S T A T E O F N E W Y O R K
________________________________________________________________________
4588
2025-2026 Regular Sessions
I N A S S E M B L Y
February 4, 2025
___________
Introduced by M. of A. CUNNINGHAM -- read once and referred to the
Committee on Energy
AN ACT to amend the public service law, in relation to New York state
renewable electric generation pilot programs
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. The public service law is amended by adding a new section
73-b to read as follows:
§ 73-B. NEW YORK STATE RENEWABLE ELECTRIC GENERATION PILOT PROGRAMS.
1. THE COMMISSION SHALL ESTABLISH NEW YORK STATE RENEWABLE ELECTRIC
GENERATION PILOT PROGRAMS TO AUTHORIZE THE DEVELOPMENT OF UP TO THREE
HUNDRED MEGAWATTS OF RENEWABLE ELECTRIC CAPACITY STATEWIDE, IN ORDER TO
STIMULATE THE GROWTH OF CLEAN, AFFORDABLE, AND RELIABLE SOURCES OF ENER-
GY AND TO FOSTER NEW PARTNERSHIPS BETWEEN ELECTRIC CORPORATIONS, ENERGY
PRODUCERS AND ENERGY CUSTOMERS IN NEW YORK STATE.
2. (A) THE COMMISSION SHALL OVERSEE THE IMPLEMENTATION OF THE PILOT
PROGRAMS AND SHALL DIRECT ELECTRIC CORPORATIONS TO BUILD OR CAUSE TO BE
BUILT RENEWABLE ENERGY FACILITIES TO BE FINANCED UNDER TERMS ESTABLISHED
THROUGH AN ORDER OF THE COMMISSION WHICH SHALL AUTHORIZE CAPITAL AND
OPERATING COSTS TO BE RECOVERED IN THE CORPORATIONS RATE BASE AND TO
EARN A REASONABLE RETURN OVER A PERIOD TO BE DETERMINED BY THE COMMIS-
SION, PROVIDED THAT THE CORPORATION SHALL, AT MINIMUM, PROVIDE THE
COMMISSION WITH THE FOLLOWING:
(I) A DETAILED DESCRIPTION AND ECONOMIC EVALUATION OF THE PROPOSED
INVESTMENT;
(II) A DISCUSSION OF THE COSTS, BENEFITS, AND RISKS OF THE PROPOSAL,
INCLUDING AN ANALYSIS OF THE COSTS, BENEFITS, AND RATE IMPLICATIONS TO
THE PARTICIPATING CUSTOMERS, TO THE COMPANY'S DEFAULT SERVICE CUSTOMERS,
AND TO THE UTILITY'S DISTRIBUTION CUSTOMERS;
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD06495-01-5
A. 4588 2
(III) A DESCRIPTION OF ANY EQUIPMENT OR INSTALLATION SPECIFICATIONS,
SOLICITATIONS, AND PROCUREMENTS IT HAS IMPLEMENTED OR INTENDS TO IMPLE-
MENT;
(IV) A SHOWING THAT IT HAS MADE REASONABLE EFFORTS TO INVOLVE LOCAL
BUSINESSES IN ITS PROGRAM;
(V) EVIDENCE OF COMPLIANCE WITH ALL APPLICABLE EMISSION LIMITATIONS;
AND
(VI) A COPY OF ANY CUSTOMER CONTRACTS OR AGREEMENTS TO BE EXECUTED AS
PART OF THE PROGRAM.
(B) RENEWABLE GENERATION FACILITIES ELIGIBLE TO BE CONSTRUCTED AND
FINANCED UNDER THE NEW YORK STATE RENEWABLE ELECTRIC GENERATION PILOT
PROGRAMS SHALL:
(I) GENERATE ELECTRICITY THROUGH USE OF THE FOLLOWING TECHNOLOGIES:
SOLAR; WIND; PHOTOVOLTAICS; TIDAL; GEOTHERMAL; AND FUEL CELLS; OR
(II) GENERATE ELECTRICITY THROUGH LOW-IMPACT, RUN-OF-RIVER HYDROELEC-
TRIC ELECTRIC GENERATING EQUIPMENT WITH CAPACITY UP TO THIRTY MEGAWATTS
WITH NO NEW STORAGE IMPOUNDMENT;
(III) BE MANUFACTURED, INSTALLED AND OPERATED IN ACCORDANCE WITH
APPLICABLE GOVERNMENT AND INDUSTRY STANDARDS;
(IV) CONNECT TO THE ELECTRIC SYSTEM AND OPERATED IN PARALLEL WITH AN
ELECTRIC CORPORATION'S TRANSMISSION AND DISTRIBUTION FACILITIES;
(V) OPERATE IN COMPLIANCE WITH ANY STANDARDS AND REQUIREMENTS ESTAB-
LISHED BY THE COMMISSION; AND
(VI) BE LOCATED WITHIN THE STATE, INCLUDING FACILITIES THAT CONSIST OF
CUSTOMER-OWNED OR LEASED GENERATORS.
(C) AUTHORIZE ELECTRIC CORPORATIONS TO OWN AN EQUITY INTEREST IN SUCH
FACILITIES AND ALLOW PARTNERSHIPS WITH INDEPENDENT POWER PRODUCERS,
DEVELOPERS, AND/OR CUSTOMER-OWNED OR LEASED GENERATORS.
§ 2. The public service commission shall provide an annual report on
or before the first day of June to the governor, the temporary president
of the senate, the speaker of the assembly, the minority leader of the
senate, and the minority leader of the assembly reporting the progress
of their efforts and the effects of the program on the environment and
public. Such report shall identify each facility participating in the
pilot project and shall include, but not be limited to, information on
each energy source or sources used for generation at such facility; the
sum capacity, in megawatts, of all electrical generating equipment used
by the facility; the date the facility will begin or has begun generat-
ing electricity; and the number and category of customer-owned or leased
generators.
§ 3. This act shall take effect immediately; provided, however, that
not later than the one hundred eightieth day after this act shall have
become a law, the public service commission shall have in place a
competitive process which shall be open to electric corporations.