tricity rates increased 13 percent in 2025, largely driven by the devel-
opment of data centers.
8. A tripling of data centers nationwide would require the equivalent
water usage of 18.5 million households just for cooling the servers.
9. Data centers convert agricultural and other non-industrial land to
industrial usage, removing farmland, woodland, and other resources while
driving up land values and property taxes.
10. The computing hardware used to run artificial intelligence (AI),
including microchips and processing, memory, and storage components has
a lifespan of 2-5 years and is regularly replaced with updated versions.
As a result, the current AI boom will be responsible for generating up
to 5 million tons of e-waste annually by 2030.
§ 2. The environmental conservation law is amended by adding a new
article 31 to read as follows:
ARTICLE 31
MORATORIUM ON DATA CENTER PERMIT ISSUANCE
SECTION 31-0101. DEFINITIONS.
31-0103. MORATORIUM ON DATA CENTER PERMIT ISSUANCE.
31-0105. GENERIC ENVIRONMENTAL IMPACT STATEMENT.
31-0107. ISSUANCE OF REGULATIONS.
§ 31-0101. DEFINITIONS.
FOR THE PURPOSES OF THIS ARTICLE, THE FOLLOWING TERMS SHALL HAVE THE
FOLLOWING MEANINGS:
1. "DATA CENTER" SHALL MEAN ALL BUILDINGS, EQUIPMENT, STRUCTURES,
INFRASTRUCTURE WITHIN AN EXISTING STRUCTURE, AND OTHER STATIONARY ITEMS,
SUCH AS SERVER RACKS, THAT ARE LOCATED ON A SINGLE SITE OR ON CONTIG-
UOUS, ADJACENT, OR OTHERWISE CONNECTED SITES, AND THAT ARE OWNED OR
OPERATED BY THE SAME ENTITY OR BY ANY ENTITY WHO CONTROLS, IS CONTROLLED
BY, OR IS UNDER COMMON CONTROL BY SUCH ENTITY, REGARDLESS OF WHETHER THE
DATA CENTER IS A SINGLE-OCCUPANT SITE OR MULTI-OCCUPANT SITE, THAT IS
CAPABLE OF USING TWENTY MEGAWATTS OF ELECTRICITY OR MORE AND IS DESIGNED
OR INTENDED TO BE PRIMARILY ENGAGED IN DATA PROCESSING, DATA STORAGE,
DATA TRANSPORT, WEB HOSTING, WEB STREAMING SUPPORT, OR OTHER SERVICES
DESCRIBED UNDER CODE 518210 OF THE 2022 NORTH AMERICAN INDUSTRY CLASSI-
FICATION SYSTEM.
2. "CONTROL" (INCLUDING THE TERMS "CONTROLLED BY" AND "UNDER COMMON
CONTROL WITH") MEANS THE POSSESSION, DIRECT OR INDIRECT, OF THE POWER TO
DIRECT OR CAUSE THE DIRECTION OF THE MANAGEMENT AND POLICIES OF AN ENTI-
TY, WHETHER THROUGH THE OWNERSHIP OF VOTING SECURITIES, BY CONTRACT, OR
OTHERWISE.
3. "ELECTRIC CORPORATION" SHALL HAVE THE SAME MEANING GIVEN TO SUCH
TERM IN SUBDIVISION THIRTEEN OF SECTION TWO OF THE PUBLIC SERVICE LAW.
4. "GAS CORPORATION" SHALL HAVE THE SAME MEANING GIVEN TO SUCH TERM IN
SUBDIVISION ELEVEN OF SECTION TWO OF THE PUBLIC SERVICE LAW.
5. "WATER-WORKS CORPORATION" SHALL HAVE THE SAME MEANING GIVEN TO SUCH
TERM IN SUBDIVISION TWENTY-SEVEN OF SECTION TWO OF THE PUBLIC SERVICE
LAW.
§ 31-0103. MORATORIUM ON DATA CENTER PERMIT ISSUANCE.
NO NEW PERMITS OF ANY KIND MAY BE ISSUED BY THE STATE OR ANY GOVERN-
MENTAL AGENCY OR POLITICAL SUBDIVISION OR PUBLIC BENEFIT CORPORATION OF
THE STATE, FOR THE SITING, CONSTRUCTION, OR COMMENCEMENT OF OPERATION OF
A DATA CENTER PRIOR TO NINETY DAYS AFTER THE DEPARTMENT SHALL HAVE
ISSUED REGULATIONS PURSUANT TO SECTION 31-0107 OF THIS ARTICLE AND THE
PUBLIC SERVICE COMMISSION SHALL HAVE TAKEN ALL ACTIONS REQUIRED PURSUANT
TO SECTION SIXTY-SIX-X OF THE PUBLIC SERVICE LAW.
§ 31-0105. GENERIC ENVIRONMENTAL IMPACT STATEMENT.
A. 10141 3
1. THE DEPARTMENT, IN CONSULTATION WITH THE DEPARTMENT OF PUBLIC
SERVICE AND THE FEDERALLY DESIGNATED BULK SYSTEM OPERATOR, SHALL
PREPARE, PURSUANT TO ARTICLE EIGHT OF THIS CHAPTER, A GENERIC ENVIRON-
MENTAL IMPACT STATEMENT ON DATA CENTER DEVELOPMENT IN THIS STATE.
2. THE GENERIC ENVIRONMENTAL IMPACT STATEMENT SHALL CONSIST OF A STUDY
OF, AND RECOMMENDED REGULATORY OR LEGISLATIVE ACTION RELATING TO,
MATTERS INCLUDING, BUT NOT LIMITED TO:
A. THE NUMBER, SIZE IN ACREAGE, CURRENT AND MAXIMUM GW CAPACITY, AND
LOCATION OF CURRENT DATA CENTERS IN THE STATE, ACTIVE PROPOSALS FOR NEW
DATA CENTERS, AND PROJECTIONS FOR FUTURE GROWTH OF DATA CENTERS.
B. ELECTRICITY CONSUMPTION BY DATA CENTERS, INCLUDING:
I. THE AMOUNT OF ELECTRICITY USED BY DATA CENTERS WITHIN THE STATE;
II. IDENTIFICATION OF THE GENERATION SOURCES FOR SUCH ELECTRICITY,
INCLUDING THE SHARE THAT COMES FROM FOSSIL FUEL GENERATION, NUCLEAR
GENERATION, RENEWABLE ENERGY SYSTEMS AS DEFINED IN PARAGRAPH (B) OF
SUBDIVISION ONE OF SECTION SIXTY-SIX-P OF THE PUBLIC SERVICE LAW, AND
GENERATION IMPORTED FROM OUTSIDE OF THE STATE;
III. THE IMPACT OF DATA CENTER DEVELOPMENT ON MONTHLY ELECTRICITY AND
GAS RATES FOR RESIDENTIAL CONSUMERS, COMMERCIAL CONSUMERS, AND INDUS-
TRIAL CONSUMERS, BROKEN DOWN BY RATE CLASS AND TYPE, AS WELL AS PROJEC-
TIONS FOR THE CHANGES TO THESE AMOUNTS FOR BOTH THE PROPOSED AND
PROJECTED GROWTH OF DATA CENTERS IN THE STATE;
IV. THE IMPACT OF DATA CENTER DEVELOPMENT ON THE BULK SYSTEM OPERATOR
INTERCONNECTION QUEUE;
V. THE IMPACT OF DATA CENTER DEVELOPMENT ON TRANSMISSION DEVELOPMENT,
TRANSMISSION CONSTRAINTS, AND OTHER ISSUES RELATING TO GRID RELIABILITY
THROUGHOUT ALL LOAD ZONES IDENTIFIED BY THE BULK SYSTEM OPERATOR; AND
VI. HOW DATA CENTER DEVELOPMENT HAS IMPACTED CAPITAL PLANNING, SPEND-
ING AND MAINTENANCE NEEDS FOR ELECTRIC CORPORATIONS AND GAS CORPO-
RATIONS.
C. WATER CONSUMPTION AND DISCHARGE BY DATA CENTERS, INCLUDING:
I. THE AMOUNT OF WATER USED BY DATA CENTERS FOR COOLING, INCLUDING THE
SOURCES OF SUCH WATER;
II. THE DAILY RATE OF CONSUMPTION OF WATER FROM SUCH SOURCES;
III. THE AMOUNT OF WATER DISCHARGED FROM DATA CENTERS BACK INTO THE
STATE'S WATER RESOURCES;
IV. THE AMOUNT OF WATER CONSUMED BY COOLING SYSTEMS, LOST TO EVAPO-
RATION, OR IN ANYWAY NOT RETURNED TO THE WATERS OF THE STATE;
V. PROJECTIONS FOR THE CHANGES TO THESE AMOUNTS FOR BOTH THE PROPOSED
AND PROJECTED GROWTH OF DATA CENTERS IN THE STATE;
VI. THE IMPACT OF DATA CENTER DEVELOPMENT ON WATER-WORKS CORPORATIONS'
CAPITAL PLANNING, SPENDING, AND MAINTENANCE NEEDS; AND
VII. THE IMPACT OF DATA CENTER DEVELOPMENT ON MONTHLY WATER RATES FOR
RESIDENTIAL CONSUMERS, COMMERCIAL CONSUMERS, AND INDUSTRIAL CONSUMERS,
BROKEN DOWN BY RATE CLASS AND TYPE, AS WELL AS PROJECTIONS FOR THE
CHANGES TO THESE AMOUNTS FOR BOTH THE PROPOSED AND PROJECTED GROWTH OF
DATA CENTERS IN THE STATE.
D. LAND USE FOR DATA CENTERS, INCLUDING:
I. THE TOTAL ACREAGE USED FOR EXISTING DATA CENTERS;
II. THE TYPES AND AMOUNT OF LAND THAT HAVE BEEN REZONED FROM OTHER
ZONING CATEGORIES FOR USE BY DATA CENTERS;
III. THE IMPACT ON LAND VALUES AND PROPERTY TAXES WITHIN A TEN-MILE
RADIUS OF A DATA CENTER;
IV. PROJECTIONS FOR THE CHANGES TO THESE AMOUNTS FOR BOTH THE PROPOSED
AND PROJECTED GROWTH OF DATA CENTERS IN THE STATE; AND
A. 10141 4
V. IMPACTS ON FARMLAND, INCLUDING AN ANALYSIS OF IMPACTS ON PRIME
FARMLAND MINERAL SOIL TYPES 1-4.
E. POLLUTION FROM DATA CENTERS, INCLUDING:
I. THE AMOUNT OF GREENHOUSE GASES EMITTED BY EACH EXISTING DATA CENTER
AND THE CUMULATIVE TOTAL FOR THE STATE EMITTED BY EXISTING, PROPOSED,
AND PROJECTED DATA CENTERS, EXPRESSED IN METRIC TONS OF CARBON DIOXIDE
EQUIVALENT, AS DEFINED IN SECTION 75-0101 OF THIS CHAPTER;
II. THE TYPES AND QUANTITY OF AIR POLLUTANTS EMITTED BY EACH DATA
CENTER AND THE CUMULATIVE TOTAL FOR THE STATE EMITTED BY EXISTING,
PROPOSED, AND PROJECTED DATA CENTERS; AND
III. THE TYPES AND QUANTITY OF WATER POLLUTION PRODUCED BY EACH DATA
CENTER, INCLUDING THERMAL POLLUTION FROM WATER DISCHARGES, AND THE CUMU-
LATIVE TOTAL FOR THE STATE PRODUCED BY EXISTING, PROPOSED, AND PROJECTED
DATA CENTERS; AND
IV. THE LEVEL OF NOISE POLLUTION PRODUCED BY EACH DATA CENTER, WITH
PROJECTIONS FOR PROPOSED AND PROJECTED DATA CENTERS, AT REGULAR INTER-
VALS BEGINNING AT THE PROPERTY LINE OF THE DATA CENTER AND EXTENDING
HALF A MILE.
F. ELECTRONIC WASTE FROM DATA CENTERS, INCLUDING:
I. THE CURRENT VOLUME OF ELECTRONIC WASTE PRODUCED BY DATA CENTERS, BY
WASTE TYPE;
II. THE CURRENT METHODS BEING USED TO DISPOSE OF OR RECYCLE ELECTRONIC
WASTE PRODUCED BY DATA CENTERS;
III. PROJECTIONS FOR THE CHANGES TO THESE AMOUNTS FOR BOTH THE
PROPOSED AND PROJECTED GROWTH OF DATA CENTERS IN THE STATE.
G. A REVIEW OF CURRENT STATUTES AND REGULATIONS ADDRESSING THE ENVI-
RONMENTAL IMPACT OF DATA CENTERS.
3. PROJECTIONS OF FUTURE DATA CENTER GROWTH WITHIN THE STATE MAY BE
BASED SOLELY ON DATA AVAILABLE AS OF THE DATE ON WHICH THIS SECTION
SHALL TAKE EFFECT, AND THE DEPARTMENT MAY CHOOSE TO ACCOUNT FOR ONGOING
CHANGES AND UNCERTAINTY IN GROWTH PROJECTIONS.
4. A DRAFT GENERIC ENVIRONMENTAL IMPACT STATEMENT SHALL BE POSTED ON
THE DEPARTMENT'S WEBSITE AND BE SUBJECT TO AT LEAST ONE HUNDRED TWENTY
DAYS OF PUBLIC COMMENT FROM THE DATE OF ISSUANCE. THE DEPARTMENT OF
ENVIRONMENTAL CONSERVATION SHALL CONDUCT AT LEAST ONE IN-PERSON PUBLIC
HEARING IN EACH OF THE FOLLOWING REGIONS OF THE STATE: WESTERN NEW YORK,
THE FINGER LAKES, THE SOUTHERN TIER, CENTRAL NEW YORK, THE MOHAWK
VALLEY, THE NORTH COUNTRY, THE CAPITAL REGION/HUDSON VALLEY, THE CITY OF
NEW YORK, AND LONG ISLAND, AS DEFINED BY THE EMPIRE STATE DEVELOPMENT
CORPORATION, AND PROVIDE MEANINGFUL OPPORTUNITY FOR COMMENT AT SUCH
HEARINGS.
5. THE DEPARTMENT SHALL ISSUE A FINAL GENERIC ENVIRONMENTAL IMPACT
STATEMENT PURSUANT TO THIS SECTION NO SOONER THAN EIGHTEEN MONTHS AFTER
THIS SECTION SHALL HAVE BECOME A LAW.
§ 31-0107. ISSUANCE OF REGULATIONS.
NO SOONER THAN THREE YEARS AFTER THE EFFECTIVE DATE OF THIS SECTION,
THE DEPARTMENT SHALL ISSUE FINAL NEW OR UPDATED REGULATIONS TO MITIGATE
THE ENVIRONMENTAL IMPACT OF DATA CENTERS. SUCH REGULATIONS SHALL BE
INFORMED BY THE GENERIC ENVIRONMENTAL IMPACT STATEMENT ISSUED PURSUANT
TO SECTION 31-0105 OF THIS ARTICLE, AND SHALL BE DESIGNED, TO THE GREAT-
EST POSSIBLE EXTENT, TO:
1. MINIMIZE ENERGY CONSUMPTION;
2. MINIMIZE EMISSION OF GREENHOUSE GASES AND PRODUCTION OF OTHER AIR,
WATER, AND SOIL POLLUTION;
3. MINIMIZE NOISE POLLUTION;
4. MINIMIZE WATER CONSUMPTION;
A. 10141 5
5. REQUIRE A MINIMUM AMOUNT OF ELECTRICITY USAGE TO BE PROVIDED BY ON-
AND OFF-SITE RENEWABLE ENERGY SYSTEMS, AS DEFINED IN PARAGRAPH (B) OF
SUBDIVISION ONE OF SECTION SIXTY-P OF THE PUBLIC SERVICE LAW, AND ENERGY
STORAGE.
§ 3. The public service law is amended by adding a new section 66-x to
read as follows:
§ 66-X. DATA CENTER RATE IMPACTS. 1. (A) NO LATER THAN EIGHTEEN MONTHS
AFTER THIS SECTION SHALL HAVE BECOME A LAW, THE COMMISSION SHALL ISSUE A
FINAL REPORT ON DATA CENTERS, AS DEFINED IN SECTION 31-0101 OF THE ENVI-
RONMENTAL CONSERVATION LAW, INCLUDING:
(I) THE IMPACT OF DATA CENTERS ON ELECTRICITY AND GAS RATES FOR RESI-
DENTIAL, COMMERCIAL, AND INDUSTRIAL USERS;
(II) HOW DATA CENTER OPERATORS CAN MINIMIZE THE IMPACT OF DATA CENTERS
ON ELECTRICITY AND GAS RATES FOR RESIDENTIAL, COMMERCIAL, AND INDUSTRIAL
USERS WITHOUT ADDITIONAL GOVERNMENT SPENDING;
(III) A REVIEW OF CURRENT STATUTES AND REGULATIONS DESIGNED TO MINI-
MIZE THE IMPACT OF DATA CENTERS ON ELECTRICITY AND GAS RATES FOR RESI-
DENTIAL, COMMERCIAL, AND INDUSTRIAL USERS; AND
(IV) AN EVALUATION OF ACTIONS THE COMMISSION CAN TAKE TO MINIMIZE THE
IMPACT OF DATA CENTERS ON ELECTRICITY AND GAS RATES FOR RESIDENTIAL,
COMMERCIAL, AND INDUSTRIAL USERS, INCLUDING, BUT NOT LIMITED TO, THE
CREATION OF A NEW CUSTOMER CLASSIFICATION FOR DATA CENTERS.
(B) A DRAFT REPORT SHALL BE ISSUED PRIOR TO THE COMPLETION OF THE
FINAL REPORT, WITH SUCH DRAFT REPORT SUBJECT TO AT LEAST ONE HUNDRED
TWENTY DAYS OF PUBLIC COMMENT FROM THE DATE OF ISSUANCE. THE FINAL
REPORT SHALL TAKE INTO CONSIDERATION FEEDBACK SUBMITTED DURING THE
PUBLIC COMMENT PERIOD.
2. NO SOONER THAN THREE YEARS AFTER THE ENACTMENT OF THIS SECTION, THE
COMMISSION SHALL ISSUE ANY ADDITIONAL ORDERS NECESSARY TO MINIMIZE, TO
THE GREATEST POSSIBLE EXTENT, THE IMPACT OF DATA CENTERS, AS DEFINED IN
SECTION 31-0101 OF THE ENVIRONMENTAL CONSERVATION LAW, ON ELECTRICITY
AND GAS RATES FOR RESIDENTIAL, COMMERCIAL, AND INDUSTRIAL USERS, AND TO
ENSURE THAT ALL COSTS ASSOCIATED WITH PROVIDING AND MAINTAINING ELECTRIC
AND GAS SERVICE TO DATA CENTERS, INCLUDING, BUT NOT LIMITED TO, REQUIRE-
MENTS FOR ANY NEW ELECTRICITY GENERATION, TRANSMISSION, AND DISTRIBUTION
INFRASTRUCTURE, COSTS ASSOCIATED WITH INCREASES IN ELECTRICITY WHOLESALE
SUPPLY AND CAPACITY MARKET PRICES, PEAK AND NON-PEAK DEMAND IMPACTS ON
GENERATION SOURCES AND GENERATION CAPACITY NEEDS, AND INCREASES IN
NATURAL GAS AND OIL COMMODITY PRICES, SHALL BE BORNE BY SUCH DATA
CENTER. IN DEVELOPING SUCH NEW ORDER OR ORDERS, THE COMMISSION SHALL BE
INFORMED BY THE GENERIC ENVIRONMENTAL IMPACT STATEMENT ISSUED PURSUANT
TO SECTION 31-0105 OF THE ENVIRONMENTAL CONSERVATION LAW AS WELL AS THE
REPORT ISSUED PURSUANT TO SUBDIVISION ONE OF THIS SECTION.
§ 4. This act shall take effect on the thirtieth day after it shall
have become a law, and shall apply to all permits pending or filed after
such effective date.