supplied in the requisition approved by the owner
 and based upon the actual value of the  subcontract  or  purchase  order
 less  an  amount  necessary  to  satisfy  any claims, liens or judgments
 against the subcontractor or materialman which have  not  been  suitably
 discharged  and, WITH REGARD TO SUBCONTRACTORS, less any retained amount
 as hereafter described. Failure by the contractor to pay any subcontrac-
 tor or materialman within seven calendar days  of  the  receipt  of  any
 payment  from  the  public  owner  shall  result in the commencement and
 accrual of interest on amounts due to such subcontractor or  materialman
 for the period beginning on the day immediately following the expiration
 of  such  seven  calendar  day  period  and  ending on the date on which
 payment is made by the contractor to such subcontractor or  materialman.
 Such  interest  payment shall be the sole responsibility of the contrac-
 tor, and shall be paid at the rate of interest in  effect  on  the  date
 payment  is made by the contractor.  Notwithstanding any other provision
 of law to the contrary, interest shall be computed at  the  rate  estab-
 lished  in  paragraph  (b)  of  subdivision one of section seven hundred
 fifty-six-b of the general business law. The contractor shall retain not
 more than five per centum of each payment to the  subcontractor  [and/or
 materialman] except that the contractor may retain in excess of five per
 centum  but  not more than ten per centum of each payment to the subcon-
 tractor provided that prior to entering  into  a  subcontract  with  the
 contractor,  the  subcontractor  is  unable  or  unwilling  to provide a
 performance bond and a labor and material bond, both in the full  amount
 S. 1387                             3
 
 of  the  subcontract,  at the request of the contractor.  THE CONTRACTOR
 SHALL PAY IN FULL, UPON PAYMENT BY THE PUBLIC OWNER, FOR  ALL  MATERIALS
 PERTINENT  TO  THE  PROJECT WHICH HAVE BEEN DELIVERED TO AND ACCEPTED AT
 THE  SITE  OR OFF-SITE BY A MATERIALMAN AND ARE COVERED BY A MANUFACTUR-
 ER'S WARRANTY, AND/OR ARE GRADED TO MEET  INDUSTRY  STANDARDS.  However,
 EXCEPT  IN THE CASE OF A MATERIALMAN WHO IS ALSO CONTRACTED TO INSTALL A
 PRODUCT HE/SHE DELIVERED, the contractor shall retain nothing from those
 payments representing proceeds owed the subcontractor and/or materialman
 from the public owner's payments to the  contractor  for  the  remaining
 amounts  of  the contract balance as provided in subdivision one of this
 section. If the contractor  has  failed  to  submit  a  requisition  for
 payment  of  the remaining amounts of the contract balance within ninety
 days of substantial completion as provided in subdivision  one  of  this
 section,  then  any clause in the subcontract between the contractor and
 the subcontractor or  materialman  which  states  that  payment  by  the
 contractor  to  such  subcontractor  or  materialman  is contingent upon
 payment by the owner to the contractor shall be deemed  invalid.  Within
 seven  calendar  days of the receipt of payment from the contractor, the
 subcontractor and/or materialman shall pay each of [his] ITS subcontrac-
 tors and materialmen in the same manner as the contractor has  paid  the
 subcontractor,  including  interest  as  herein  provided above. Nothing
 provided herein shall create any obligation on the part  of  the  public
 owner to pay or to see to the payment of any moneys to any subcontractor
 or  materialman  from  any contractor nor shall anything provided herein
 serve to create any relationship in contract or  otherwise,  implied  or
 expressed,  between  the  subcontractor  or  materialman  and the public
 owner.
   § 2. Paragraph (a) of subdivision 1 and subdivision 2 of section 106-b
 of the general municipal law, paragraph (a) of subdivision 1 as  amended
 by  chapter  98  of  the  laws  of  1995 and subdivision 2 as amended by
 section 15 of part MM of chapter 57 of the laws of 2008, are amended  to
 read as follows:
   (a) The contractor shall periodically, in accordance with the terms of
 the contract, submit to the public owner and/or [his] ITS agent a requi-
 sition  for  a  progress payment for the work performed and/or materials
 furnished to the date of the requisition less any amount previously paid
 to the contractor. The public owner shall in accordance with  the  terms
 of  the  contract  approve  and  promptly  pay  the  requisition for the
 progress payment less an amount necessary to satisfy any  claims,  liens
 or  judgments  against  the  contractor  which  have  not  been suitably
 discharged and less any retained  amount  as  hereafter  described.  The
 public owner shall retain not more than five per centum of each progress
 payment,  NOT  INCLUDING  ANY  PAYMENT  FOR  MATERIALS  PERTINENT TO THE
 PROJECT WHICH HAVE  BEEN  DELIVERED,  ACCEPTED  AND  ARE  COVERED  BY  A
 MANUFACTURER'S  WARRANTY,  AND/OR ARE GRADED TO MEET INDUSTRY STANDARDS,
 to the contractor except that the public owner may retain in  excess  of
 five  per  centum  but  not  more  than  ten per centum of each progress
 payment, NOT INCLUDING  ANY  PAYMENT  FOR  MATERIALS  PERTINENT  TO  THE
 PROJECT  WHICH  HAVE  BEEN  DELIVERED,  ACCEPTED  AND  ARE  COVERED BY A
 MANUFACTURER'S WARRANTY, AND/OR ARE GRADED TO MEET  INDUSTRY  STANDARDS,
 to  the contractor provided that there are no requirements by the public
 owner for the contractor to provide a performance bond and a  labor  and
 material  bond both in the full amount of the contract. The public owner
 shall pay IN FULL, upon requisition from the contractor, for ALL materi-
 als pertinent to the project which have been delivered to  the  site  or
 off-site  by the contractor and/or subcontractor and suitably stored and
 S. 1387                             4
 
 secured as required by the public owner and  the  contractor  [provided,
 the  public  owner  may  limit such payment to materials in short and/or
 critical supply and materials specially fabricated for the project  each
 as  defined in the contract]. When the work or major portions thereof as
 contemplated by the terms of the contract are  substantially  completed,
 the contractor shall submit to the public owner and/or [his] ITS agent a
 requisition for payment of the remaining amount of the contract balance.
 Upon  receipt  of  such  requisition  the public owner shall approve and
 promptly pay the remaining amount of the contract balance less two times
 the value of any remaining items to be completed and an amount necessary
 to satisfy any claims, liens or judgments against the  contractor  which
 have  not  been  suitably discharged. As the remaining items of work are
 satisfactorily completed or corrected, the public owner  shall  promptly
 pay,  upon  receipt  of  a  requisition,  for these items less an amount
 necessary to satisfy any claims, liens or judgments against the contrac-
 tor which have not been suitably discharged. Any claims, liens and judg-
 ments referred to in this section shall pertain to the project and shall
 be filed in accordance with the terms of the applicable contract  and/or
 applicable  laws.  Where  the public owner is other than the city of New
 York, the term "promptly pay" shall mean  payment  within  thirty  days,
 excluding  legal  holidays,  of  receipt  of the requisition unless such
 requisition is not approvable  in  accordance  with  the  terms  of  the
 contract. Notwithstanding the foregoing, where the public owner is other
 than  the city of New York and is a municipal corporation which requires
 an elected official to approve progress payments, "promptly  pay"  shall
 mean  payment  within  forty-five  days,  excluding  legal  holidays, of
 receipt of the requisition unless such requisition is not approvable  in
 accordance with the terms of the contract.
   2.  Payment  by  contractors  to subcontractors. Within seven calendar
 days of the receipt of any payment from the public owner, the contractor
 shall pay each of [his] ITS subcontractors and materialmen the  proceeds
 from  the  payment  representing  the value of the work performed and/or
 materials furnished by the subcontractor and/or materialman and reflect-
 ing  the  percentage  of  the  subcontractor's  work  completed  or  the
 materialman's material supplied in the requisition approved by the owner
 and  based  upon  the  actual value of the subcontract or purchase order
 less an amount necessary to  satisfy  any  claims,  liens  or  judgments
 against  the  subcontractor  or materialman which have not been suitably
 discharged and, WITH REGARD TO SUBCONTRACTORS, less any retained  amount
 as  hereafter  described. Failure by the contractor to make any payment,
 including any remaining amounts of the contract balance  as  hereinafter
 described,  to  any  subcontractor  or materialman within seven calendar
 days of the receipt of any payment from the public owner shall result in
 the commencement and accrual of interest on amounts due to such  subcon-
 tractor  or  materialman for the period beginning on the day immediately
 following the expiration of such seven calendar day period and ending on
 the date on which payment is made by the contractor to such  subcontrac-
 tor  or  materialman.  Such interest shall be the sole responsibility of
 the contractor, and shall be paid at the rate of interest in  effect  on
 the  date  payment  is made by the contractor. Notwithstanding any other
 provision of law to the contrary, interest shall be computed at the rate
 established in paragraph (b) of subdivision one of section seven hundred
 fifty-six-b of the general business law. The contractor shall retain not
 more than five per centum of each payment to the  subcontractor  [and/or
 materialman] except that the contractor may retain in excess of five per
 centum  but  not more than ten per centum of each payment to the subcon-
 S. 1387                             5
 
 tractor provided that prior to entering  into  a  subcontract  with  the
 contractor,  the  subcontractor  is  unable  or  unwilling  to provide a
 performance bond and a labor and material bond both in the  full  amount
 of  the  subcontract  at  the  request of the contractor. THE CONTRACTOR
 SHALL PAY IN FULL, UPON PAYMENT BY THE PUBLIC OWNER, FOR  ALL  MATERIALS
 PERTINENT  TO  THE  PROJECT WHICH HAVE BEEN DELIVERED TO AND ACCEPTED AT
 THE SITE OR OFF-SITE BY A MATERIALMAN AND ARE COVERED BY  A  MANUFACTUR-
 ER'S  WARRANTY,  AND/OR  ARE GRADED TO MEET INDUSTRY STANDARDS. However,
 EXCEPT IN THE CASE OF A MATERIALMAN WHO IS ALSO CONTRACTED TO INSTALL  A
 PRODUCT HE/SHE DELIVERED, the contractor shall retain nothing from those
 payments representing proceeds owed the subcontractor and/or materialman
 from  the  public  owner's  payments to the contractor for the remaining
 amounts of the contract balance as provided in subdivision one  of  this
 section.  If  the  contractor  has  failed  to  submit a requisition for
 payment of the remaining amounts of the contract balance  within  ninety
 days  of  substantial  completion as provided in subdivision one of this
 section, then any clause in the subcontract between the  contractor  and
 the  subcontractor  or  materialman  which  states  that  payment by the
 contractor to such  subcontractor  or  materialman  is  contingent  upon
 payment  by  the owner to the contractor shall be deemed invalid. Within
 seven calendar days of the receipt of payment from the  contractor,  the
 subcontractor and/or materialman shall pay each of [his] ITS subcontrac-
 tors  and  materialmen in the same manner as the contractor has paid the
 subcontractor, including interest as herein  provided  above.    Nothing
 provided  herein  shall  create any obligation on the part of the public
 owner to pay or to see to the payment of any moneys to any subcontractor
 or materialman from any contractor nor shall  anything  provided  herein
 serve  to  create  any relationship in contract or otherwise, implied or
 expressed, between the  subcontractor  or  materialman  and  the  public
 owner.
   §  3.  Section  756-c of the general business law, as added by chapter
 127 of the laws of 2002, is amended to read as follows:
   § 756-c. Retention. 1. By mutual agreement of the relevant parties  an
 owner may retain a reasonable amount of the contract sum as retainage. A
 contractor  or  subcontractor  may  also  retain a reasonable amount for
 retainage so long as the amount does not exceed  the  actual  percentage
 retained  by  the owner. Retainage shall be released by the owner to the
 contractor no later than thirty days after the  final  approval  of  the
 work  under a construction contract. In the event that an owner fails to
 release retainage as required by this  article,  or  the  contractor  or
 subcontractor  fails  to  release a proportionate amount of retainage to
 the relevant parties after receipt of  retainage  from  the  owner,  the
 owner,  contractor,  or  subcontractor,  as  the  case  may be, shall be
 subject to the payment of interest at the rate of one percent per  month
 on the date retention was due and owing.
   2.  NOTWITHSTANDING THE PROVISIONS OF SUBDIVISION ONE OF THIS SECTION,
 NO PORTION OF ANY PAYMENT DUE AND OWING TO A MATERIAL SUPPLIER FOR MATE-
 RIALS WHICH HAVE BEEN DELIVERED, ACCEPTED AND ARE COVERED BY A  MANUFAC-
 TURER'S  WARRANTY,  AND/OR  GRADED  TO  MEET INDUSTRY STANDARDS SHALL BE
 RETAINED BY AN OWNER, CONTRACTOR OR SUBCONTRACTOR.
   § 4. This act shall take effect on the thirtieth day  after  it  shall
 have become a law and shall apply to materials delivered and accepted on
 or after such effective date.