S T A T E O F N E W Y O R K
________________________________________________________________________
6761--A
2021-2022 Regular Sessions
I N A S S E M B L Y
March 29, 2021
___________
Introduced by M. of A. MAMDANI, FORREST, GALLAGHER, MITAYNES, BURDICK,
SIMON, ANDERSON, CARROLL, CLARK, GONZALEZ-ROJAS, O'DONNELL, GOTTFRIED,
ENGLEBRIGHT, EPSTEIN, DINOWITZ, GALEF, COLTON, THIELE, WALKER, BURKE,
KELLES, DAVILA, SEAWRIGHT -- read once and referred to the Committee
on Energy -- committee discharged, bill amended, ordered reprinted as
amended and recommitted to said committee
AN ACT to amend the public service law and the environmental conserva-
tion law, in relation to prohibiting the development of any new major
electric generating facilities that would be powered in whole or in
part by any fossil fuel
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. Short title. This act shall be known and may be cited as
the "clean futures act".
§ 2. Section 160 of the public service law is amended by adding a new
subdivision 10 to read as follows:
10. "FOSSIL FUEL" MEANS COAL, PETROLEUM PRODUCTS, AND FUEL GASES.
"COAL" SHALL INCLUDE BITUMINOUS COAL, ANTHRACITE COAL, AND LIGNITE.
"FUEL GASES" SHALL INCLUDE BUT NOT BE LIMITED TO METHANE, NATURAL GAS,
LIQUEFIED NATURAL GAS, AND MANUFACTURED FUEL GASES. "PETROLEUM PRODUCTS"
SHALL INCLUDE ALL PRODUCTS REFINED OR REREFINED FROM SYNTHETIC OR CRUDE
OIL OR OIL EXTRACTED FROM OTHER SOURCES, INCLUDING NATURAL GAS LIQUIDS.
PROVIDED THAT NOTHING IN THIS SUBDIVISION SHALL AFFECT THE EXCLUSION FOR
PUBLIC UTILITY SERVICES SET FORTH IN SUBDIVISION TWO OF THIS SECTION.
§ 3. Section 162 of the public service law is amended by adding a new
subdivision 6 to read as follows:
6. (A) NOTWITHSTANDING ANY OTHER PROVISION OF LAW, RULE OR REGULATION,
BEGINNING UPON THE EFFECTIVE DATE OF THIS SUBDIVISION THE BOARD SHALL
NOT ISSUE A CERTIFICATE FOR ANY MAJOR ELECTRIC GENERATING FACILITY THAT
WOULD BE POWERED IN WHOLE OR IN PART BY ANY FOSSIL FUEL.
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD10500-07-1
A. 6761--A 2
(B) NOTWITHSTANDING PARAGRAPH (A) OF THIS SUBDIVISION, THE BOARD MAY
ISSUE A CERTIFICATE FOR A MAJOR ELECTRIC GENERATING FACILITY POWERED IN
WHOLE OR IN PART BY ANY FOSSIL FUEL IF BOTH OF THE FOLLOWING CONDITIONS
ARE MET:
(I) THE DEVELOPER OF SUCH MAJOR ELECTRIC GENERATING FACILITY SHALL
PROVIDE TO THE BOARD, THE COMMISSION, AND THE COMMISSIONER OF ENVIRON-
MENTAL CONSERVATION, AN ATTESTATION IN WRITING, SIGNED BY BOTH NEW YORK
INDEPENDENT SYSTEM OPERATOR AND THE APPROPRIATE NEW YORK TRANSMISSION
OWNER OR PUBLIC AUTHORITY, ATTESTING TO:
(1) THE EXISTENCE OF A RELIABILITY NEED. FOR THE PURPOSES OF THIS
SUBDIVISION, A "RELIABILITY NEED" MEANS AN ELECTRICITY SYSTEM NEED,
WHICH IF UNMET WOULD RESULT IN A VIOLATION OF A NORTH AMERICAN ELECTRIC
RELIABILITY CORPORATION MANDATORY STANDARD;
(2) THE UNAVAILABILITY OF EITHER LOCAL OR BULK TRANSMISSION SYSTEM
UPGRADES THAT WOULD ADDRESS SUCH RELIABILITY NEED; AND
(3) SUCH MAJOR ELECTRIC GENERATING FACILITY WOULD RESOLVE SUCH RELI-
ABILITY NEED; AND
(II) THE DEVELOPER OF SUCH MAJOR ELECTRIC GENERATING FACILITY SHALL
DEMONSTRATE TO THE SATISFACTION OF THE BOARD, THE COMMISSION, AND THE
COMMISSIONER OF ENVIRONMENTAL CONSERVATION THAT THE EXISTING RELIABILITY
NEED CANNOT BE ADDRESSED WITHIN AN APPROPRIATE TIME FRAME BY ANY COMBI-
NATION OF TRANSMISSION, ENERGY STORAGE, ZERO CARBON ELECTRIC GENERATION,
DEMAND RESPONSE, AND/OR ENERGY EFFICIENCY.
(C) ANY WRITTEN COMMUNICATION BETWEEN AN APPLICANT AND THE BOARD
CONCERNING A PROPOSED MAJOR ELECTRIC GENERATING FACILITY SHALL BE MADE
PUBLICLY AVAILABLE ON THE DEPARTMENT'S WEBSITE.
§ 4. Section 172 of the public service law is amended by adding two
new subdivisions 3 and 4 to read as follows:
3. THE DEPARTMENT OF ENVIRONMENTAL CONSERVATION SHALL NOT ISSUE ANY
PERMIT OTHERWISE AUTHORIZED PURSUANT TO SUBDIVISION ONE OF THIS SECTION,
OR ISSUED PURSUANT TO SECTION 19-0311 OF THE ENVIRONMENTAL CONSERVATION
LAW, FOR ANY MAJOR ELECTRIC GENERATING FACILITY THAT WOULD BE POWERED IN
WHOLE OR IN PART BY ANY FOSSIL FUEL, UNLESS THE DEVELOPER OF SUCH MAJOR
ELECTRIC GENERATING FACILITY HAS SATISFIED THE PROVISIONS OF SUBPARA-
GRAPHS (I) AND (II) OF PARAGRAPH (B) OF SUBDIVISION SIX OF SECTION ONE
HUNDRED SIXTY-TWO OF THIS ARTICLE.
4. ANY WRITTEN COMMUNICATION BETWEEN AN APPLICANT FOR A PERMIT PURSU-
ANT TO SUBDIVISION ONE OF THIS SECTION AND THE DEPARTMENT OF ENVIRON-
MENTAL CONSERVATION SHALL BE MADE PUBLICLY AVAILABLE ON THE DEPARTMENT
OF CONSERVATION'S WEBSITE.
§ 5. Section 19-0311 of the environmental conservation law is amended
by adding a new subdivision 6 to read as follows:
6. NO PERMIT SHALL BE ISSUED UNDER THIS SECTION THAT WOULD BE IN
VIOLATION OF SUBDIVISION THREE OF SECTION ONE HUNDRED SEVENTY-TWO OF THE
PUBLIC SERVICE LAW. ANY WRITTEN COMMUNICATIONS BETWEEN AN APPLICANT FOR
SUCH A PERMIT AND THE DEPARTMENT SHALL BE MADE PUBLICLY AVAILABLE ON THE
DEPARTMENT'S WEBSITE.
§ 6. This act shall take effect immediately.