S T A T E O F N E W Y O R K
________________________________________________________________________
2254
2025-2026 Regular Sessions
I N S E N A T E
January 16, 2025
___________
Introduced by Sen. COMRIE -- read twice and ordered printed, and when
printed to be committed to the Committee on Procurement and Contracts
AN ACT to amend the state finance law, in relation to damages to
contracts occasioned by delay
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. The state finance law is amended by adding a new section
138-b to read as follows:
§ 138-B. DAMAGES OCCASIONED BY DELAY. 1. FOR PURPOSES OF THIS SECTION
THE FOLLOWING TERMS SHALL HAVE THE FOLLOWING MEANINGS:
(A) "STATE AGENCY" SHALL MEAN ANY STATE DEPARTMENT, BOARD, BUREAU,
COMMISSION, DIVISION, OFFICE, COUNCIL, OR STATE COMMITTEE OR ANY STATE
AUTHORITY AS DEFINED IN SUBDIVISION ONE OF SECTION TWO OF THE PUBLIC
AUTHORITIES LAW. SUCH TERM SHALL NOT INCLUDE THE LEGISLATURE OR JUDICI-
ARY.
(B) "CONTRACT" SHALL MEAN ANY AGREEMENT AWARDED BY A STATE AGENCY FOR
THE DESIGN, CONSTRUCTION, RECONSTRUCTION, DEMOLITION, ALTERATION, REPAIR
OR IMPROVEMENT OF ANY PUBLIC WORKS PROJECT.
(C) "DELAY" SHALL MEAN ANY DELAY, DISRUPTION, INTERFERENCE, INEFFI-
CIENCIES, IMPEDANCE, HINDRANCE OR ACCELERATION IN THE PERFORMANCE OF THE
CONTRACT WHICH CAUSES DAMAGES TO BE INCURRED BY A CONTRACTOR.
(D) "CLAIM" SHALL MEAN A REQUEST FOR ADDITIONAL COSTS ONLY FROM THE
FOLLOWING CAUSES:
(I) THE FAILURE OF THE STATE AGENCY TO TAKE REASONABLE MEASURES TO
COORDINATE AND PROGRESS THE WORK;
(II) EXTENDED DELAYS ATTRIBUTABLE TO THE STATE AGENCY IN THE REVIEW OR
ISSUANCE OF ORDERS-ON-CONTRACT OR FIELD ORDERS, IN SHOP DRAWING REVIEWS
AND APPROVALS OR AS A RESULT OF THE CUMULATIVE IMPACT OF MULTIPLE ORDERS
ON CONTRACT, WHICH CONSTITUTE A QUALITATIVE CHANGE TO THE PROJECT WORK
AND WHICH HAVE A VERIFIABLE IMPACT ON PROJECT COSTS; OR
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD04916-01-5
S. 2254 2
(III) THE UNAVAILABILITY OF THE SITE FOR SUCH AN EXTENDED PERIOD OF
TIME WHICH SIGNIFICANTLY AFFECTS THE SCHEDULED COMPLETION OF THE
CONTRACT.
2. ALL CONTRACTS MADE AND AWARDED SHALL CONTAIN A CLAUSE WHICH ALLOWS
A CONTRACTOR TO MAKE A CLAIM FOR ADDITIONAL COSTS ARISING FROM DELAY IN
THE PERFORMANCE OF A CONTRACT IF SUCH DELAY IS CAUSED BY A MATERIAL ACT
OR OMISSION OF THE STATE AGENCY.
3. THE CONTRACTOR SHALL PROVIDE A NOTICE OF CLAIM OF AN ANTICIPATED
CLAIM FOR DELAY TO A STATE AGENCY BY PERSONAL SERVICE OR CERTIFIED MAIL
NO MORE THAN FIFTEEN DAYS AFTER SUCH CONTRACTOR KNEW THE FACTS WHICH
FORM THE BASIS OF THE CLAIM. THE STATE AGENCY SHALL ACKNOWLEDGE RECEIPT
OF THE NOTICE, IN WRITING, WITHIN FIVE DAYS. SUCH NOTICE SHALL AT A
MINIMUM PROVIDE A DESCRIPTION OF ANY OPERATIONS THAT WERE, ARE BEING OR
WILL BE DELAYED, AND THE DATE OR DATES AND REASONS FOR THE DELAY. IN NO
CASE SHALL ORAL NOTICE CONSTITUTE NOTICE PURSUANT TO THIS SECTION OR BE
DEEMED TO CONSTITUTE A WAIVER OF THE WRITTEN NOTICE REQUIREMENT. FOR
THE PURPOSES OF THIS SECTION, FAILURE TO PROVIDE SUCH NOTICE SHALL BE
CONSIDERED TO HAVE PREJUDICED THE STATE AGENCY.
4. FAILURE BY A CONTRACTOR TO ADEQUATELY PROGRESS THE COMPLETION OF
WORK SHALL BE CONSIDERED IN DETERMINING THE CAUSES OF DELAY. FOR ANY
CLAIM ASSERTED PURSUANT TO THIS TITLE, THE CONTRACTOR SHALL KEEP
DETAILED WRITTEN RECORDS OF THE COSTS AND SHALL MAKE THEM AVAILABLE FOR
THE PURPOSES OF AUDIT AND REVIEW. FAILURE TO PROVIDE THE REQUIRED WRIT-
TEN NOTICE OR TO MAINTAIN AND FURNISH RECORDS OF THE COSTS OF SUCH
CLAIMS SHALL CONSTITUTE A WAIVER OF THE CLAIM.
5. THE FOLLOWING INFORMATION SHALL BE PROVIDED BY THE CONTRACTOR UPON
REQUEST OF A STATE AGENCY IF NOT PREVIOUSLY SUPPLIED:
(A) A DESCRIPTION OF THE OPERATIONS THAT WERE DELAYED, THE REASONS FOR
THE DELAY AND AN EXPLANATION OF HOW THEY WERE DELAYED;
(B) A DETAILED FACTUAL STATEMENT OF THE CLAIM PROVIDING ALL NECESSARY
DATES, LOCATIONS AND ITEMS OF WORK AFFECTED BY THE CLAIM;
(C) THE DATE ON WHICH ACTIONS RESULTING IN THE CLAIM OCCURRED OR
CONDITIONS RESULTING IN THE CLAIM BECAME EVIDENT;
(D) THE NAMES, FUNCTIONS AND ACTIVITIES OF EACH CONTRACTOR INVOLVED
IN, OR KNOWLEDGEABLE ABOUT FACTS THAT GAVE RISE TO SUCH CLAIM;
(E) THE IDENTIFICATION OF ANY PERTINENT DOCUMENTS, AND THE SUBSTANCE
OF ANY MATERIAL ORAL COMMUNICATION RELATING TO SUCH CLAIM;
(F) THE AMOUNT OF ADDITIONAL COMPENSATION SOUGHT; AND
(G) IF AN EXTENSION OF TIME IS ALSO REQUESTED, THE SPECIFIC NUMBER OF
DAYS FOR WHICH IT IS SOUGHT AND THE BASIS FOR SUCH REQUEST AS DETERMINED
BY AN ANALYSIS OF THE CONSTRUCTION PROGRESS SCHEDULE.
6. WHEN SUBMITTING ANY CLAIM, THE CONTRACTOR SHALL CERTIFY IN WRITING
AND UNDER OATH THAT THE SUPPORTING DATA IS ACCURATE AND COMPLETE TO
THEIR BEST KNOWLEDGE OR BELIEF, AND THAT ANY AMOUNT DEMANDED REFLECTS,
IN GOOD FAITH, WHAT THEY BELIEVE TO BE THE STATE AGENCY'S LIABILITY.
§ 2. This act shall take effect on the one hundred eightieth day after
it shall have become a law and shall apply to all contracts entered into
on and after such date.